2026 renovation price list: build an itemised budget

Select the required scope and quantity according to 8 categories and 117 company project price items, and check the preliminary subtotal and non-inclusive conditions item by item. No query is automatically created or data is transmitted, and the result is not a formal all-inclusive quote.

DemolitionDismantling, cleaning and mud removal11 items
A01

Remove wall or floor tiles

Remove the old tiles down to the cement bed, provide basic protection and bag the debris for temporary storage. Firmly bonded tiles or removal down to the concrete cost an extra HK$10 per sq ft.

sq ft · HK$30 per sq ft
A02

Break out floor tiles and screed down to concrete

Remove the tiles and cement screed to expose the concrete, then clear the rubble. Deep breaking-out and work in recessed slabs are quoted separately.

sq ft · HK$52 per sq ft
A03

Strip painted walls back to concrete

Remove the existing paint and plaster to expose the concrete for re-rendering.

sq ft · HK$18 per sq ft
A04

Remove a non-load-bearing masonry wall

Remove the partition and make good the junctions with the walls, floor and ceiling. Confirm that the wall is non-structural before starting and follow Buildings Department minor works requirements where applicable.

sq ft · HK$69 per sq ft · Minimum spending HK$2,800
A05

Remove a plasterboard partition

Remove the plasterboard and framing and clear the fixing points.

sq ft · HK$34 per sq ft · Minimum spending HK$1,850
A06

Remove kitchen cabinets or a bathroom vanity

Take out base units, wall cabinets and worktops and make the water and electrical points safe. Measured by the horizontal length of the cabinets.

linear ft · HK$170 per linear ft
A07

Remove a built-in wardrobe or tall cabinet

Remove the cabinet, back panel and trims and make good the wall edges. Measured by the front area of each cabinet (height × width) and the number of cabinets, with a minimum of HK$740 per cabinet.

sq ft · HK$61 per sq ft · Minimum spend HK$740
A08

Remove timber flooring

Remove the flooring, backing and adhesive and clean the floor. A backing board or thick adhesive adds HK$5 per sq ft.

sq ft · HK$22 per sq ft
A09

Kitchen strip-out and removal (one room)

Strip out wall tiles, floor tiles and cabinets, including carrying the debris out. The scope for an open-plan kitchen is assessed individually.

room · HK$9,950 per room
A10

Bathroom strip-out and removal (one room)

Strip out wall and floor tiles, sanitaryware and vanity cabinets, including carrying the debris out.

room · HK$9,950 per room
A11

Construction waste removal (per truckload)

Includes carrying debris downstairs, trucking, lawful disposal and government disposal charges. Small jobs can be charged by the bag, with a minimum of HK$2,000. A09 and A10 already include carrying debris out. Any additional waste removal depends on the actual scope.

truckload · HK$4,200 per truckload
Mud water, waterproofing, tilingArtificial base material; facing bricks are extra (unless otherwise noted)19 items
B01

Cement-sand wall rendering

Prepare the surface, set guides and apply and level cement-sand render.

sq ft · HK$43 per sq ft · Minimum spending HK$2,350
B02

Floor screeding and levelling

Level the floor with cement-sand screed and form falls to the drain in wet areas. Differences over 30 mm are assessed separately.

sq ft · HK$22 per sq ft · Minimum spending HK$1,850
B03

Build a masonry partition and render both sides

Build a lightweight-block or red-brick partition with wall ties and render both faces.

sq ft · HK$93 per sq ft · Minimum spending HK$3,700
B04

Convert a painted wall to a rendered surface

Strip the existing finish and apply cement-sand render to prepare the wall for tiling.

sq ft · HK$26 per sq ft
B05

Convert a tiled wall to a paint-ready surface

Remove the tiles and render and level the wall. Painting is charged separately under the E items.

sq ft · HK$31 per sq ft
B06

Mason on a day rate

A day rate for general repairs or small works. Materials are charged at cost.

day · HK$2,700 per day
C01

SikaTop® Seal-107 waterproofing (by area)

Clean and dampen the substrate, reinforce internal corners and pipe penetrations and apply two coats in crossing directions. A third coat costs HK$10 extra per sq ft.

sq ft · HK$39 per sq ft · Minimum spending HK$2,350
C02

Bathroom waterproofing (one room, about 30–40 sq ft)

Two coats of Sika 107 across the whole floor, up the walls to 6 ft and to full height in the shower. Includes a 24-hour flood test. Area above 40 sq ft is charged under C01.

room · HK$4,850 per room
C03

Kitchen waterproofing (one room)

Apply two coats of Sika 107 across the floor, extend 150 mm up at the wall-to-floor junction and reinforce the sink area.

room · HK$4,300 per room
C04

Flood test (24–48 hours)

Seal the floor drain, add 2–3 cm of water, monitor the level and the ceiling below, and take photos. A test is already included in the per-room bathroom waterproofing item.

occasion · HK$1,400 per test
C05

Bathroom strip-out and new waterproofing

Strip the tiles back to the substrate, repair it, apply two waterproofing coats and flood-test. Tiling is excluded. C01, C02, C04 and A10 are not charged again for the same bathroom work.

room · HK$13,000 per room
D01

Floor tiling (straight-laid tiles up to 600 × 600 mm)

Set out the tile layout, bed the tiles with adhesive or adhesive mortar, grout the joints and finish the edges.

sq ft · HK$78 per sq ft · Minimum spending HK$3,250
D02

Wall tiling (straight-laid tiles up to 600 × 600 mm)

Set out the tiles, bed them with tile adhesive, grout the joints and finish the external corners.

sq ft · HK$78 per sq ft · Minimum spending HK$3,250
D03

Wood-effect plank tiling

Stagger and align the joints and cut and finish the edges. Herringbone or chevron patterns attract the diagonal-layout surcharge.

sq ft · HK$98 per sq ft · Minimum spending HK$3,250
D04

Large-format tiling (600 × 1,200 or 800 × 800 mm)

Apply adhesive to the substrate and tile backs, use levelling clips and allow for two-person handling.

sq ft · HK$120 per sq ft · Minimum spending HK$3,700
D05

Extra-large tiles or sintered slabs (750 × 1,500 mm and above)

Use suction lifters, adhesive on both surfaces, levelling clips and specialist cutting. The access route and lift dimensions need checking.

sq ft · HK$150 per sq ft · Minimum spending HK$4,650
D06

Small, mosaic or hexagonal tiling

Align each tile and grout the narrow joints.

sq ft · HK$130 per sq ft · Minimum spending HK$3,250
D08

Epoxy grouting

Clean the joints, apply epoxy grout and clean the tile faces.

sq ft · HK$21 per sq ft · Minimum spending HK$1,400
D09

Tiled shower base with kerb

Build the shower base to site dimensions, with waterproofing and tiling.

set · HK$2,050 per set
PaintingCalculated based on the expanded area of walls and ceilings6 items
E01

Full paint strip, skim coat, prime, sand and repaint

Strip the old paint back to plaster, apply moisture-resistant primer, skim 2–3 times, sand and apply 2–3 finish coats. Suitable for peeling or mould-affected walls, or after the underlying leak has been fixed. The standard interior finish is Nippon Paint Super 5-in-1, second generation.

sq ft · HK$39 per sq ft · Minimum spending HK$7,450 · Minimum 1 square foot
E02

Local filler repairs, moisture-resistant primer, sanding and repainting

Remove loose patches, fill cracks and chips, apply moisture-resistant primer, sand and apply two finish coats. For generally sound walls with local cracking. The standard interior finish is Nippon Paint Super 5-in-1, second generation.

sq ft · HK$21 per sq ft · Minimum spending HK$4,650 · Minimum 1 square foot
E03

Repaint sound walls throughout the flat

Clean the walls, fill nail holes, lightly sand and apply two finish coats. For sound existing walls. The standard finish is Nippon Paint Super 5-in-1, second generation. An extra coat to cover a dark colour costs HK$4 per sq ft.

sq ft · HK$12 per sq ft · Minimum spending HK$3,700 · Minimum 1 square foot
E04

Paint a timber door and frame

Sand, fill nail holes, prime and apply the finish paint.

set · HK$1,650 per set
E05

Local mould treatment and repainting

Treat the mould and apply mould-resistant primer and finish paint. Tracing the source of a leak is extra.

wall face · HK$1,250 per wall face
E06

Decorative or textured paint finish

Prime, form the texture with a trowel or roller and apply a protective topcoat. Materials vary by brand.

sq ft · HK$110 per sq ft · Minimum spending HK$2,800
Plumbing and sanitary ware installationWater supply and sanitary ware installation13 items
G01

Open up and inspect supply and waste pipes

Open the specified area, inspect, report with photos and make good the opening. Pipe alterations are extra.

items · HK$930 per item
G02

Relocate a hot or cold water supply point

Chase the wall, install new copper pipe, pressure-test and reinstate the render.

point · HK$1,700 per point
G03

Full hot and cold water pipework for one kitchen

Water supply and drainage for the sink and washing machine, with pressure testing.

items · HK$13,300 per item
G04

Full hot and cold water pipework for one bathroom

Water supply and drainage connections for the shower, toilet and basin, with pressure testing.

items · HK$13,300 per item
G05

Replace supply and waste pipes throughout the kitchen and bathroom

Replace the kitchen and bathroom pipework and pressure-test. Rebuilding concealed pipework and chasing new routes are assessed separately.

items · HK$22,300 per item
G06

Install a washing-machine drain and cold supply

Provide a new waste connection and cold-water tap.

items · HK$1,550 per item
G07

Relocate a toilet and reroute its waste pipe

Relocate the toilet, alter the waste pipe and make good the floor. From HK$9,300, subject to an on-site assessment.

items · HK$9,300 per item
K01

Install a toilet

Fit the toilet, connect the water supply and waste, and seal with mould-resistant silicone.

unit · HK$1,300 per unit
K02

Install a basin and tap

Fit the basin, tap and waste and connect the hot and cold supplies.

set · HK$1,150 per set
K03

Install a shower mixer

Install the mixer at the shower and connect the hot and cold supplies.

set · HK$970 per set
K04

Install a ducted cooker hood

Mount the hood, fit the duct, form the opening and test it. Removal and disposal of an old hood cost an extra HK$470.

unit · HK$860 per unit
K05

Install a shower screen (labour only)

Set out, drill, fit and seal the screen. Thick frameless glass starts at HK$1,400 for installation.

set · HK$860 per set
K06

Install a full set of bathroom fixtures and hardware

Installation of taps, bathroom heater, extractor fan, toilet and accessories.

set · HK$5,650 per set
Electric power engineeringConstruction by registered electrical workers9 items
H01

Electrical inspection (one visit)

Check tripping, earth leakage and circuits and provide an initial report. A full check of multiple circuits or an open-plan kitchen costs HK$1,650.

occasion · HK$770 per visit
H02

Add a single 13A socket with concealed conduit

Chase the wall, draw in wiring, fit the back box and faceplate, and make good with filler.

set · HK$640 per set
H03

Add a double 13A socket, TV outlet or network point

Chase the wall, draw in wiring, fit the back box and faceplate, and make good with filler.

set · HK$1,200 per set
H04

Replace a light switch and reconnect wiring

Remove the old switch, fit the new switch and connect the wiring.

unit · HK$430 per unit
H05

Install a pendant or ceiling light

Install and wire the customer's light fitting. Complex ceiling work is extra.

light · HK$670 per light
H06

Add a dedicated electrical circuit

A dedicated water-heater, induction-hob or oven circuit, including connection at the main board. Any increase in incoming supply capacity is assessed separately.

circuit · HK$3,350 per circuit
H07

Supply and install LED strip or T5 lighting

LED strip or T5 lighting, including driver and wiring.

linear ft · HK$150 per linear ft
H08

Supply and install a recessed spotlight

Recessed spotlight, including wiring.

light · HK$310 per light
H09

Replace a distribution board

Replace the old fuse box with MCB/RCD protection and label the circuits.

unit · HK$6,800 per unit
Custom furnitureDirect feet measured according to the horizontal width of the cabinet45 items
FUR01

Tall cabinet (1,501–2,400 mm)

Wardrobes, tall entrance cabinets and tall storage units. Includes 18 mm cabinet and door panels, back panel, PVC edging, standard soft-close hinges, internal shelves, standard installation and basic trims.

linear ft · HK$2,900 per linear ft · Minimum quantity 2 direct feet
FUR02

Mid-height cabinet (901–1,500 mm)

For sideboards, window-sill cabinets or study storage.

linear ft · HK$1,350 per linear ft · Minimum quantity 2 direct feet
FUR03

Base or low cabinet (900 mm and below)

For TV units, bedside cabinets and low shoe cabinets.

linear ft · HK$1,250 per linear ft · Minimum quantity 2 direct feet
FUR04

Extra-height supplement (above 2,400 mm)

Full-height cabinets are charged for each additional 100 mm. The actual height is stated in the quote.

linear ft · HK$100 per linear ft · Minimum quantity 2 direct feet
FUR05

Wardrobe with hinged or sliding doors

Includes one hanging rail, three shelves and two drawers, plus the track for sliding doors.

linear ft · HK$2,900 per linear ft · Minimum quantity 2 direct feet
FUR06

Platform or tatami bed

Platform frame and storage compartments with lift-up covers or drawers. Heights over 450 mm are assessed separately.

sq ft · HK$340 per sq ft
FUR07

Storage bed with manual hydraulic lift

Includes the storage base, bed board and manual lift mechanism. FUR36 is already included.

linear ft · HK$1,850 per linear ft · Minimum quantity 2 direct feet
FUR08

Desk or dressing table

Worktop, one or two drawers and a cable port.

linear ft · HK$1,850 per linear ft · Minimum quantity 2 direct feet
FUR09

Open bookcase or shelving

Shelves, sides and back, without doors. Adding doors is priced at the basic cabinet rate.

linear ft · HK$1,950 per linear ft · Minimum quantity 2 direct feet
FUR10

Low TV unit

Drawers or hinged doors, with cable ports.

linear ft · HK$1,250 per linear ft · Minimum quantity 2 direct feet
FUR11

Mid-height shoe cabinet

Angled or flat shelves and ventilation openings.

linear ft · HK$1,350 per linear ft · Minimum quantity 2 direct feet
FUR12

Tall entrance shoe or storage cabinet

Standard tall-cabinet specification.

linear ft · HK$2,900 per linear ft · Minimum quantity 2 direct feet
FUR13

Mid-height sideboard

Base cabinet with open cubbies or wall cabinets. Stone tops are priced separately at the worktop rate.

linear ft · HK$1,350 per linear ft · Minimum quantity 2 direct feet
FUR14

Kitchen base cabinet without worktop

Moisture-resistant carcass, door panels, soft-close hinges, adjustable feet and plinth.

linear ft · HK$1,300 per linear ft · Minimum quantity 2 direct feet
FUR15

Kitchen wall cabinet

Moisture-resistant carcass, door panels and soft-close hinges.

linear ft · HK$1,250 per linear ft · Minimum quantity 2 direct feet
FUR16

Tall kitchen appliance or crockery cabinet

Allows space for the appliances and ventilation.

linear ft · HK$3,350 per linear ft · Minimum quantity 2 direct feet
FUR17

Stainless-steel cabinet

Grade 304 stainless-steel carcass and doors.

linear ft · HK$2,600 per linear ft · Minimum quantity 2 direct feet
FUR18

Stone plinth under kitchen cabinets

Provides moisture protection and space for pipework.

unit · HK$2,050 per unit
FUR19

Seamless solid-surface worktop

600 mm deep with a straight edge, including one sink cut-out and one hob cut-out.

linear ft · HK$830 per linear ft
FUR20

Quartz worktop

600 mm deep with a straight edge, including one sink cut-out and one hob cut-out. Imported brands are quoted separately.

linear ft · HK$1,200 per linear ft
FUR21

Sintered-stone worktop

Slab thickness of 12 mm or more with a straight edge, including one sink cut-out and one hob cut-out.

linear ft · HK$1,700 per linear ft
FUR22

Stainless-steel worktop

Grade 304 stainless steel with a straight edge, including one sink cut-out and one hob cut-out.

linear ft · HK$1,200 per linear ft
FUR23

Full bullnose edge

Round off the front edge of the worktop.

linear ft · HK$90 per linear ft
FUR24

Additional cut-out

For a second sink, soap dispenser, tap hole or similar opening.

unit · HK$330 per unit
FUR25

Bathroom vanity with seamless solid-surface top

Carcass, door panels, soft-close hinges and a top with a basin cut-out. A quartz top costs extra.

linear ft · HK$3,250 per linear ft · Minimum quantity 2 direct feet
FUR26

Mirrored bathroom cabinet

Mirrored doors and shelves. LED or demisting mirrors are extra.

linear ft · HK$1,150 per linear ft · Minimum quantity 2 direct feet
FUR27

Tall bathroom cabinet

Tall-cabinet specification using moisture-resistant board.

linear ft · HK$2,900 per linear ft · Minimum quantity 2 direct feet
FUR28

Standard plated handle

Supply and installation.

handle · HK$70 per handle
FUR29

PVD metal handle

Scratch-resistant, colourfast finish. Supply and installation.

handle · HK$250 per handle
FUR30

Handleless push-to-open catch

Supply and installation.

door · HK$140 per door
FUR31

Upgrade to Blum or Hettich soft-close hinges

Replaces the standard soft-close hinges.

unit · HK$380 per unit
FUR32

Blum TANDEMBOX drawer runners

Full-extension, soft-close runners.

set · HK$1,500 per set
FUR33

Blum LEGRABOX drawer

Full-extension, soft-close drawer with metal sides.

set · HK$2,250 per set
FUR34

Standard kitchen pull-out basket

Pull-out storage for crockery or condiments.

unit · HK$1,000 per unit
FUR35

Premium kitchen accessory

Options include a corner pull-out, rice bin, electric waste bin or sensor light. The price depends on the model, capped at the listed figure.

item · HK$2,900 per item
FUR36

Manual hydraulic bed-lift hardware

Supply and installation.

set · HK$1,000 per set
FUR37

Electric hydraulic bed-lift hardware

Supply and installation.

set · HK$2,050 per set
FUR38

Fold-down wall-bed hardware

Supply and installation.

set · HK$3,650 per set
FUR39

Extending dining-table hardware

Supply and installation.

set · HK$2,050 per set
FUR40

LED strip inside cabinet

LED strip and driver with sensor or switch.

linear ft · HK$150 per linear ft
FUR41

Recessed cabinet spotlight

Recessed spotlight, including wiring.

light · HK$310 per light
FUR42

Furniture delivery

Per delivery, with direct lift access to the flat. Split deliveries are charged per trip.

occasion · HK$660 per visit
FUR43

Stair-carry charge in a walk-up building

Manual carrying up the stairs.

floor · HK$300 per floor
FUR44

Special trims and infill panels

False walls, full-height infill, and boxing in beams and columns. Standard trims are included.

m · HK$250 per m
FUR45

Remove an old cabinet

Dismantle and dispose of the existing cabinet.

linear ft · HK$170 per linear ft
Ceiling, floor, miscellaneousCeiling, floor, insurance, door and view12 items
F01

Plasterboard suspended ceiling on a metal frame

Metal framing, plasterboard, joint tape, filler and sanding. Painting is extra. Ceiling heights above 3.2 m carry a 15–25% surcharge.

sq ft · HK$51 per sq ft · Minimum 100 sq. ft.
F02

Plywood and plasterboard ceiling on a timber frame

A timber frame and plywood backing support a plasterboard face, suitable for shaped ceilings and added support.

sq ft · HK$100 per sq ft · Minimum 50 sq. ft.
F03

Recessed lighting cove

Form a plasterboard cove and allow space for the LED strip and driver. Strip lighting is charged separately under H07.

linear ft · HK$460 per linear ft · Minimum quantity 10 linear feet
F04

Curtain pelmet

Form a plasterboard or plywood pelmet with space for the curtain track.

linear ft · HK$460 per linear ft · Minimum 8 feet
F05

Aluminium suspended ceiling for one kitchen or bathroom

Clip-in aluminium panels, two LED lights and provision for an access hatch. The rate for areas over 40 sq ft is HK$90 per sq ft.

room · HK$3,650 per room
J01

SPC flooring, supplied and installed

Includes moisture-resistant underlay, click installation and edge trims.

sq ft · HK$60 per sq ft · Minimum 200 sq. ft.
J02

Laminate flooring, supplied and installed

Includes moisture-resistant underlay, click installation and edge trims.

sq ft · HK$82 per sq ft · Minimum 200 sq. ft.
J03

Self-levelling floor preparation

Clean and prime the floor, then apply self-levelling compound.

sq ft · HK$22 per sq ft · Minimum spending HK$2,800
J04

Skirting boards

Supply and fit PVC or timber skirting.

linear ft · HK$10 per linear ft
L02

Third-party liability and employees' compensation insurance for whole-home works

Third-party and employees' compensation cover during works. For small jobs this is already included in the item labour rates.

policy · HK$6,700 per policy
L03

Replace an internal plywood door

Door leaf, frame, hinges and handle, including installation. Solid timber doors start at HK$4,650.

door leaf · HK$3,000 per door leaf
L04

Tradesperson's site visit

A visit to inspect the site, measure and discuss the scope. The HK$500 travel fee is fully credited against the works when you order. It is only included in this estimate when you select it. Confirm the credit in the formal quote.

occasion · HK$500 per visit
Final cleaningWhole house cleaning and formaldehyde removal1 items
L01

RenoClean post-renovation cleaning and formaldehyde treatment

Whole-home cleaning and formaldehyde treatment.

sq ft · HK$16 per sq ft · Minimum spending HK$2,800
Public price list backup

Public PDFs can be downloaded/backed up; calculations still only use the 2026 catalog built into this site, and the unit price can be overwritten by the management backend.

The renovation PDF was archived on 21 October 2026. On 2 November that year, the company updated A11 to set a HK$2,000 minimum for small bagged-waste collections.

Check current A11 charges and inclusions for bagged waste and truckloads
Renovation project price list PDFCustomized Furniture Price List PDF

FROM ESTIMATE TO QUOTATION

How does a free online renovation estimate differ from an on-site quotation?

Use the calculator to budget for the work you select, then share site photos and your requirements for review. When comparing quotations, check the total alongside the scope and exclusions.

Read the renovation quotation guide, itemised prices and 500 sq ft example
Renovation quotation and material selection illustration with a work list, sample board and measuring tools
Illustration of quotation planning and material selection. It does not show a completed project or a fixed package.
From an online estimate to a formal renovation quotation
MethodWhat you receiveWhat to prepareFees and scope
Free online estimateSubtotal for selected work, planning allowance and exclusionsSaleable floor area and the work you want to carry outFree and no phone number required. The result is an estimate.
Free enquiry on WhatsAppOrganise your requirements and find out what information is still neededEstimate, site photos, district and intended start dateThe initial enquiry is free. Unmeasured details still need verification.
On-site measurement and renovation quotationWe check dimensions, site constraints and who supplies materials before confirming the itemised written quotation.Property location, times available for a visit and list of workThe site visit policy below and the arrangements confirmed when booking apply.

Site measurement policy: Free site measurements until 31 December 2026 for enquiries covering at least two items of work. No deposit is required. After that, the fee is HK$500, credited against your order. Online estimates and enquiries are free.

  1. 01 · Choose the workDecide what you want to change and what to keep
  2. 02 · Calculate your budgetCheck quantities, minimum charges and the planning allowance
  3. 03 · Share your detailsReview the prefilled WhatsApp result and send it when ready
  4. 04 · Confirm your quotationAfter site verification, agree the scope of work in writing

Renovation quotation FAQs

Will the calculator automatically send my estimate to your company on WhatsApp?

You control when the message is sent. The button beside the result opens WhatsApp with your selected work and budget already filled in. Check the draft and tap Send when ready. You can also add site photos.

Does an online renovation estimate include all work?

The estimate covers only the items you select. Finishes, equipment, concealed deterioration, site constraints and items awaiting prices must be checked individually. The planning allowance is money you set aside, not an automatic company charge.

How do I compare two renovation quotations?

Use the same list of work to compare units, quantities, materials, waste disposal, protection, payment schedules and exclusions. Ask for written confirmation before approving extra work, and compare the scope as well as the totals.

Is an on-site renovation quotation always free?

Online estimates and initial enquiries are free. A site measurement is arranged separately under the policy on this page. We confirm the applicable conditions with you when booking your visit.

Already have a list of work or site photos?

Tell us the district, scope and timing so we can follow up on your requirements.

Ask about an on-site quotation on WhatsApp

Look at the scope of the project first, then compare renovation quotes

The same total may include different processes, fabrics or clearing arrangements. Read the company's price list and 500-foot example, check what's included, what's not included, and the minimum consumption, and then sort out the next step of enquiry.

2026 Renovation Quotation Guide: Price List, Scope and Quotation Comparison

Why discuss your project with HK Create Design?

Understand your Renovation quotation / budget before you decide.

Start with the existing conditions

Tell us what you want to keep or replace. We can then check the work stages, materials, waste removal and exclusions item by item.

Check the budget item by item

Use the online prices and calculator for an initial estimate. We confirm site conditions, exclusions and final costs in the written quote.

Open the renovation calculator ↗