2026 kitchen renovation budget: break it down into five major parts before calculating

Even a small kitchen brings together more trades than most rooms. Work usually starts with removing cabinets and tiles, then relocating pipes and wiring. Waterproofing, rendering and tiling follow before the ceiling, cabinets and worktop go in. The hob, cooker hood and fittings are installed last. To see what the total covers, split the quote into demolition and clearance, waterproofing and masonry, plumbing/electrical/gas work, cabinets and worktops, and installation of appliances and hardware. State how each is measured, for example per room, linear foot, square foot, set or light fitting (see published rates).

Any idea how to dismantle it? Because the quotations written by different companies are quite different, some say "kitchen set" and some list them item by item. Consumer Council research shows that 58% of respondents find it difficult to compare quotations due to different formats, and 49% are concerned that the quotations are too crude. Among respondents with actual renovation experience, 19% have had disputes with renovation companies.[1]. By breaking the kitchen into items, you can compare the quantities and materials packaged item by item instead of simply comparing the total number.

In addition, it is necessary to distinguish between "project fees" and "planning buffer". The engineering fee is calculated based on the project and quantity; the planning buffer is reserved by the owner to deal with problems discovered after disassembly (such as rusty old pipes and hollow walls), and is not charged by the renovation company. In our quick budget, we usually recommend setting aside 20% as a planning buffer. However, whether or not this money is used, we should first have a written order to start work.

If you are adding a dishwasher, start with the dishwasher planning checklist. Use the exact model's installation manual to check the cabinet opening, door clearance, water supply, drainage and power. Agree who installs the appliance and who alters the cabinetry, plumbing or wiring. Confirm the site conditions before finalising cabinet drawings. The appliance width alone is insufficient.

  • List five major areas: demolition, cement and water proofing, water, electricity and coal, kitchen countertops, and electrical appliance installation.
  • Please write the same quantity for each item. It is not acceptable to write only "one set"
  • Separate project costs from your own planning buffer
  • Ask about the minimum fees for certain projects

02

Dismantling the old items and clearing them for transportation: full dismantling and partial dismantling, the price difference is huge.

At our published rates, stripping out and clearing the entire kitchen (A09) costs HK$9,950 per kitchen. If you are replacing only the cabinets and keeping the tiles, cabinet removal (FUR45) costs HK$170 per linear foot (see published rates). Your choice also affects whether waterproofing, rendering and tiling need to be redone. Agree what to remove before costing the job.

The Consumer Council reminds that before demolishing old renovations, contractors need to determine the location of indoor structural walls; demolition of indoor gas installations should be handled by qualified persons or companies; the extent of demolition of floor tiles and walls must also be specified in detail, such as whether the muddy water layer under the bricks will be demolished, because these details will affect the charges.[2]. Many kitchens have gas pipes attached to them. Before dismantling them, they must be handled by qualified personnel. It is not advisable to ask a dismantling technician to cut the pipes.

Allow for construction waste removal. A09 already includes carrying the waste out. For partial cabinet removal or additional debris, check whether you need A11 waste removal at HK$4,200 per truckload. Small jobs can be priced by the bag (see published rates). Government construction waste facilities also charge disposal fees, for example HK$71 per tonne at public fill reception facilities and HK$200 per tonne at landfills. A one-tonne minimum applies outside the outlying-island facilities[7]. The quotation should indicate that the clearing and transportation system has been included, otherwise it will be difficult to add additional items upon completion.

  • Decided to completely dismantle (A09) or decided to dismantle only the cabinets (FUR45)
  • Confirm that the gas installation has been removed or sealed by a qualified person
  • Specify that it will be removed to the brick surface and to be removed to the mud bottom.
  • Ask if there are bags for mud removal, and if bags are ordered per truck,
Comparison of public prices for kitchen countertops (per square foot)

Most recommended Not recommended, it depends on the situationThe star rating is based on the company's recommendations for general Hong Kong housing, and ultimately depends on the on-site conditions.

You can swipe left or right on your phone to view the complete table.

CountertopPrice numberUnit price8 direct feet amountsuitable forRecommendation
Seamless stoneFUR19HK$830HK$6,640Want an integrated basin with fewer interfaces?4 stars・Not highly recommendedThe cheapest, but easier to scratch and absorb color
rock slabFUR21HK$1,700HK$13,600Heat-resistant, thin appearance4 stars・Not highly recommendedIt’s heat-resistant and looks good, but it’s the most expensive and the corners are prone to chipping.
stainless steelFUR22HK$1,200HK$9,600Easy to clean, heavy oil fumes4 stars・Not highly recommendedEasiest to clean and suitable for cooking over high heat all day long

Cost = unit rate × 8 linear ft. The comparison excludes cut-outs and transport restrictions. Prices are from our published rate card. (see published rates)

03

Kitchen waterproofing and tile laying: the least noticeable but the most affecting downstairs

Kitchens see less standing water than bathrooms, but sinks, washing machines and floor cleaning all introduce moisture. After stripping back to the cement substrate or concrete, it is prudent to renew the waterproofing. Our published kitchen waterproofing item (C03) costs HK$4,300 per kitchen with a 150 mm wall upstand. An optional flood test (C04) costs HK$1,400 per test (see published rates).

The Consumer Council highlights waterproofing as an area of Masonry and tiling that is particularly easy to overlook. Quotations should state the Waterproofing locations, waterproofing materials, height of the membrane and whether a leak test is included. Fewer than half the contractors in its study specified the material, height and test details, leaving room for disputes[2]. So when looking at kitchen quotes, it’s best not to just see the word “waterproof”.

At published rates, floor tiling (D01) and wall tiling (D02) each cost HK$78 per sq ft, with a minimum charge of HK$3,250 for each item (see published rates). Small kitchen floors often fall below the minimum. Budget for the higher of the area-based price and the minimum charge. The Consumer Council also notes the distinction between backing materials and finish tiles. Many quotations cover labour and backing materials only. Owners often buy the tiles separately and diagonal or herringbone patterns may cost extra[2].

Kitchen waterproofing (C03) costs HK$4,300 per kitchen. It covers the entire floor, a 150 mm upstand at floor-to-wall junctions and reinforcement around the sink, using two coats of Sika 107 (see published rates). For masonry base materials, we use products including Optimix.

  • Waterproof range: the entire width of the floor + the height of the wall to be specified
  • The name of the waterproof material is the same as the number of coating layers
  • Do you want to close the water and test the water (C04)
  • Facing tiles are packaged with materials and are laid diagonally. Is there any surcharge?
Design renderings: The kitchen countertops are the same as bricks and do not represent the actual completed case.
Design renderings: The kitchen countertops are the same as bricks and do not represent the actual completed case. Select an image to enlarge
Project photo of bespoke kitchen cabinets with worktop | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

04

Water pipe: should it be replaced or not? Which pipe should be used? Count from edge to edge.

In older kitchens, ageing supply and waste pipes are a common problem. Our published rates are HK$13,300 for a complete set of kitchen hot and cold pipes (G03), HK$1,700 per point for a local hot/cold supply relocation (G02), and HK$1,550 for a washing-machine drain (G06) (see published rates). To check existing pipes first, opening up for inspection (G01) costs HK$930 per item.

The Consumer Council reminds that if you are considering replacing the water pipes in older units, you should make it clear with the contractor that starting from the first water pipe switch after entering the house, it will start from the building's strata water meter switch. Open pipes and concealed pipes will affect other projects, and the quotation should also specify the materials and sources of pipes and accessories.[2]. If these points are not written clearly, it is most likely to occur, "I thought it was covered, but it turns out it is not."

In terms of legislation, the Water Supplies Department points out that specified plumbing works for the construction, installation, maintenance, alteration, repair or removal of internal water supply systems must be carried out by designated persons such as licensed plumbers and registered plumbers. The public can check using the electronic service of the Register of Licensed Plumbers[6]. The plumbing works we arrange will be handled by qualified persons, and owners can also conduct their own searches.

When drinking-water pipes need replacement, our partner licensed plumber seeks approval from the Water Supplies Department. HK Create Design coordinates the application for the owner.

We use copper for drinking-water pipework and exclude galvanised iron. Common choices include Wednesbury (supplied by CYH, BS EN 1057), Kembla (Kempress), LAWTON, OTTO and OPAL. We use Pegler (Pegler Yorkshire), Tectite and ENDEX fittings, including push-fit and silver-brazed connections. The pipes and fittings carry product certification and meet Water Supplies Department requirements. Our partner licensed plumber handles the replacement and we coordinate the application.

  • Decide on complete throat replacement (G03) or partial relocation (G02)
  • Indicate the starting point for pipe replacement: enter the house gate and activate the stratified water meter
  • Pipe material, origin, open pipe and concealed pipe
  • Plumbing works are carried out by designated persons and can be searched
  • We coordinate the Water Supplies Department application for drinking-water pipe replacements
Worked example 1

Demonstration 1: Assume that the 8-foot straight kitchen is completely dismantled and redone.

Assumptions

  • Hypothetical examples, not actual cases or quotes.
  • The kitchen floor is 30 square feet, the wall tiles are 60 square feet, and the position of the stove remains unchanged.
  • Add 1 independent circuit and 3 sets of 13A sockets; use quartz stone for the countertop.
  • The cost of gas and electrical appliances are not included.

How to calculate quantities

  1. "A09" Demolition and removal of kitchen: HK$9,950/room × 1 = HK$9,950
  2. "C03" kitchen waterproofing: HK$4,300/room × 1 = HK$4,300
  3. "G03" Kitchen complete set of hot and cold water pipes: HK$13,300/item × 1 = HK$13,300
  4. "D02" wall tile: HK$78/square foot × 60 = HK$4,680
  5. "D01" floor tile: HK$78/square foot × 30 = HK$3,250 (if the minimum charge is not reached, the minimum charge will be calculated)
  6. "F05" Kitchen and toilet aluminum false ceiling: HK$3,650/room × 1 = HK$3,650
  7. "H06" independent circuit: HK$3,350/circuit × 1 = HK$3,350
  8. "H02" 13A unit: HK$640/set × 3 = HK$1,920
  9. "FUR14" kitchen base cabinet: HK$1,300/straight sq ft × 8 = HK$10,400
  10. "FUR15" wall cabinet: HK$1,250/straight sq ft × 8 = HK$10,000
  11. "FUR20" quartz stone countertop: HK$1,200/straight sq ft × 8 = HK$9,600
  12. "K04" range hood installation: HK$860/unit × 1 = HK$860
  13. The subtotal of the project is HK$75,260; plus 20% planning buffer (reserved by the owner, not charged by the company) ≈ HK$90,312.

In this example, a full kitchen refit totals about HK$75,260, or HK$90,312 with a 20% planning contingency. The small floor area attracts the minimum tiling charge.

The actual quantity must be measured on site; gas modifications, electrical appliances, and deep cleaning are not included; the condition of the old pipes may increase or decrease the project, and a written quotation must prevail. (see published rates)

Use your square footage instead and see a reference budget

05

Electricity: There are many electrical appliances in the kitchen, so the circuit and socket locations need to be planned in advance.

While home kitchens have ovens, steam ovens, induction cookers, dishwashers, refrigerators and microwaves, many kitchens in old buildings only have two or three sockets. The Electrical and Mechanical Department's Household Electrical Safety Manual reminds that electrical appliances with large power consumption should be powered by independent sockets. Sockets should not be installed near faucets, gas switches or cooking stoves. Socket circuits must be protected by leakage circuit breakers (commonly known as water and gas switches). Newly installed wall wires must also be protected by appropriate enclosures.[5].

Before adding or altering an electrical installation, arrange a feasibility assessment by a registered electrical contractor. Consider future demand and whether to apply to the electricity supplier for an increased load. Before energisation, a registered electrical worker must inspect and test the completed installation and issue a Work Completion Certificate (WR1). Retain the certificate for your records. You do not need to submit it to the EMSD[4].

Our published rates are HK$3,350 per dedicated circuit (H06), HK$640 per single 13A socket (H02) and HK$1,200 per twin socket (H03) (see published rates). If the flat's distribution board is also ageing, consider item H09,distribution board replacement, at HK$6,800. Mark each appliance on the kitchen plans, then count the sockets and circuits required.

Our standard wiring ranges include Hilly and ei8ht, with Prysmian and Nexans available for higher specifications. We select cable brands with product certification such as 3C and install to the EMSD's Code of Practice for the Electricity (Wiring) Regulations. On completion, a registered electrical worker inspects and tests the installation and issues a WR1[10]. We commonly use Schneider switches and sockets.

  • List all kitchen appliances with the same power and decide which ones should use independent circuits.
  • Keep sockets away from faucets, gas switches and stoves
  • Obtain WR1 Completion Certificate upon completion
  • Evaluate whether the old electrical box needs to be replaced first

06

Gas stove: You can’t install it yourself, and it’s not easy to change it easily.

Kitchen relocation most often involves gas pipes. The Electrical and Mechanical Department points out that residential gas cooking stoves must be approved by the Electrical and Mechanical Department and bear the "GU" mark, and must be installed and tested by a registered gas installation technician employed by a registered gas works contractor before they can be used. Pay attention to whether the gas connection hose is damaged or expired, and contact the registered gas works contractor every 18 months to conduct a safety inspection of all gas installations.[3].

During the actual renovation, we will first confirm with the owner whether the position of the stove will be moved. If the position of the stove remains unchanged, you usually only need to arrange for a registered gas contractor to cut off the gas before dismantling the old one, reconnect and test it after completion. If it needs to be moved, you must first confirm the feasibility with the gas company or registered contractor before drawing it into the kitchen cabinet diagram. For the gas part, we will not quote the public price as it needs to be separately assessed by a registered gas engineering contractor.

In addition, the kitchen cabinet design should reserve openings for the stove and access points, and the bottom of the cabinet should not completely seal the gas pipe. The Consumer Council also reminds that the removal of indoor gas installations should be handled by qualified persons or companies.[2]. These are safety issues and should not be compromised to save some time.

  • Stoves must have the "GU" mark
  • Installation and testing is carried out by a registered gas installation technician
  • Before moving the furnace head, confirm the feasibility first
  • Gas pipe inspection space reserved in kitchen cabinets
Compare kitchen projects with official requirements

You can swipe left or right on your phone to view the complete table.

EngineeringRequests/Suggestionsperson in chargeOwners want to keep
gas stoveMust have "GU" mark and be installed and tested by a registered gas installation technician[3]Registered gas works contractorInstallation record, inspection date
electricityAfter completion, inspect, test and issue WR1[4]; the socket must be protected by a leakage circuit breaker[5]Registered electrical contractorWR1 Completion Certificate
water pipeSpecified plumbing works to be carried out by designated persons[6]Licensed plumbers, etc.Pipe material information and photos
mud headGovernment facilities charge per metric ton, landfills charge $200 per metric ton[7]contractor or ownerClearance arrangement written into quotation
WaterproofingThe quotation lists the location, materials, and height, which is the same as the water test[2]PlastererConstruction photos and water test records

The above is a summary of general requirements. The actual latest regulations of relevant departments shall prevail [3][4][6]. [2][3][4][5][6][7]

Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge

07

Kitchen cabinets: straight feet, floor cabinets, wall cabinets, tall cabinets

Cabinet length is measured along the wall in linear feet. Our published prices per linear foot are HK$1,300 for base units (FUR14), HK$1,250 for wall units (FUR15) and HK$3,350 for tall appliance units (FUR16) (see published rates). Measure each run of an L-shaped kitchen separately and record how the corner is counted to avoid charging twice.

List each hardware item and accessory. For example, a pull-out basket (FUR34) costs HK$1,000 each and an extra cut-out (FUR24) costs HK$330 each (see published rates). The Consumer Council's study also found that over 75% of the companies surveyed said a kitchen door could be converted to a sliding door[1]——But the kitchen door involves fire protection requirements, so it is not suitable for every unit. You must first understand the conditions of the same unit in the building.

Our Custom furniture service includes design and whole-home drawings: floor plans, ventilation/fire services/plumbing/electrical layouts, furniture designs, VR renderings and furniture production drawings. Before ordering, owners can see where each cabinet, socket and cut-out will go. Clear drawings help catch issues such as an impractical cut-out before installation.

From 2026, ENF-grade board is standard for all our bespoke furniture at no extra charge. Under GB/T 39600-2021, the formaldehyde emission limit for ENF is ≤0.025 mg/m³, stricter than E0 (≤0.050 mg/m³)[9]. ENF boards have very low emissions but still release some formaldehyde. Ventilate the flat before moving in. We call this approach “Pure Space”.

Kitchen cabinets carry a one-year warranty from delivery covering damage other than deliberate damage. Examples include detached hinges, loose runners, screws coming loose and swollen doors.

  • Base cabinets, wall cabinets, and high cabinets are measured in feet apart
  • The corner position meter method is clearly stated to avoid duplication.
  • Hardware such as baskets and openings are listed item by item
  • Please review the floor plan, water and electricity diagram and VR renderings before placing your order.
  • Confirm that ENF-grade board is standard for cabinet carcasses
  • Warranty coverage includes hinges, runners, screws and swollen doors
Design renderings: Cabinets and water pipes under kitchen renovation. The actual plan needs to be measured and confirmed on site.
Design renderings: Cabinets and water pipes under kitchen renovation. The actual plan needs to be measured and confirmed on site. Select an image to enlarge

08

Kitchen cabinet materials: standard ENF-grade board, worktops and hardware options

Cabinet pricing has three main components: carcasses, worktops and hardware. From 2026, ENF-grade board is standard. Base units (FUR14, HK$1,300 per linear foot) include moisture-resistant carcasses, doors, soft-close hinges, adjustable legs and plinths. Wall units (FUR15, HK$1,250 per linear foot) include carcasses, doors and soft-close hinges (see published rates).

All four worktops include one sink cut-out, one hob cut-out and a straight edge. Solid-surface and quartz worktops are 600 mm deep. A rounded edge costs an extra HK$90 per linear foot and additional cut-outs cost HK$330 each (see published rates). Hardware upgrades include Blum or Hettich hinges (FUR31, HK$380 each), TANDEMBOX (FUR32, HK$1,500 per set) and LEGRABOX (FUR33, HK$2,250 per set) (see published rates).

For a consistently damp area under the sink, consider a 304 stainless-steel cabinet (FUR17, HK$2,600 per linear foot) (see published rates). Ask for the quotation to specify the board grade, worktop finish and hardware models for checking and future warranty claims.

We manufacture our ENF-grade boards at our own factory in Foshan.

  • Specify standard ENF-grade board for cabinet carcasses
  • Record the worktop type, edge profile and number of cut-outs
  • List each hardware upgrade by model and quantity
  • Consider stainless-steel cabinets for damp areas
Worked example 2

Demonstration 2: Keep the bricks and water and electricity, only replace the kitchen cabinets with the countertops

Assumptions

  • Hypothetical examples, not actual quotes.
  • The old base cabinets and wall cabinets were 8 square feet each, and a total of 16 square feet were dismantled.
  • The new countertop is made of seamless stone and requires 2 additional openings and 1 pull basket.

How to calculate quantities

  1. "FUR45" demolition of old cabinets: HK$170/straight sq ft × 16 = HK$2,720
  2. "FUR14" kitchen base cabinet: HK$1,300/straight sq ft × 8 = HK$10,400
  3. "FUR15" wall cabinet: HK$1,250/straight sq ft × 8 = HK$10,000
  4. "FUR19" seamless stone countertop: HK$830/straight sq ft × 8 = HK$6,640
  5. "FUR24" additional holes: HK$330/piece × 2 = HK$660
  6. "FUR34" basket: HK$1,000/piece × 1 = HK$1,000
  7. "K04" range hood installation: HK$860/unit × 1 = HK$860
  8. The subtotal is HK$32,280, which is HK$42,980 less than Demonstration 1, but old pipes, waterproofing and electricity are not processed.

Replacing the cabinets and worktop costs about HK$32,280. This option suits a kitchen with sound plumbing and wiring and intact tiles.

If the old pipe is old or there are insufficient sockets, it will be more expensive to cut it in the future. It is recommended to do a water and electricity inspection (G01/H01) before making a decision. (see published rates)

Use your square footage instead and see a reference budget
Project photo of rewiring and conduit replacement at Dandenong Mansion, Wan Chai | HK Create Design
Project photo: electrical work at Dandenong Mansion, Wan Chai, July 2026 | HK Create Design Select an image to enlarge

09

Small kitchen renovation costs: worked examples for 6 ft and 8 ft layouts

Many Hong Kong kitchens have only a 6–8 ft run. At our published rates, replacing the cabinets and worktop in a 6 ft single-wall kitchen costs about HK$23,180, compared with about HK$32,280 for 8 ft (see published rates).

A full refit includes stripping out and clearance, waterproofing, a complete set of hot and cold pipes, tiling, a suspended ceiling, a dedicated circuit and sockets. The example comes to about HK$63,730 for 6 ft or HK$75,260 for 8 ft (see published rates). Two major differences between replacement and a full refit are plumbing (HK$13,300) and demolition (HK$9,950). Check the condition of existing pipes before deciding.

Watch for minimum charges in small kitchens. A 20–30 sq ft floor still attracts the HK$3,250 minimum tiling charge (see published rates). These are hypothetical examples. Actual quantities are confirmed by site measurement.

  • Decide between a full strip-out and cabinet replacement first
  • Check minimum charges for small areas
  • Inspect old pipes before deciding whether to replace them
  • Gas alterations and appliances are priced separately

10

Countertop: seamless stone, quartz stone, slate, stainless steel

Material has the greatest effect on worktop cost. Published rates per linear foot are HK$830 for solid surface (FUR19), HK$1,200 for quartz (FUR20), HK$1,700 for sintered stone (FUR21) and HK$1,200 for stainless steel (FUR22) (see published rates). Over an 8 ft run, the highest- and lowest-priced materials can differ by several thousand dollars. Consider how you cook and use the surface as well as its appearance.

The joints of seamless stone are not obvious, making it easy to make an integrated basin; quartz stone has high hardness and is scratch-resistant; rock slabs are thin and heat-resistant, but you need to be more careful when opening holes and handling; stainless steel is easy to clean and is suitable for families who cook a lot. Regardless of the edge selection, you must clearly indicate the depth of the countertop, whether there is a water retaining edge, and the number of basin and stove openings.

A common mistake is that after the countertop is installed, it is discovered that the opening position is not the same as the size of the electrical appliance. Therefore, we will first confirm the model and size of the stove, sink and faucet before producing production drawings. During the on-site measurement, it will also be checked whether the wall is vertical and whether the floor is flat, because gaps between kitchen cabinets and countertops are often caused by uneven base layers.

A partner export factory supplies our quartz worktops directly, with a quality guarantee and a wide choice of colours. We finish junctions around the sink and along the wall with DOWSIL mould-resistant silicone sealant.

  • Choose countertop materials according to cooking habits
  • Indicate the table depth, water retaining edge, and number of openings.
  • Please confirm the model and size of electrical appliances before issuing production drawings.
  • On-site review to ensure that the wall is vertical and level with the floor
Kitchen cabinet materials: carcasses, worktops and hardware at our published rates

You can swipe left or right on your phone to view the complete table.

ComponentMaterialOur rateWhat is included and what to check
Cabinet carcassStandard ENF-grade board for moisture-resistant cabinet carcassesIncluded in base units (FUR14) at HK$1,300 per linear foot and wall units (FUR15) at HK$1,250 per linear footStandard from 2026 at no extra charge. Formaldehyde emissions are very low but measurable.
Cabinet doors and standard hardwareDoors and soft-close hinges. Base units also include adjustable legs and plinths.Included in FUR14 and FUR15View door samples before placing the order
stainless steel cabinet304 stainless steelFUR17: HK$2,600 per linear footSuitable for damp areas and under-sink cabinets
Solid-surface worktopSeamless stoneFUR19: HK$830 per linear footOne sink cut-out and one hob cut-out, 600 mm deep with a straight edge
Quartz countertopsquartz stoneFUR20: HK$1,200 per linear footOne sink cut-out and one hob cut-out, 600 mm deep with a straight edge. Imported brands are quoted separately.
Slate countertopsSintered stone, 12 mm thick or moreFUR21: HK$1,700 per linear footOne sink cut-out and one hob cut-out, with a straight edge
stainless steel countertop304 stainless steelFUR22: HK$1,200 per linear footOne sink cut-out and one hob cut-out, with a straight edge
Hinge upgradesBlum or Hettich hingesFUR31 HK$380Per hinge
Drawer runnersBlum TANDEMBOX/LegraBoxFUR32 HK$1,500;FUR33 HK$2,250Per set
Pull-out basketPull-out basketFUR34: HK$1,000 eachAdditional cut-outs (FUR24): HK$330 each

Rates are from our published price list. The ENF-grade emission limit of ≤0.025 mg/m³ is from national standard GB/T 39600-2021 [9]. (see published rates)[9]

Project photo of plumbing work at Yat Man House, Ho Man Tin Estate | HK Create Design
Project photo: plumbing at Yat Man House, Ho Man Tin Estate, May 2026 | HK Create Design Select an image to enlarge

11

Quotation review: The five most common missing items in the kitchen

There are five most common omissions in kitchen quotations: 1. Mud removal is not mentioned; 2. The waterproofing range is not mentioned and the same as water testing; 3. The starting point and material of the water pipe are not mentioned; 4. The number of electrical circuits and sockets are not mentioned; 5. The hardware and openings of the kitchen cabinets are not mentioned. The Consumer Council recommends that the quotation should be as detailed as possible. For example, for paint, the number of layers of primer and oil on the surface should be stated, for water pipes, the materials and origin should be stated, and for mud and water, the actual area should be stated.[2]. The same principle applies to everything in the kitchen.

Complaint figures from the Consumer Council show that there were 400 cases in the "Renovation and Home Maintenance Works" category in 2024, 347 cases in 2025, and 352 cases from January to September 2026; there were 779, 656 and 617 cases in the "Furniture Renovation" category in the same period.[8]. Kitchen renovation brings together building work and furniture. An itemised written quotation is a practical way to reduce disputes.

Also keep an eye out for changes. After starting work, first add sockets, change cabinet doors, and replace countertops. There should be a written order with the amount stated before starting work. The Consumer Council’s research also mentioned that nearly 30% of the respondents believe that there is no need to revise the quotation when the project changes. This idea should not be encouraged.[1].

  • Check out the five major missing items one by one: transportation, waterproofing, water pipes, electricity, and hardware.
  • Each item has unit, quantity, unit price
  • Changes must be made in writing
  • Payment is based on the project stage, it is not easy to pay in one go

12

Processes at the same time: no rework if scheduled first

The general principle of kitchen work is "conceal first, then surface": after dismantling the old ones, do the water pipes and electric wires (hidden work) first, take photos to record the position of the pipes, then do waterproofing and plastering, then lay the tiles, install the false ceiling, and finally install the kitchen cabinets and countertops. If the order is reversed, for example, after laying the bricks, the sockets must be changed first, and then the bricks must be cut, which is a waste of time and can easily damage the waterproof layer.

After the waterproofing is completed, it is best to do a closed water test to confirm that there is no leakage before laying bricks. Kitchen cabinets are usually produced on-site after measuring and confirming the drawings. Therefore, during the demolition and water and electricity period, the designer and owner should have already determined the cabinet size, door panel color and hardware.

Owners who live in the building should also pay attention to the management office's renovation time, removal regulations and soil disposal. After we finish the work, we will remove the trash, sweep up and do basic cleaning. If deep cleaning or formaldehyde removal is required, we can have our professional cleaning company follow up.

  • After demolishing the old ones, do the water and electricity first and take photos to record them.
  • After waterproofing, close the water and test the water before laying bricks.
  • The kitchen cabinet drawings will be confirmed during the water and electricity period
  • Understand the management office’s renovation time and transportation regulations in advance
Small kitchen renovation costs at our published rates

You can swipe left or right on your phone to view the complete table.

Kitchen layout and scopeItems included at our published ratesSubtotalExclusions
6 ft single-wall kitchen, cabinets and worktop onlyRemove 12 linear ft of existing cabinets (FUR45), HK$2,040. Add 6 ft of base units, HK$7,800, 6 ft of wall units, HK$7,500, a 6 ft solid-surface worktop, HK$4,980, and cooker hood installation, HK$860.HK$23,180Excludes plumbing, waterproofing, electrical work and tiling
8 ft single-wall kitchen, cabinets and worktop onlyRemove 16 linear ft of existing cabinets, HK$2,720. Add base units, HK$10,400, wall units, HK$10,000, a solid-surface worktop, HK$6,640, two extra cut-outs, HK$660, a pull-out basket, HK$1,000, and cooker hood installation, HK$860.HK$32,280As in Example 2. Excludes plumbing, electrical work and waterproofing.
6 ft single-wall kitchen, full strip-out and refitKitchen strip-out and clearance, HK$9,950. Waterproofing, HK$4,300. All hot and cold pipes, HK$13,300. Wall tiling, 45 sq ft, HK$3,510. Floor tiling, 20 sq ft at the minimum charge, HK$3,250. Aluminium suspended ceiling, HK$3,650. Dedicated circuit, HK$3,350. Two 13A sockets, HK$1,280. Base units, HK$7,800. Wall units, HK$7,500. Solid-surface worktop, HK$4,980. Cooker hood installation, HK$860.HK$63,730Excludes gas alterations, appliances and supply of finish tiles
8 ft single-wall kitchen, full strip-out and refitAs in Example 1, including an 8 ft quartz worktop, three 13A sockets, 60 sq ft of wall tiling and 30 sq ft of floor tilingHK$75,260Excludes gas alterations, appliances and supply of finish tiles

These planning examples are hypothetical. Tiling a small area attracts the HK$3,250 minimum charge. Owners may allow a separate 20% contingency in their own budget. This is separate from our charges. The site measurement and subsequent written quotation confirm the final price. (see published rates)

13

Common mistakes in kitchen renovation: saving money in the wrong place will make it more expensive

The first common mistake is to only change the surface and ignore the hidden projects. Many owners feel that they will not replace the old kitchen cabinets if there is still water coming out. As a result, water seeps from the bottom of the new kitchen cabinets a year or two after they are installed. They have to dismantle the cabinets, cut bricks and then repair them. The total cost is higher than replacing them all at the beginning. If the unit is older, at least one or two locations should be drilled and inspected to understand the condition of the pipes before making a decision.

The second mistake was to show the electrical appliances before they were decided. Ovens, dishwashers, refrigerators and range hoods all have specified sizes and heat dissipation requirements. If you build a cabinet without choosing a model, it is easy to find that it cannot be put in, the door cannot be opened, or the socket is blocked by the cabinet body. It is recommended to select the main electrical appliances at the design stage, and at least know the width, height, depth and power requirements.

A third mistake is choosing the lowest unit rate without checking quantities and minimum charges. For items such as tiling, budget for the higher of the minimum charge and the unit rate multiplied by the quantity. A fourth mistake is omitting a contingency for defects uncovered during demolition. A fifth is agreeing changes verbally. Confirm extra work in writing to avoid disputes over the final bill.

  • Check the hidden project first, don’t just change the surface
  • Determine the main electrical appliance models first, and then display the cabinet diagrams
  • Pay attention to the minimum charges when calculating your budget
  • Leave a planning buffer and document changes in writing
Project photo of bespoke wardrobes and storage cabinets | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge

14

Let us help you calculate your kitchen budget

HK Create Design (HK CREATE DESIGN) takes on jobs big and small, from removing a cabinet or two or replacing a worktop to a complete kitchen with whole-home custom design. Our designers and tradesmen with over 15 years' experience will discuss plans with you for free; you can first WhatsApp 5243 7747 photos of your kitchen and rough dimensions, and we will advise whether to fully demolish or partially refurbish.

For a closer estimate and professional advice, book a site measurement. It is free until 31 December 2026 for two or more work items, with no deposit. After that, the fee is HK$500, credited against your order (see published rates). The website's AI quotation assistant and 117-item price calculator can give you a preliminary estimate. Our team confirms the final price in writing after measuring on site.

All 117 price items are disclosed. You can check the item numbers in this article yourself and then compare them item by item with our written quotation. In this way, both sides know the purpose of every move.

  • WhatsApp 5243 7747 Send photos of the same size for free consultation
  • Book a site measurement. Until 31 December 2026 it is free for two or more work items, with no deposit. After that, the fee is HK$500, credited against your order.
  • Use AI quotation/computer for preliminary reference
  • Check item by item with written quotation

FAQ

12 practical questions answered

01How much does it cost to renovate a kitchen in a small unit in 2026?

It depends on whether you want a full or partial refit. At published rates, a hypothetical 8 ft single-wall kitchen costs about HK$75,260 for a full strip-out and refit or HK$32,280 for cabinets and worktop replacement. Both exclude appliances and a planning contingency (see published rates). We confirm the price in writing after measuring on site.

02Does kitchen renovation have to be redone and waterproofed?

If you remove the mud bottom or concrete, it is recommended to redo it. The Consumer Council recommends that the quotation list the waterproofing location, materials, and height of the waterproofing layer, and the Council will not test the water.[2]. If you only replace the cabinets and not the bricks, waterproofing is usually not involved.

03Can I ask the decorator to move the gas stove easily?

No. The EMSD requires gas cooking stoves to be installed and tested by registered gas installation technicians employed by registered gas works contractors[3]. The feasibility should be confirmed before moving.

04Do I need to apply for a socket in the kitchen?

Before adding or modifying electrical equipment, it should be evaluated by a registered electrical contractor. After completion, a registered electrical engineer will inspect and test and issue a WR1 completion certificate, which the owner can keep.[4].

05Are kitchen cabinets measured by square feet?

A linear foot measures cabinet length along the wall, making prices easier to compare. Our published rates are HK$1,300 per linear foot for base units and HK$1,250 for wall units (see published rates). For L-shaped kitchens, measure each run separately and specify how the corner is counted.

06Should pipe replacement be measured from edge to edge?

The Consumer Council reminds us to make it clear that the first water pipe entering the house starts with the switch of the layered water meter, and that the pipe materials and origins must be clearly stated.[2]. Plumbing works must be carried out by designated persons such as licensed plumbers[6].

07What is the difference between an AI quotation and a written quotation?

The AI quotation assistant and computer make a preliminary estimate based on the public price, for reference only; the written quotation is based on the master's on-site measurement and understanding of the condition of the old pipes and walls, and is the basis for the final price.

08How much does it cost to renovate a small 6 ft kitchen?

At our published rates, replacing the cabinets and solid-surface worktop costs about HK$23,180. A full refit with waterproofing, plumbing, tiling, a suspended ceiling and electrical work costs about HK$63,730. Both are hypothetical examples, subject to site measurement (see published rates).

09Do ENF-grade kitchen cabinets cost extra?

From 2026, we use ENF-grade board as standard for all bespoke furniture at no extra charge. ENF board has very low formaldehyde emissions (≤0.025 mg/m³). It still emits some formaldehyde, so ventilate before moving in[9].

10What does kitchen waterproofing include?

Kitchen waterproofing (C03) costs HK$4,300 per kitchen. It includes two coats of Sika 107 over the whole floor, a 150 mm upstand at floor-to-wall junctions and reinforcement around the sink (see published rates).

11Do I have to arrange the application to replace drinking-water pipes myself?

No. Our partner licensed plumber applies to the Water Supplies Department for approval. HK Create Design coordinates the process for you.

12Do kitchen cabinets come with a warranty?

Yes. The one-year warranty covers damage other than deliberate damage, including detached hinges, loose runners, screws coming loose and swollen doors.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Consumer Council: Home Improvement Services Research Report Press Release Accessed: 2026-11-01
  2. [2]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-01
  3. [3]Electrical and Mechanical Services Department: Safety Instructions for Residential Gas Cooking Stoves Accessed: 2026-11-01
  4. [4]Electrical and Mechanical Services Department: Household Electrical Safety Manual - New installation, addition or modification Accessed: 2026-11-01
  5. [5]Electrical and Mechanical Services Department: Household Electrical Safety Manual - General Installation Instructions Accessed: 2026-11-01
  6. [6]Water Supplies Department: Licensed Plumber Accessed: 2026-11-01
  7. [7]Environmental Protection Department: Construction Waste Disposal Charging Scheme Accessed: 2026-11-01
  8. [8]Consumer Council: Complaint Figures Accessed: 2026-11-01
  9. PricesHK Create Design 2026 detailed project budget and public price list Accessed: 2026-11-01