01

When a partial renovation makes sense

First, a problem may be confined to one area, such as a bathroom leaking into the flat below, loose kitchen cabinet door hinges, mould on bedroom walls or a buckled living room floor. The Buildings Department identifies pipework, bathroom waterproofing and exterior walls as common sources of seepage[2]. Find and repair the source. The rest of the flat may need little work.

Second, you may want to spread costs over several years. A whole-home refit may cost HK$200,000–300,000, whereas working on one or two areas at a time can bring each phase down to tens of thousands of dollars. Third, you may want to stay at home. A whole-home refit often means moving out for one or two months, with extra rent and moving costs. For many partial refits you can stay in the flat.

Fourth, you may have bought a resale flat that the previous owner kept in good condition. If you'd like to Floor replacement in a different colour or add a wardrobe, a full strip-out may be unnecessary.

In an older flat with worn wiring and pipes, a partial refit may only treat the symptoms. Have the electrical and plumbing systems inspected before choosing between a partial and a full refit.

  • Problems confined to particular areas
  • Spread work over several years on a limited budget
  • Stay at home during the work
  • Inspect electrics and pipework first in an older flat
Project photo of kitchen cabinet installation | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

02

Option 1: Bathroom only

Bathrooms are a common starting point as leaks, slow drainage and cracked tiles affect both daily life and neighbours. A full example includes A10 bathroom strip-out and waste removal at HK$9,950, and C02 bathroom waterproofing at HK$4,850 including a 24-hour ponding test. Around 185 sq ft of wall and floor tiling costs HK$14,430, G04 complete hot and cold pipework HK$13,300, K06 installation of the sanitary fittings and hardware HK$5,650, a 2 ft FUR25 vanity base unit HK$6,500, and K05 shower screen installation HK$860[1]. Total: about HK$55,540. Adding a standard aluminium suspended ceiling (F05, HK$3,650) brings this to about HK$59,190. The shower screen and toilet themselves are priced separately.[1]

For a dated bathroom without leaks, the tiles can stay. D08 epoxy regrouting costs HK$21 per sq ft, E05 local mould treatment and repainting HK$1,250 per wall, K03 shower mixer replacement HK$970 per set and K01 toilet replacement HK$1,300 each[1]. A few thousand dollars can refresh the room.

Plan for the time without a working bathroom. Strip-out through to installation usually takes seven to ten working days. Use a second bathroom if you have one. Otherwise, discuss keeping the toilet in place until the latest practical stage or staying with relatives for a few days.

Test the waterproofing before tiling. C02 includes a 24-hour ponding test, during which the floor drain is sealed, the floor is filled with water, and the water level and ceiling below are monitored[1]. Start tiling after the test confirms there are no leaks, even if time is tight.

  • Full bathroom refit: about HK$55,540
  • Refresh with existing tiles: from a few thousand dollars
  • Arrange alternative facilities for 7–10 days
  • Test waterproofing before tiling
Six partial renovation options compared

You can swipe left or right on your phone to view the complete table.

PlanExample scopeExample totalDuration
BathroomFull refitAbout HK$55,5407–10 working days
Kitchen (cabinet replacement)6 ft each of wall cabinets, base cabinets and quartz worktopHK$28,2003–5 days
Kitchen (full refit)8 ft kitchen including waterproofing and plumbingAbout HK$74,2403–4 weeks
living and dining room200 sq ft, including painting, flooring, furniture and a lighting coveAbout HK$53,280About 2 weeks
Main bedroom100 sq ft, including painting, flooring and a wardrobeAbout HK$36,360About 1–2 weeks
floor400 sq ft of SPC flooringAbout HK$24,000About 2th
electricityInspection, distribution board, sockets and circuitAbout HK$14,7602–3 days

Based on HK Create Design's published 2026 prices. Final quantities and prices are confirmed by a site survey and written quotation. [1]

Bathroom-only renovation concept (design rendering) | HK Create Design
Design rendering of a bathroom-only refit. The final design depends on site measurements and the agreed drawings | HK Create Design Select an image to enlarge
Partial renovation budgets illustrated | HK Create Design
Partial renovation budgets at a glance | HK Create Design Select an image to enlarge

03

Option 2: Kitchen only

The first option is made-to-measure cabinets. HK$28,200 includes 6 linear ft of wall cabinets, 6 linear ft of base cabinets and a 6 linear ft quartz worktop. The cabinets use premium moisture-resistant ENF-grade boards. A Hong Kong designer measures on site, and the package includes VR renderings and design drawings.

The second option is a full refit. It includes A09 kitchen strip-out and waste removal at HK$9,950, C03 waterproofing at HK$4,300, wall and floor tiling, G03 complete hot and cold pipework at HK$13,300, plus new cabinets and worktop[1]. An 8 ft kitchen comes to about HK$74,240 and takes around three to four weeks in this example. Our kitchen renovation service page has a separate full strip-out example that includes a suspended ceiling and electrical work. Compare the work items you need.

Cabinet replacement is usually enough if the tiles are sound, there are no leaks and the pipes are free of rust. Consider a full refit if the area under the sink is often damp, wall tiles sound hollow or the old pipework is galvanised.

While the kitchen is out of use, plan for meals out or a temporary cooking area in the living room with a rice cooker and induction hob. Cabinet-only replacement usually interrupts kitchen use for three to five days. Move the fridge to the living room and pack crockery in boxes, then reorganise everything once the new cabinets are fitted.

  • 6 ft custom kitchen cabinets with quartz worktop: HK$28,200
  • Full refit: about HK$74,240 for an 8 ft kitchen
  • Choose cabinet replacement if tiles and pipes are sound
  • Plan temporary cooking arrangements
HK Create Design・Illustrated overviewSix partial renovation options
  1. BathroomPrioritise leaks and worn finishes.
  2. kitchenReplace cabinets or refit the whole kitchen.
  3. living and dining roomThe most visible room in the home.
  4. BedroomWardrobe storage and mould.
  5. floorSPC flooring in two days.
  6. electricitySafety first.
HK Create Design・Figures at a glancePartial renovation examples
  1. $55,540BathroomFull refit
  2. $53,280living and dining room200 sq ft
  3. $36,360Main bedroom100 sq ft

Examples based on HK Create Design's published 2026 rates.

「Define the scope of a partial refit. Record exactly which walls will be painted and the doorway where the new flooring will stop, so everyone knows what to expect at handover.」

Project supervisor, HK Create Design
Kitchen and bathroom budgets comparing 6 ft of kitchen cabinets, a full 8 ft kitchen refit and a bathroom with a suspended ceiling
Example budgets. The HK$28,200 package includes 6 ft each of wall cabinets, base cabinets and quartz worktop. The full 8 ft kitchen example is around HK$74,240. The bathroom example with an aluminium suspended ceiling is around HK$59,190. It includes installation of the shower screen and toilet, with both products supplied at extra cost. Final prices are confirmed in writing after measurement. Select an image to enlarge

04

Option 3: Living and dining room

Renewing the living and dining room can change how the whole flat feels, as this is where most guests and family spend time. Common items are preparing and painting walls, SPC flooring, a TV unit with shelves, a sideboard and a lighting cove.

A 200 sq ft example includes E02 filling, damp-resistant treatment, sanding and painting of 600 sq ft at HK$12,600, J01 SPC flooring over 200 sq ft at HK$12,000, a 6 ft FUR10 low TV unit at HK$7,500, 4 ft of FUR09 open shelving at HK$7,800, a 4 ft FUR13 sideboard at HK$5,400, a 12 ft F03 lighting cove at HK$5,520, and 12 ft of H07 strip lighting at HK$1,800, plus one delivery[1]. The total comes to about HK$53,280.

You can usually stay at home for a living and dining room refit. Move the furniture into bedrooms for painting. Flooring generally takes one or two days and furniture installation one day. The overall programme is around two weeks.

SPC flooring and underlay add around 5–6 mm, creating a step where the living room meets adjoining rooms. Use transition strips at doorways and check the clearance beneath doors so they do not scrape the new floor. If necessary, ask the installer to plane the bottom edge so the door swings freely.

  • 200 sq ft living and dining room: about HK$53,280
  • About two weeks, with the flat occupied
  • Allow for different floor levels between rooms
  • Fit transition strips at doorways
Example totals for six partial renovation options(Unit:HK$)
Kitchen (full refit)
HK$74,240
Bathroom
HK$55,540
living and dining room
HK$53,280
Main bedroom
HK$36,360
Kitchen (cabinet replacement)
HK$28,200
Flooring, 400 sq ft
HK$24,000
electricity
HK$14,760

Based on HK Create Design's published 2026 prices. [1]

Site photo of a completed bathroom renovation | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge

05

Option 4: Bedroom

Bedroom refits often address limited wardrobe space, mouldy walls or the changing needs of a growing child. For a 100 sq ft main bedroom, allow HK$6,300 for E02 preparation and painting of around 300 sq ft, HK$12,000 for J01 SPC flooring with a 200 sq ft minimum, and HK$17,400 for a 6 ft FUR05 wardrobe, plus one delivery[1]. The total comes to about HK$36,360.

SPC flooring has a minimum billable area of 200 sq ft[1]. A 100 sq ft bedroom is still charged at 200 sq ft. Laying other bedrooms or the living room at the same time can reduce your effective price per square foot.

Before painting mouldy walls, find the source. Check for external wall or window leaks and excessive indoor humidity. The Buildings Department identifies exterior walls and pipes as possible sources[2]. If the source remains, mould can return after repainting. E01 stripping, skim coating, damp-resistant treatment, sanding and painting costs HK$39 per sq ft and suits peeling, mould-affected or previously water-damaged walls[1].

For a child's room, consider a Platform beds with a desk. FUR06 platform beds cost HK$340 per sq ft and FUR08 desks are HK$1,850 per linear ft[1]. Store toys and books under the bed and choose a desk the child can still use in secondary school.

  • 100 sq ft main bedroom: about HK$36,360
  • SPC minimum: 200 sq ft
  • Find the cause of mould first
  • Child's room: platform bed with desk
Bedroom-only renovation concept (design rendering) | HK Create Design
Design rendering of a bedroom-only refit. The final design depends on site measurement and the agreed drawings | HK Create Design Select an image to enlarge

06

Option 5: Flooring only

Flooring can make a quick visual difference. SPC flooring can be laid over existing tiles without a strip-out or tile rubble, usually in one or two days. J01 costs HK$60 per sq ft, including underlay, click-fit installation and transition strips[1]. For 400 sq ft, allow around HK$24,000.

The Consumer Council compared floor types and advises choosing according to water resistance, wear and maintenance requirements[6]. SPC is water- and scratch-resistant. J02 laminate at HK$82 per sq ft offers a softer feel underfoot but is more sensitive to water[1]. For a tiled finish, allow more time and money for removing and replacing the old tiles.

Before laying SPC, check that the existing tiles are level and sound. Treat any hollow spots or uneven sections first. J03 self-levelling compound for floor levelling is HK$22 per sq ft[1]. An uneven base can leave noisy or uneven flooring.

In an occupied home, move furniture in stages. Lay the bedroom floors first with the furniture in the living room, then reverse the arrangement. A 400 sq ft flat generally takes two days. J04 skirting costs HK$10 per linear ft[1]. New skirting can finish the edges neatly.

  • SPC over existing tiles: HK$60 per sq ft
  • 400 sq ft: around HK$24,000 and two days
  • Address hollow or uneven areas first
  • Move furniture in stages
Worked example 1

Example: occupied 200 sq ft living and dining room

Assumptions

  • Walls generally sound
  • Existing tiles level
  • TV unit, shelves, sideboard and lighting cove

How to calculate quantities

  1. E02:600 × HK$21 = HK$12,600;J01:200 × HK$60 = HK$12,000
  2. FUR10:6 × HK$1,250 = HK$7,500;FUR09:4 × HK$1,950 = HK$7,800
  3. FUR13:4 × HK$1,350 = HK$5,400
  4. F03:12 × HK$460 = HK$5,520;H07:12 × HK$150 = HK$1,800
  5. FUR42:HK$660
  6. Total: HK$53,280

Example total of about HK$53,280 over approximately two weeks, with the residents staying at home.

Lighting cove painting is included in the wall painting allowance. The site measurements and written quotation confirm the final price. [1]

Use your square footage instead and see a reference budget
Made-to-measure wardrobe after installation | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge

07

Option 6: Electrical work only

Electrical improvements are largely concealed but important for safety. Older flats may have a fuse box without earth-leakage protection, too few sockets and frequent tripping. An H01 electrical inspection costs HK$770 and includes a preliminary report[1]. This is the starting point for a partial electrical refit.

Typical work includes H09 distribution board replacement to replace an old fuse box with an MCB/RCD board at HK$6,800, H02 new 13 A sockets at HK$640 each, and H06 dedicated circuits for water heaters, induction hobs or ovens at HK$3,350 each[1]. The Electrical and Mechanical Services Department says a registered electrical contractor must carry out additions or alterations to fixed installations and issue a Work Completion Certificate[7].

Rewiring involves chasing the walls and making good the plaster afterwards. Complete electrical work before painting to avoid paying for paint repairs.

One typical project includes an inspection, distribution board replacement, six new sockets and one dedicated circuit for about HK$14,760 (HK$770 + HK$6,800 + HK$3,840 + HK$3,350)[1]. It generally takes two to three days.

  • H01 electrical inspection: HK$770
  • H09 distribution board replacement: HK$6,800
  • Use a registered electrical contractor and obtain a Work Completion Certificate
  • Complete electrics before painting
Checklist for living at home during renovation

You can swipe left or right on your phone to view the complete table.

PropertypracticeReasonResponsible person
Protect separate zonesSeparate areas using sheeting and protective boardsReduce dustContractor
Hours for noisy workSchedule loud tasks during daytimeConsider neighbours and family membersContractor and owner
VentilationOpen windows during and after workDisperse odours from paint and furnitureOwner
Alternative bathroom arrangementsRetain the toilet until the latest practical stage or stay elsewhere temporarilyBathroom out of use during renovationOwner and contractor
Temporary cooking arrangementsRice cooker and induction hobKitchen out of useOwner
SafetyKeep tools away from childrenPrevent accidentsContractor and owner

Typical arrangements for HK Create Design projects in occupied homes. [3][4]

Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge

08

Reducing disruption while you live at home

If you stay in the flat, start by separating the work and living areas with tape and protective sheeting. Cover furniture with plastic and lay protection boards over the floors. Our crew tidies the work area at the end of each day so it is easier to use the flat in the evening.

Agree hours for noisy work. The Environmental Protection Department's FAQs on home renovation noise ask residents to consider their neighbours[3]. Building management usually sets permitted working hours. Group drilling and tile removal in daytime so family members, including Older residents and babies, can go out during the noisiest work.

Ventilate during and after the work. Paint and new furniture can give off odours. The Environmental Protection Department notes that renovation materials can affect indoor air quality[4]. Keep windows open when possible, and consider sleeping in an unaffected, well-ventilated room.

Store tools and materials out of children's reach. During electrical work, follow the contractor's instructions and leave the main switch to the electrician.

  • Separate work and living areas
  • Schedule loud tasks during daytime
  • Maintain ventilation
  • Keep tools and materials out of children's reach

09

Matching new work to existing finishes

A common problem is a visible mismatch at the edge of the new work. New paint colours can differ from the old walls, floor levels can change, and the woodgrain on new cabinet doors may differ from the old doors.

For a consistent colour, paint a complete wall or room. To match an existing colour, take the old paint tin or a small paint chip to the supplier.

SPC and underlay add around 5–6 mm, so use a transition strip at bedroom doors. If you are replacing tiles, differences in thickness between old and new tiles may require adjustments to the mortar bed.

For additional cabinets, choose a board colour close to the existing finish or use a deliberate contrast. HK Create Design has four books of board samples, and you can take swatches home to compare with your furniture.

  • Paint one complete wall at a time
  • Fit transition strips at doorways with SPC flooring
  • Check thickness when replacing tiles
  • Take board samples home to match furniture
Breakdown of the full bathroom refit example(Unit:HK$)
tiling
HK$14,430
water pipe
HK$13,300
Strip-out
HK$9,950
Bathroom vanity
HK$6,500
Sanitary fittings and hardware
HK$5,650
Waterproofing
HK$4,850
Shower screen
HK$860

Based on HK Create Design's published 2026 prices. [1]

10

Do you need a renovation company for a partial refit?

A partial refit can involve several trades. Bathrooms can require strip-out, masonry, waterproofing, plumbing and fixture installation. A living room can need painters, flooring installers, carpenters and electricians. One company can coordinate the order of work and make responsibility for each task clear.

The Consumer Council recommends checking quotations in detail across 12 areas, including the scope, material brands and models, quantities, payment and warranties[5]. For a partial refit, specify the boundaries too, such as which walls will be painted and the doorway where the new floor ends.

HK Create Design's minimum charge per job is HK$2,000[1]. Some items have a minimum quantity or charge, such as 200 sq ft for SPC flooring or HK$3,700 for E03 repainting[1]. Combining several small jobs in one visit often costs less.

The government encourages homeowners to retain usable materials and reduce renovation waste[9]. A partial refit can help by replacing only the worn-out areas.

  • Have one company coordinate the trades
  • Set out the work boundaries in writing
  • Check minimum charges and quantities
  • Retaining usable finishes reduces waste

11

Common partial renovation mistakes

A common mistake is repainting before investigating mould or ceiling water marks. They can return within months. Seepage may come from an upstairs bathroom, an exterior wall or pipework[2]. Establish the source, notify the upstairs owner or management office where needed, and resolve it before renewing the finish.

Another mistake is defining the area too narrowly. A single fresh wall may not match its neighbours, and half a new floor can leave a difficult threshold. Treat a complete room or living and dining area as one project to get an even finish.

Allow for minimum charges and quantities. Ordering separate visits from different trades can mean paying minimum and transport charges each time. HK Create Design currently offers free on-site measurement for projects with two or more work items, so it can be more economical to group them[1].

Plan ahead. If you install a living room floor now and refit the bathroom in two years, the floor will need protection during bathroom demolition. Tell your designer about future phases so the current work allows for them.

Before work starts, move valuables and electronics out of the area or cover them well. Dust inside televisions, speakers and computers can be difficult to remove.

  • Fix the cause before renewing finishes
  • Work on one complete area at a time
  • Group small jobs to reduce costs
  • Plan for the next few years
  • Put valuables away before work starts
Worked example 2

Example: 100 sq ft main bedroom refit

Assumptions

  • Walls generally sound
  • SPC flooring billed at the 200 sq ft minimum
  • 6 ft wardrobe

How to calculate quantities

  1. E02:300 × HK$21 = HK$6,300
  2. J01: 200 × HK$60 = HK$12,000 (minimum quantity)
  3. FUR05:6 × HK$2,900 = HK$17,400
  4. FUR42:HK$660
  5. Total: HK$36,360

Example total of about HK$36,360.

Laying other rooms at the same time brings down the average SPC cost per square foot. Address the source of any mould before finishing the walls. [1]

Use your square footage instead and see a reference budget
HK Create Design・Work sequenceOrder of work for a phased renovation
  1. Electrics and plumbingStart with concealed work
  2. Kitchen and bathroomWet trades
  3. Painting and flooringSurface finishes
  4. furnitureInstall last
Illustrated partial renovation checklist | HK Create Design
Partial renovation checklist | HK Create Design Select an image to enlarge

12

Planning a renovation in stages

When renovating over several years, start with concealed work and wet trades, then move on to finishes and dry trades. A useful order is electrics and plumbing, kitchen and bathroom, painting and flooring, and finally furniture.

Wiring requires wall chases, so painting first means paying to repaint. Refitting a bathroom later can also expose a newly laid floor to rubble, dust and scratches.

A typical three-year plan addresses the electrical inspection, distribution board and bathroom in year one, prioritising safety and leaks. Tackle the kitchen in year two, then whole-home painting, flooring and furniture in year three. The example allows around HK$50,000–80,000 per year.

Keep quotes, photos and completion certificates for each phase. They help the next contractor avoid repeating work or damaging earlier installations. At the start of each phase, check earlier work, such as bathroom sealant and distribution board labels, and report any issues while the warranty applies.

  • Concealed work and wet trades first
  • Finishes and dry trades later
  • Three-year plan: safety, kitchen, then finishes
  • Keep records for every phase

13

Arrange a partial renovation with HK Create Design

HK Create Design has handled renovations of all sizes since 2019, with designers and tradespeople who have over 15 years of experience. Partial renovations also receive design work and a quotation. Our Custom furniture service includes design and whole-home drawings.

Send photos and dimensions to 5243 7747 on WhatsApp for a free preliminary estimate. Site measurement is free for projects with two or more work items until 31 December 2026. After that, the L04 site visit is HK$500, fully credited against a confirmed order[1].

Visit Shop 16, G/F, Fu Yau Building, 61 Po Kong Village Road, Wong Tai Sin, Kowloon, by appointment to see board, flooring and tile samples. All works come with a one-year warranty.

  • WhatsApp 5243 7747
  • Design and quotations for partial renovations
  • Free measurement for a limited period, then HK$500 credited against a confirmed order
  • One-year warranty

Advice from our tradespeople

「Define the scope of a partial refit. Record exactly which walls will be painted and the doorway where the new flooring will stop, so everyone knows what to expect at handover.」

Project supervisor, HK Create DesignHK Create Design project team

「When a family stays at home during a bathroom refit, we try to keep the toilet in place until the latest practical stage. We test the waterproofing for a full 24 hours and begin tiling only when the test confirms there are no leaks.」

Masonry and waterproofing specialist, HK Create DesignHK Create Design project team

FAQ

9 practical questions answered

01How much does a bathroom-only refit cost?

The full example costs about HK$55,540 for strip-out, waterproofing, tiling, pipework, sanitary fittings and a vanity. A refresh with existing tiles can start at a few thousand dollars[1].

02Can I stay at home during a partial renovation?

For most living room, bedroom, flooring and electrical projects you can. Arrange alternative bathroom facilities for 7–10 days during a bathroom refit.

03How much is SPC flooring for one room?

At HK$60 per sq ft, J01 has a 200 sq ft minimum, so the minimum is HK$12,000. Consider laying other areas at the same time[1].

04Can I repaint just one wall?

Yes. Allow for colour differences and paint a complete wall or room. The minimum charge for E03 repainting is HK$3,700[1].

05What order should renovation phases follow?

Start with electrics and plumbing, then the kitchen and bathroom. Finish with painting, floors and furniture. This allows concealed work and wet trades to finish before surface finishes and dry trades.

06Can I simply paint over mould?

First identify the source of the leak or humidity[2]. After it is resolved, E01 stripping, skim coating, damp-resistant treatment and painting costs HK$39 per sq ft[1].

07Should I renovate selected rooms or the whole flat?

If only a few areas need attention and wiring and pipes are sound, a partial renovation may be enough. In an older flat where the pipes and wiring have deteriorated or several areas need work, a whole-home renovation usually saves time and reduces overall costs.

08How much does it cost to replace kitchen cabinets while keeping the tiles?

The first option is made-to-measure cabinets. HK$28,200 includes 6 linear ft of wall cabinets, 6 linear ft of base cabinets and a 6 linear ft quartz worktop. The cabinets use premium moisture-resistant ENF-grade boards. A Hong Kong designer measures on site, and the package includes VR renderings and design drawings.

09How much does a partial electrical refit cost?

The example, including an inspection, distribution board replacement, six new sockets and one dedicated circuit, comes to about HK$14,760[1].

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]HK Create Design published 2026 rates and work item descriptions Accessed: 2026-11-03
  2. [2]Buildings Department: water seepage FAQs Accessed: 2026-11-03
  3. [3]Environmental Protection Department: FAQs on noise from renovation in residential premises Accessed: 2026-11-03
  4. [4]Environmental Protection Department: Indoor Air Quality Information Centre FAQs Accessed: 2026-11-03
  5. [5]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-03
  6. [6]Consumer Council guide to choosing flooring Accessed: 2026-11-03
  7. [7]Electrical and Mechanical Services Department: Household Electrical Safety Handbook, new installations, additions and alterations Accessed: 2026-11-03
  8. [8]Buildings Department: 2026–27 Estimates reply on numbers of private buildings by age Accessed: 2026-11-03
  9. [9]Hong Kong GovHK: Environmentally Friendly Tips for Home Renovation Accessed: 2026-11-03