Cement & Cement-based Mortars · Bagged pre-mixed concrete
OPTIMIX PC30 / PC40 / PC45 / PC60 Packaged Concrete
OPTIMIX PC30 / PC40 / PC45 / PC60 Packaged Concrete(PC30 / PC40 / PC45 / PC60)
Materials can be purchased separately from HK Create Design. Give us the quantity and district for unit prices, lead times and kerbside or upstairs delivery rates.
Small renovation pours such as floor repairs, air-conditioning plinths and thresholds may be too small for a concrete truck, while a site mix is harder to proportion consistently. The OPTIMIX PC range comes in 40 kg bags of factory-blended cement and coarse aggregate to mix with clean water. The manufacturer states that PC30 (Standard), PC40 (Premium), PC45 (Superior) and PC60 (Grade 60) meet Hong Kong’s Code of Practice for Structural Use of Concrete 2013. Waterproof versions are PC30W, PC40W, PC45W and PC60W. The January 2026 data sheet gives grades C30/10, C40/10, C45/10 and C60/10, with 28-day compressive strengths above 45, 55, 60 and 75 MPa respectively. It lists a 75 mm slump, 4–6 hour setting time, 10 mm maximum aggregate and chloride content of 0.02% by cement weight. Each PC30 bag takes 3.4–3.8 L of water and yields about 19 litres. Mixed density is 2,350 kg/m³ and shelf life is 6 months. For waterproof versions, 28-day initial surface absorption (ISAT at 60 minutes) is about 0.01 ml/m²·s. The range is designed for small to medium pours, particularly where a mixer truck cannot deliver. Residential structural work requires assessment by a qualified person. We generally use these products for non-structural or approved small-scale work.

Buy materials: kerbside handover or delivery to your floor
The quote lists materials, delivery and any applicable upstairs delivery fee separately. Choose a handover option to request a price.
Add other materials (optional)
Small concrete fills, such as large holes in floors and thresholds
HK Create Design · Materials and upstairs delivery quotes · 5243 7747
How many bags of concrete are needed per cubic metre?
Each 40 kg PC-series bag has a manufacturer’s indicative yield of about 19 litres. Choose the grade specified for the project and estimate the bag count from the volume to fill.
| Volume to fill | Calculated at 19 L per bag |
|---|---|
| 0.10 m³(100 L) | Approximately 5.26 bags. Order 6 bags. |
| 0.25 m³(250 L) | Approximately 13.16 bags. Order 14 bags. |
| 0.50 m³(500 L) | Approximately 26.32 bags. Order 27 bags. |
Multiply length, width and average depth in metres to get cubic metres. Round up to whole bags and allow extra for waste. Use the concrete grade specified in the project drawings.
Check the manufacturer's data sheet and application conditions
OPTIMIX PC30 Pre-mixed Concrete · Application illustration
How is a small concrete pour carried out?


Illustrative application result. Colour, detailing and drying conditions vary on site.
- Material benefits
- The factory preblends the cement and coarse aggregate, so small jobs can be mixed a bag at a time.
- Where to use it
- For small pours such as thresholds and plinths, particularly where a concrete truck cannot reach. For load-bearing work, use the grade specified by the design.
- Application method
- Mix with the water quantity specified for the selected model, place in the form, compact, finish and cure as directed.
OPTIMIX PC30 Pre-mixed Concrete application steps

- For fully bonded application, clean the base of dust, oil and dirt. Use SF80 primer or PROCRETE polymer bonding emulsion if required.
- Use rigid, leak-tight formwork and apply a release agent if required.
- Mix in a drum, vertical-shaft or free-fall mixer for at least 5 minutes. Hand mixing takes longer. Each PC30 bag requires 3.4–3.8 L of clean water.
- Pour into the formwork or onto the base within the working time. Compact using a vibrator to fill the space without trapped air.
- Sprinkle with water and cover with polyethylene sheeting for 3 days, or apply a curing membrane.
Manufacturer’s specifications
View PC30 / PC40 / PC45 / PC60 Manufacturer's information and sources
| Item | Specification |
|---|---|
| Grade | PC30:C30/10;PC40:C40/10;PC45:C45/10;PC60:C60/10 [1] |
| 28-day compressive strength | PC30 > 45 MPa;PC40 > 55 MPa;PC45 > 60 MPa;PC60 > 75 MPa [1] |
| Slump/setting time | 75 mm / 4–6 hours [1] |
| Maximum aggregate diameter | 10 mm [1] |
| Chloride content (by weight of cement) | 0.02% for all four products [1] |
| cement content | PC30 430 kg/m³;PC40 470 kg/m³;PC45 547 kg/m³;PC60 510 kg/m³ [1] |
| Mixing water per bag | PC30 and PC60: 3.4–3.8 L. PC40 and PC45: 3.6–4.0 L. [1] |
| Yield and pack size | About 19 L per 40 kg bag [1] |
| Mixed density / shelf life | 2,350 kg/m³; 6 months [1] |
| Surface water absorption of waterproof models | PC30W / PC40W / PC45W / PC60W: 28-day ISAT (60 minutes), approximately 0.01 ml/m²·s [1] |
| Meets requirements | Hong Kong Buildings Department Code of Practice for Concrete Structures 2013 [1] |
Suitable applications
- Small concrete fills, such as large holes in floors and thresholds
- Non-structural plinths for air conditioners or equipment
- Small concrete pours where a mixer truck cannot reach
Applications to avoid
- Structural changes that have not been assessed by a competent person
- Large concrete pours (consider a ready-mix concrete delivery)
How we use this material on site
For small concrete fills we mix the PC range with the specified water quantity, compact with a vibrator or tamping rod, then water and cover with plastic sheet to cure for 3 days.
View the work details Hong Kong strip-out work, site protection and debris removalWe clean deep floor voids or notches left after demolition, treat the bonding surface and fill them with bagged concrete.
View the work details Hong Kong commercial renovation, shopping mall and retail painting worksFor equipment bases and thresholds in shops, we choose an appropriate grade and follow the engineer's requirements where relevant.
View the work detailsApplication notes
- Avoid adding excess water on site or mixing in other materials unless approved by the manufacturer’s technical department.
- The product is alkaline and can irritate skin. Wear gloves and eye protection during application.
- Works involving structures must be assessed and approved by a competent person.
Cement and cement-based mortars Other products
Specifications are drawn from the manufacturer’s website or technical data sheets (TDS). Refer to the latest manufacturer’s information for updates. HK Create Design is independent of the brands, whose names and trademarks belong to their respective owners.