01

Why custom furniture has several stages

You can buy ready-made furniture after seeing it in the shop, whileBespoke furniturestarts with design and then moves to production. Each piece is made to the dimensions and needs of your flat, so the survey, drawings and materials must be confirmed before fabrication.

The survey confirms dimensions, design drawings confirm appearance and function, and material selection confirms boards, colours and fittings. Production drawings instruct the factory. Installation and handover establish whether the finished pieces match the design.

The Consumer Council advises comparing past projects, reputation, commitments and which services are included, such as measurement, design and drawings[4]. Establish which stages the service includes at the outset.

  • Design before production
  • Made to measure
  • Purpose of each stage
  • Confirm the service scope
HK Create Design・Illustrated overviewPrepare before enquiring
  1. Address and areaEstate and floor area.
  2. Floor planFlat layout plan.
  3. PhotosEvery wall.
  4. Budget and datesPrice and timing.
Custom furniture throughout a flat | HK Create Design
Site photo: Custom furniture on site. HK Create Design. Select an image to enlarge

02

1. WhatsApp enquiry

Start on WhatsApp with the address or estate, saleable area, any floor plan, furniture list, photos, budget range and target completion date. These details help produce a more accurate initial estimate.

For a new or public housing flat, provide the developer’s or Housing Authority’s layout plan. ForOlder flat renovation, photograph each wall, window ledge, beam, column and switch. More detail helps the designer prepare an initial estimate.

WhatsApp HK Create Design at 5243 7747. After discussing the requirements, arrange an on-site measurement.

  • Address and floor area
  • Floor plan
  • Furniture list
  • Photos of the property
  • Budget and target date
Custom furniture stages: key figures illustrated | HK Create Design
Custom furniture stages: key figures at a glance | HK Create Design Select an image to enlarge

03

2. On-site measurement

On site, the surveyor measures each wall, height, beam, column, sill, pipe, switch and air conditioner. They also check that walls are plumb and floors level.

HK Create Design offers free on-site measurement for two or more items of work through 31 December 2026. Otherwise the HK$500 survey fee is credited against an order.

If plastering, tiling or partition changes are under way, take the final measurements after wet trades finish and walls and floors are ready, to avoid dimensional changes.

Describe how you live: hanging versus folded clothes, number of shoes, mattress thickness, TV size and appliances that must fit inside cabinets. Mattress thickness, for example, affects thePlatform bedsplatform and bedside cabinet height. TV size affects cabinet width and cable routes. If you fold most clothes, allow more shelves and drawers. If you hang more, allow more rails.

  • Measure walls, beams, columns and window ledges
  • Measure pipes and switches
  • Free measurement for two or more items of work
  • Final measurement after wet trades
  • Explain everyday habits
Eight-stage custom furniture timeline

You can swipe left or right on your phone to view the complete table.

stepscontentIndicative timing
1. EnquiryDiscuss the requirements on WhatsAppSame day
2. Site measurementOn-site measurementBy appointment
3. Design and quotationDrawings, VR renderings and quotationDepends on the number of revisions
4. Choose materialsBoard, colours and hardwareDepends on selection time
5. Production drawingsCheck and signProduction starts after owner approval
6. ProductionFactory cutting and assemblyAbout two to four weeks
7. InstallationDelivery and installationOne to several days
8. HandoverDefects and warrantyAfter installation

Timing depends on the project and confirmed arrangements. [1]

HK Create Design・Work sequenceEight steps to custom furniture
  1. EnquiryWhatsApp
  2. Site measurementSite visit
  3. DesignVR renderings
  4. Choose materialsColour samples and fittings
  5. Production drawingsSign
  6. Manufacture2–4 weeks
  7. InstallationDelivery
  8. AcceptanceWarranty

「“Clients who know their requirements at the survey and reply to the drawings within a day or two can sometimes cut the overall time in half.”」

Head of Design, HK Create Design
On-site measurement (design rendering) | HK Create Design
Design illustration: On-site measurement. The final design follows the site measurements and design drawings. HK Create Design. Select an image to enlarge

04

3. Design drawings and quotation

After taking measurements, the designer prepares the drawings and quotation. HK Create Design's custom furniture service includes design and full drawings for the flat: floor plans, ventilation, fire services, plumbing and electrical layouts, furniture designs, VR visualisations and production drawings.

VR renderings show colour, scale and how the furniture fits before work begins. Check the walkway, door swings, daylight and access to windows.

The quote should show dimensions, cabinet type, board, doors, hardware, quantity and unit price for each item. HK Create Design’s 2026 rates include wardrobes at HK$2,900 per linear foot, platform beds at HK$340 per sq ft and low TV cabinets at HK$1,250 per linear foot[1].

Designs normally go through one or two rounds of revisions. Make changes before production where possible. Use a tape measure at home to check the proposed desk height, wardrobe depth and walkway width before approval.

  • Floor plans and design drawings
  • VR renderings
  • Itemised quotation
  • Revise before work begins

05

4. Choose board, colours and fittings

Once the design direction is agreed, choose materials. HK Create Design uses ENF board as standard and moisture-resistant board in wet areas. View physical samples for colour and grain at the showroom.

Standard soft-close hinges are included. Optional FUR31 Blum or Hettich hinges cost HK$380 each, and FUR32 TANDEMBOX costs HK$1,500 per set[1]. Handles are available in plated or PVD finishes, or choose a handleless front.

Record each sample number and hardware model. The Consumer Council recommends receiving detailed drawings, dimensions, material samples and colours for selection and signed approval after agreeing the custom furniture quotation[2].

  • ENF-grade board as standard
  • See colour samples at the showroom
  • Choose hardware upgrades
  • Record sample and model numbers
Custom storage cabinets throughout a flat | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge

06

5. Approve production drawings

Production drawings guide factory cutting. Check each piece’s precise dimensions, board, colour, hardware, drilled openings and shelf positions.

Check survey dimensions, door swings, drawer and shelf quantities, switches, sockets and cable openings, and confirm colours and hardware model numbers.

Sign once everything is correct. The Consumer Council recommends including specific design or material requirements in the contract and keeping the furniture drawings[3]. Changes after signing the production drawings may require panels to be cut again at extra cost.

  • Check dimensions
  • Check door swings
  • Check shelves and drawers
  • Check sockets and cable routes
  • Sign and keep a copy
Furniture cost breakdown for a 400 sq ft flat (HK$)(Unit:HK$)
6 ft wardrobe
$17,400
4 ft wardrobe
$11,600
Platform beds
$8,840
TV cabinets
$7,500
Shoe cabinet
$5,800
Delivery
$660

HK Create Design’s published prices for 2026. [1]

HK Create Design・Figures at a glanceIndicative time
  1. 2–4 weeksManufactureAfter drawing approval
  2. 4–8 weeksThroughout the projectEnquiry to installation
  3. One yearWarrantyAfter completion

Depends on the individual project.

07

6. Factory production, usually two to four weeks

Production normally takes two to four weeks after drawings are approved, depending on design and quantity. Simple wardrobes and bookcases are quicker than shaped fronts, lacquer or special hardware.

The factory cuts, edge-bands and drills the panels, preassembles some components and packages them. Owners can use this time for other trades such as painting and flooring.

Allow extra lead time around Lunar New Year, when factories may close. Order early if you plan to move in before the holiday. Summer and year-end are also busy periods, so book surveys and installation ahead.

  • Usually 2–4 weeks
  • Shaped doors take longer
  • Paint and lay flooring during production
  • Order ahead of holidays
Project photo of bespoke kitchen cabinets with worktop | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge
Factory production (design rendering) | HK Create Design
Design illustration: Furniture manufacturing in the workshop. The final design follows the site measurements and design drawings. HK Create Design. Select an image to enlarge

08

7. Delivery and installation

Delivery and installation are arranged after production. FUR42 delivery costs HK$660 per trip where the lift serves the flat directly. Split deliveries are charged per trip[1]. In walk-up buildings or where there is no lift, FUR43 stair carry costs HK$300 per floor[1]. If old cabinets require removal, FUR45 removal and disposal costs HK$170 per linear foot[1].

Before installation, complete painting and flooring, clean the floor, confirm air-conditioner and curtain-track positions and register the delivery and installation time with management.

One piece may take a few hours to install, while a whole flat can take one to several days. Drilling causes noise. The Environmental Protection Department’s residential renovation noise guidance advises consideration for neighbours[7], so schedule installation during the daytime.

Hong Kong’s rainy season is humid, with mean monthly relative humidity of around 81–83% from May to August[6]. In heavy rain, protect the packaging from water and unwrap indoors. Check for water marks, scratches and impact damage, then photograph and report any issues immediately.

  • Delivery: HK$660 per trip
  • Stair carry — HK$300 per floor
  • Remove old cabinets: HK$170 per linear ft
  • Complete painting and flooring first
  • Daytime installation
Furniture delivery and installation (design rendering) | HK Create Design
Design illustration: Furniture delivery and installation. The final design follows the site measurements and design drawings. HK Create Design. Select an image to enlarge

09

8. Handover and warranty

Check each piece. Doors and drawers should move smoothly, soft-close fittings should work, door gaps should be even, edge banding secure, colours true to the sample and wall junctions properly finished.

The Consumer Council recommends preparing a defects list and agreeing rectification and final payment arrangements with the contractor[3]. Photograph defects, list them and request follow-up.

The Consumer Council advises limiting the initial deposit to 40% of the contract sum and paying the balance after handover inspection[5]. HK Create Design offers a one-year warranty for workmanship and installation issues.

  • Test doors and drawers
  • Inspect door gaps and edge banding
  • Check against the colour sample
  • Prepare a defects list
  • One-year warranty
Worked example 1

Example: furnishing a whole 400 sq ft flat

Assumptions

  • 6 ft wardrobe and 4 ft wardrobe
  • 26 sq ft platform bed
  • 6 ft TV cabinet and 2 ft tall shoe cabinet
  • One delivery

How to calculate quantities

  1. 6 ft wardrobe: 6 × HK$2,900 = HK$17,400
  2. 4 ft wardrobe: 4 × HK$2,900 = HK$11,600
  3. Platform bed: 26 × HK$340 = HK$8,840
  4. TV cabinet: 6 × HK$1,250 = HK$7,500
  5. Shoe cabinet: 2 × HK$2,900 = HK$5,800
  6. Delivery: HK$660
  7. Total: HK$51,800

About HK$51,800.

Hardware upgrades excluded. Subject to measurement and written quotation. [1]

Use your square footage instead and see a reference budget
Made-to-measure TV and display cabinets | HK Create Design
Site photo: Custom TV cabinets on site. HK Create Design. Select an image to enlarge

10

How long does the whole process take?

The eight stages generally take four to eight weeks from first enquiry to installation. Design revisions, material selection and factory lead times affect the total.

With complete information, materials chosen promptly, one or two design rounds and two weeks’ production, the whole process can take around four weeks. Revisions, long-lead materials or holidays can extend it beyond eight.

Prepare plans and photos early, explain your needs at the survey, choose materials promptly and check the production drawings as soon as they arrive.

  • Usually 4–8 weeks
  • As little as about four weeks
  • Revisions can extend the timeline
  • Timely owner decisions can shorten the schedule

11

Coordinating with other renovation work

If the project also includesWhole-flat renovation, coordinate furniture with the other trades. A typical sequence is strip-out, plumbing and electrical work, plastering and tiling, ceilings, final measurement, painting, flooring, furniture installation and cleaning.

Furniture design and factory production can run alongside other renovation work. Coordinating them with painting and flooring helps ensure the flat is ready when furniture arrives.

Plan sockets behind the TV cabinet, USB outlets by the bedside and power for wardrobe lighting during electrical work. HK Create Design coordinates these points with the furniture on the building-services drawings.

  • Strip-out, building services and wet trades first
  • Final measurement
  • Install furniture after painting and flooring
  • Coordinate design and production with other work
  • Allow for electrical points
Delivery and installation charges

You can swipe left or right on your phone to view the complete table.

ItemUnit of measurePrice
FUR42 TransportoccasionHK$660
FUR43 walk-up building or no liftper floorHK$300
FUR45 Remove old cabinetslinear ftHK$170
FUR44 Special finishing or trimmingmHK$250

HK Create Design’s published prices for 2026. [1]

HK Create Design・Illustrated comparisonFactors that shorten or delay the work
  1. Speed upComplete details, prompt materials selection and drawing approval
  2. DelayDesign revisions, material delays or unfinished works

12

Common causes of delay

Delays arise if unfinished walls change dimensions after measurement, repeated design revisions require new drawings and quotations, or imported boards and special hardware have long lead times.

Unsigned production drawings hold up manufacturing. Unfinished paint or flooring can block installation, as can missing building management approval or an unregistered delivery slot.

Allow a buffer, move to the next stage once decisions are complete and discuss problems early. HK Create Design confirms the next step with you at each stage.

  • Unfinished walls
  • Repeated design revisions
  • Materials on order
  • Production drawings awaiting approval
  • Other works unfinished
  • Delivery unregistered with management

13

New flats, public housing and older flats

A new flat often needs little strip-out or wet work. Start with the developer’s plan before handover, measure on site after taking possession and release production when drawings are signed. Allow time for defect rectification and check management rules on work and deliveries.

For public housing, design discussions can begin once the allocation letter confirms the flat and layout. Check estate management requirements before installation and prioritise storage and circulation in smaller flats.

Older flats often need old furniture removed, services and wet works completed, then final measurement after walls and floors are ready. Check uneven surfaces and allow for scribing. FUR44 special detailing costs HK$250 per metre for false walls, ceiling-height infill and beam or column boxing[1].

Older walk-up buildings also require a stair-carry allowance. FUR43 costs HK$300 per floor[1]. Check stair turns for large pieces. They may need to be made in sections and assembled on site.

  • New flats: begin with the developer’s plan
  • Public housing: start after receiving the allocation letter
  • Older flats: measure after wet trades
  • Walk-up buildings: stairs and sectional delivery

14

What owners can do at each stage

For the enquiry, prepare plans, photos, a furniture list and budget. For the survey, provide access and lighting and explain your routine, mattress and TV sizes, clothing quantity and particular requirements.

Review drawings and VR renderings against how you will use each piece. Ask questions and group changes into one response. View physical samples in the showroom and in your flat’s light, then select any hardware upgrades.

At drawing approval, check dimensions, door swings, shelves, drawers and socket positions before signing. During manufacture, arrange painting and flooring and book delivery and installation with management.

Clear and clean the installation route and arrange for someone to attend. Inspect each piece at handover, list defects and settle the balance after resolving issues as agreed.

  • Enquiry: prepare the details
  • Survey: explain your requirements
  • Design: review the drawings carefully
  • Production drawings: check each item
  • Installation: arrange for someone to attend
  • Handover: prepare a defects list
Worked example 2

Example: replacing a wardrobe on the third floor of a walk-up

Assumptions

  • Third floor without a lift
  • Remove 6 ft of old wardrobe
  • One delivery

How to calculate quantities

  1. Delivery: HK$660
  2. Stair carry: 3 × HK$300 = HK$900
  3. Old cabinet removal: 6 × HK$170 = HK$1,020
  4. Total additional charges: HK$2,580

Additional charges are around HK$2,580, plus the cost of the new wardrobe.

Subject to site conditions and a written quotation. [1]

Use your square footage instead and see a reference budget

15

Contract and payment terms

Get a clear written quotation and contract before ordering custom furniture. When the Consumer Council tested renovation quotations from 11 companies, only 2 supplied detailed terms. Another 6 supplied basic terms, and 3 supplied none[2]. Contract terms vary, so ask for the agreed details in writing.

Specify dimensions, board, colours, hardware, quantities and prices for each piece, production and installation dates, payment stages, warranty period and cover, and the cost of changes.

The Consumer Council advises limiting the first deposit to 40% of the contract sum and cites the Hong Kong Institute of Building Inspectors’ recommendation to divide payments into four stages[5]. Pay the balance after the inspection and once all defects have been put right.

Confirm any changes during construction and their cost in writing[3], and keep a written record of the agreement.

  • Written quotation and contract
  • Specify dimensions and materials
  • Set out the timetable
  • First instalment: no more than 40%
  • Confirm changes in writing
Custom furniture stages: checklist illustrated | HK Create Design
Custom furniture stages: checklist | HK Create Design Select an image to enlarge

16

Installation-day arrangements

The day before, confirm the arrival time, parking and lift arrangements. Some buildings require advance registration or protective lift panels. Clear the route and installation area for the fitters.

Have someone available to confirm door swings, shelf heights and handle positions. If something changes on the day, agree and record it.

Fitters use protective sheeting or cardboard on floors and walls. Point out finishes and equipment that need particular care, such as new timber flooring, fresh paint and installed appliances.

Fitters remove packaging and wood offcuts. Carry out an initial inspection on site, point out defects and ventilate the flat before moving in.

  • Confirm time and parking
  • Register with building management
  • Clear loose items
  • Someone on site
  • Carry out an initial on-site inspection

17

Order custom furniture from HK Create Design

HK Create Design has served Hong Kong homeowners since 2019. Its designers and tradespeople with over 15 years’ experience provide floor plans, building-services drawings, furniture designs, VR renderings and production drawings. ENF board is standard.

For two or more work items, complimentary site measurement is offered until 31 December 2026. Showroom: Shop 16, G/F, Fu Yau Building, 61 Po Kong Village Road, Wong Tai Sin, Kowloon. WhatsApp 5243 7747. HK Create Design offers a one-year warranty and has a HK$2,000 minimum charge.

  • Design and full-home drawings included
  • Free site measurement for a limited time
  • WhatsApp 5243 7747

Advice from our tradespeople

「“Clients who know their requirements at the survey and reply to the drawings within a day or two can sometimes cut the overall time in half.”」

Head of Design, HK Create DesignHK Create Design team

「“I check the paint and flooring the day before installation. If the furniture goes in before the flooring is ready, having to take it out and refit it wastes everyone’s time.”」

Project supervisor, HK Create DesignHK Create Design project team

FAQ

14 practical questions answered

01How long does custom furniture take to make?

Production usually takes two to four weeks after approval of production drawings. The whole process from enquiry to installation is usually four to eight weeks.

02Is there a measurement fee?

On-site measurement is free for two or more work items through 31 December 2026. Otherwise it costs HK$500, credited on order.

03When is the best time for measurement?

Take final measurements after wet trades such as rendering and tiling are complete and walls and floors are finished.

04How many revisions can I make to the design drawings?

Usually one or two revision rounds are included. Changes after signing production drawings may cost extra.

05Is delivery charged separately?

FUR42 delivery: HK$660 per trip. Stair carry where there is no lift: HK$300 per floor[1].

06How is old cabinet removal charged?

FUR45 removal and disposal of old cabinets: HK$170 per linear foot[1].

07How much deposit is required?

The Consumer Council recommends an initial payment of no more than 40% of the contract sum, with the balance after inspection[5].

08How long does installation take?

One item usually takes a few hours. Furniture throughout a flat may take one to several days.

09Can the work be finished before Lunar New Year?

Factories may close around Lunar New Year. Order early and allow additional time.

10What should I consider for custom furniture in an older flat?

Walls may not be plumb and floors may not be level. Wait until wet trades are complete for final measurement and allow finishing margins.

11Can large furniture fit into a walk-up building?

Measure the stair turns. Larger pieces may need sectional manufacture and on-site assembly. Stair carry costs HK$300 per floor[1].

12Does someone have to be present on installation day?

Have someone present to confirm door swings, shelf heights and handle locations, then carry out an initial inspection when fitting is complete.

13Can I make changes after signing the production drawings?

Changes can be discussed. Once the factory cuts panels, revisions may mean recutting and extra cost. Check all details before signing.

14What should I check at handover?

Inspect doors, drawers, gaps, edge banding, colours and finishing. List defects for follow-up[3].

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]HK Create Design published 2026 rates and work item descriptions Accessed: 2026-11-03
  2. [2]Consumer Council, 16 November 2020 — survey of residential renovation quotes finds unclear scope and calls for better quotations Accessed: 2026-11-03
  3. [3]Consumer Council, 15 December 2020 — disputes over renovation quality and the value of detailed contracts and regular follow-up Accessed: 2026-11-03
  4. [4]Consumer Council: Don’t want to overspend again? Read the renovation quotation! Accessed: 2026-11-03
  5. [5]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-03
  6. [6]Hong Kong Observatory climatological normals, 1991–2020 Accessed: 2026-11-03
  7. [7]Environmental Protection Department: FAQs on noise from renovation in residential premises Accessed: 2026-11-03