01

Handover responsibilities: complete these six lines before requesting a quote

Match each line to the landlord's or management's latest instructions and record its date. Identify the responsible party, price boundary and acceptance check. Resolve conflicts before work begins.[1]

Handover responsibilities: complete these six lines before requesting a quote

You can swipe left or right on your phone to view the complete table.

rangeWhat to enter for site condition and instructionsWhat to enter for pricing and handover
Signboard and shopfrontRemove or retain: ___ Instruction revision: ___Responsible trade: ___ Making good at the connection: ___
Ceiling, partitions and fixed cabinetsLocation, quantity and extent to retain: ___Rate or included scope: ___ Handover photos: ___
Finished wall and floor surfacesLayer to remove and required finish afterward: ___Included or extra: ___ Inspection by: ___
Building services and other equipmentRetain / isolate / remove / reinstate: ___Appropriate contractor: ___ Tests and documents: ___
Protection and waste removalGoods lift, route, time slots and vehicle trips: ___Included scope: ___ Rate for extras: ___
Handover and outstanding itemsInspection, rectification and key handover dates: ___Signed off by: ___ Outstanding items assigned to: ___

Use this schedule for an initial shop enquiry. The lease, specialist assessments and building rules determine the actual requirements. Agree night work and completion dates separately. [1][2]

02

Retail strip-out and office reinstatement — specify the handover scope separately

Retail shops, restaurants and offices have different equipment and handover requirements. Offices may involve partitions, ceilings and carpets. Shops may involve signage, counters and displays. Compare the actual work even where the floor area is the same.

Divide the schedule into removal, retention, making good, clearance and handover. Assign responsibility for every item, including equipment interfaces and work requiring specialist trades.

Choose a quote for a shop strip-out and reinstatement or an office strip-out and reinstatement. The type of work will already be selected when you enquire. If the goods lift or loading arrangements are still to be confirmed, check the waste removal costs and site restrictions.

  • Are the landlord's reinstatement schedule and management requirements available?
  • What finish is required on the walls, floor and ceiling after removal?
  • Is there a goods lift? What loading hours and parking restrictions apply?

03

How do strip-out and reinstatement for handover differ?

Obtain the written handover scope before identifying which shop fittings to remove or retain.

Demolition is a task. Reinstatement defines the required result at handover.

Removing partitions, ceilings, cabinets and floor coverings is a defined task. Handover can also require repairs, reinstatement, cleaning and records. Match each item to the actual instructions.

Resolve differences between documents in writing first

Gather the relevant lease clauses, original handover records, current plans and landlord instructions. Seek appropriate professional advice on disputed responsibilities or lease terms. A works quotation cannot settle those terms or guarantee refund of the rental deposit.

Illustrative scenario or worked example 1

New requirement to retain part of the ceiling

Assumptions

  • Assume an old drawing called for full removal but the latest written instruction requires part of it to stay.

Checks to make

  1. Mark the disputed area and suspend work there.
  2. Agree the revised work, protection and limits of making good.
  3. Update the plans, quotation and copies held by each trade.

Obtain one agreed instruction before work proceeds to avoid reinstating something removed in error.

This hypothetical example illustrates planning only. It represents neither an actual job nor an agreed price or schedule. The site assessment determines the actual plan. [1]

04

What information should I prepare for a quote?

Assign responsibilities for the premises, equipment and specialist work using the site and instructions as well as drawings.

Include photos of the shop interior as well as the shopfront

Photograph the route from the entrance through each shop area and mark partitions, signs, equipment and items to retain. Include area, floor, loading route and handover deadline so the contractor can assess access and clearance.

Identify who may alter each building service

Air conditioning, fire services, electrical installations and other systems need separate assessment. Establish ownership, what must remain, who isolates each service and who reinstates it. Use appropriately qualified people and leave unidentified equipment undisturbed.

What information should I prepare for a quote?

You can swipe left or right on your phone to view the complete table.

InformationPurpose
Current photos and layout planConfirm visible quantities
Records of the original handover and later fit-outDistinguish landlord's fixtures, tenant additions and items to retain
Written handover requirementsDefine the required handover condition
Management rules for work and moving materialsCoordinate work sequence, protection and waste clearance
Equipment and contractor detailsIdentify specialist trade and connection responsibilities

Editorial planning and handover checklist. Confirm the individual site and work sequence separately. [1][2]

05

How to itemise a shop demolition and reinstatement quotation

Include demolition, making good, building services, clearance and handover in the quotation.

Define the scope before comparing totals

If the landlord’s checklist only says “remove the sign”, ask the contractor to quote separately for removing the sign and its brackets and for making good the shopfront. Ask the landlord to mark the area on a photo. Do they just want the fixing holes filled, or do they also want the old adhesive removed and the entire shopfront repainted? Compare the totals once both quotes show what is included and what costs extra.[1]

Use project-specific retail prices rather than office or residential rates

A published demolition item rate covers only the defined work. The final shop price depends on measured quantities, site conditions and building services. Confirm these before deriving a total.

For your first WhatsApp enquiry, you can write “My premises are in ___ (district and type of premises). I want to remove or keep ___. My expected handover date is ___.” If the date is still open, write “to be confirmed”. You can send site photos, the landlord’s reinstatement checklist or the moving times set by building management now or later. Before sharing the checklist, cover any names, phone numbers and rent amounts.

How to itemise a shop demolition and reinstatement quotation

You can swipe left or right on your phone to view the complete table.

Project scopeDetails to specify
Partitions, cabinets, ceiling and floorWhich areas or layers are to be removed?
Building services and signageWho retains, isolates, removes and reinstates each item?
Wall and floor repairs and surface finishesMaking-good scope and required finish
Common-area protectionLifts, corridors and loading points
Waste removalCarriage, visits, disposal and records
Inspection and rectificationWho inspects, handles defects and receives the documents?

Editorial planning and handover checklist. Confirm the individual site and work sequence separately. [1][2]

Get an itemised shop strip-out quote based on your landlord’s reinstatement requirements

06

Work back from the handover date

Work back from handover and identify the conditions for meeting each date.

Reserve time for inspection and rectification before scheduling construction

Allow time after demolition for waste removal, repairs, relevant tests, joint inspection and outstanding items. Check when the management office can attend before agreeing the key handover.

State what must be complete by each date

Show what must be finished before the next stage. If services are still live, collection is unarranged or the scope awaits approval, the original start date may need to move.

This sequence is for planning. The agreed scope determines the actual dates.

  • Confirm the written handover scope and responsible parties.
  • Check the site, plans, equipment and relevant procedures.
  • Agree demolition, making good and clearance arrangements.
  • Complete the checks, rectification and document handover.
Shop reinstatement handover documents covering scope, existing condition, variations, inspection and handover
Illustration of a handover document check. Each shopping centre, tenancy and handover has its own requirements. Select an image to enlarge

07

How can I reduce handover disputes?

Before-and-after photos from matching positions and a defects list help establish the agreed handover condition.

Use matching camera positions before and after strip-out

Tie each photo to an area and scope item. Record what was removed, retained or repaired, as well as the original state of equipment and common areas.

Illustrative scenario or worked example 2

Shorter working hours with the same key-handover date

Assumptions

  • Assume building management subsequently restricts work and carrying hours.

Checks to make

  1. Check demolition, clearance and repair dates against the revised access hours.
  2. Check whether labour, attendance and charges need adjusting.
  3. Confirm the revised inspection and defects arrangements with the handover team.

Put time constraints in a work schedule and confirm what is feasible before agreeing an accelerated finish.

This hypothetical example illustrates planning only. It represents neither an actual job nor an agreed price or schedule. The site assessment determines the actual plan. [1][2]

08

What if the drawings and latest reinstatement instructions conflict?

Record each document's date, revision and issuer. Have the responsible party resolve conflicts in writing before the crew decides what equipment or walls to retain.

Send the agreed revision to demolition, building services, repair and handover teams and match the revised quotation to that version.[1]

09

How should extra demolition, night work and waiting be priced?

If the premises restrict work to certain hours, specify the time slots, visits and carrying arrangements assumed in the quote. Confirm the effects of schedule or scope changes on labour, charges and handover.

Put the sequence in writing, with time for making good, testing, clearance and defects. Agree variations in writing.

10

Information to prepare for a retail reinstatement enquiry

Redact personal details and unrelated commercial terms before sharing plans or instructions if desired.

Compare related workConstruction waste removal prices.

  • Shop location, area, wide-angle site photos and available drawings
  • Reinstatement schedule agreed by the landlord or management
  • Contacts for retained equipment, building services and signs
  • Dates for works, carriage, joint inspection and key handover

FAQ

6 practical questions answered

01Can a demolition crew carry out the entire reinstatement?

Check the scope and qualifications. Clearly assign electrical, mechanical, fire services and other specialist work.

02Does reinstatement always mean returning a shop to a bare shell?

The relevant documents and agreed handover requirements determine the scope.

03Does management's agreement to start cover all requirements?

Building management permission alone does not confirm statutory, equipment and specialist trade requirements.

04Can demolition start before checking the landlord's requirements?

First agree the scope and required finish. This reduces the risk of removing an item that should stay or having to redo the work.

05Does finishing demolition satisfy the lease reinstatement requirements?

Handover may include making good, equipment work or documents. Check each against the agreed requirements and obtain appropriate advice if the lease terms are unclear.

06Does demolition have a one-year warranty?

Demolition items do not carry a warranty. Warranties for making good or new work are set out in their individual written quotations. Check who is responsible for handover checks and outstanding items.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Consumer Council: request a detailed renovation quotation Accessed: 2026-11-12
  2. [2]Environmental Protection Department — construction waste management Accessed: 2026-11-12