01

Don’t first ask “How much will it cost to demolish the whole house?”: First make a list of the range of quotes that can be quoted

Start by listing locations and quantities. In each room mark floors, walls, ceilings, cabinets, frames, sanitaryware and appliances for retention, removal or inspection. Removing tiles to the cement bed differs from taking the bed back to concrete. Cabinet removal may exclude service isolation, repairs, carrying and disposal. Mark the scope on photos before comparing quotations.

Match quantities to units. Floor and wall finishes usually use actual work area, cabinets may use horizontal length or face area, and debris may be charged by load, bag or weight. Saleable area × 3 is only the company's initial paint-area estimate.[6]

Unidentified concealed works should not be written as "included". The shutdown conditions, notifiers, assessment responsibilities and processes that cannot be done before written confirmation should be listed so that risks can be determined in advance.

  • Each location is attached with a photo and marked as reserved, demolished, or pending verification.
  • Specify whether removal stops at the finish, the cement bed or the concrete
  • Trigger conditions and confirmation procedures for undecided items
Design rendering: Demolition preparation scene with complete protection and safety equipment.
Design rendering: Demolition preparation scene with complete protection and safety equipment. Select an image to enlarge

02

Walls, kitchens, windows: three types of demolition that cannot be judged by the naked eye

The Buildings Department explains that when demolishing or altering structural walls, beams, and columns, the owner must appoint an authorized person and a registered structural engineer to evaluate, submit plans, and obtain approval and consent before the construction is carried out by a registered contractor. Demolition of non-structural walls within a unit may be exempted from approval, but must still comply with regulations including fire safety.[1] The thickness of the walls, the sound of knocks, or the appearance of the renovation are not enough to determine its nature.

Kitchen enclosure walls and doors may have structural or fire resistance implications. Converting to an open kitchen may also affect fire protection, escape, location and area; you should first check the approved plans and seek professional advice, and do not include feasibility in the demolition price by default.[1]

Modification of windows will depend on the size, height and distance from the ground and may be a minor project or subject to higher requirements; environmentally friendly terraces or working platforms cannot be enclosed with windows or glass panels.[1] If you have any questions, please provide photos, dimensions and window condition assessment first. Do not dismantle dangerous windows by yourself.

  • Check available approved plans and management office information
  • Suspected structures, fire resistance, exterior walls or common parts need to be verified first
  • Independent Measurement and Assessment of Window Works
Break down "demolition" into comparable quotation items

You can swipe left or right on your phone to view the complete table.

Project scopeQuantity / pricing methodpublic reference priceNot included or needs to be verifiedrisk
Old wall or floor tiles stripped to the cement bedActual square feet of constructionHK$30 per sq ftBasic protection and temporary storage in bags; please ask for transportation.If you want to dig into concrete, add HK$10/foot; suspected structures will not be processed.
The floor is drilled from brick to concreteActual floor square feetHK$52 per sq ftIndependent verification of deep chiseling, caissons and subsequent levelingFirst identify hidden pipes, wires and waterproofing layers
Non-structural brick partition wallWidth × Height Square FeetHK$69/square foot; minimum HK$2,800The scope of interface modification must be clearly statedNon-structural, fire-resistant or kitchen enclosures must be verified first
Gypsum board partition walls and joistsWall square feetHK$34/square foot; minimum HK$1,850Hidden equipment and power modification are not included by defaultFirst confirm the wiring, pipes or equipment inside the wall
Rubble removalActual number of cars or bagsHK$4,200 per truckload. Bagged waste is subject to a HK$2,000 minimum charge.Confirm whether the kitchen and toilet have been removed and movedThe number of vehicles, routes, freight elevators and mix levels will change

The amount is the company's 2026 public price, which is only used to check the same range, and is not the average market price or official quotation; the nature of the wall must be determined according to the requirements of the Buildings Department. [1][7]

Design renderings: Corridor ground protection and arrangement of engineering waste do not replace site clearance planning.
Design renderings: Corridor ground protection and arrangement of engineering waste do not replace site clearance planning. Select an image to enlarge
Strip-out work in progress | HK Create Design
Project photograph: demolition and strip-out, HK Create Design Select an image to enlarge
Demolition and strip-out: key figures illustrated | HK Create Design
Demolition and strip-out: key figures at a glance | HK Create Design Select an image to enlarge

03

Electricity and water pipes: Before demolition, clarify who can handle it and what documents should be retained after completion

Distribution boards, wiring, switches, sockets and fixed appliances form part of a residential electrical installation. EMSD advises engaging a registered electrical contractor for additions, alterations, inspections, tests and repairs. Before energisation, a registered electrical worker inspects and tests the installation and issues theWR1. [5] When demolition encounters wall wires, fixed lighting, water heaters or distribution boxes, first ask who will arrange for the registered contractor and when to submit the documents. The wires cannot be cut by the demolition workers.

Whether a water main can be subjected to minor works depends on the type and conditions listed by the Water Supplies Department. Non-minor works must first be applied to by a licensed plumber from the Water Authority and carried out by a designated person.[4] If there is a water meter, shared system, water heater or the nature of the work is unknown, it must first be defined by a licensed plumber.

Photograph the retained or newly installed pipelines, valve positions and position descriptions before the wall and floor are sealed to facilitate future maintenance; photos do not replace required tests or certificates.

  • Write down the person in charge of electricity and water pipes and handover documents
  • The work involved will be handled by the corresponding registered/licensed persons before coverage.
  • Save WR1 and related water pipe files
Worked example 1

Example 1: add four demolition items separately to check the total.

Assumptions

  • It is purely a demonstration, not a completed case or a formal quotation by the company.
  • Assume 50 sq ft of confirmed non-structural masonry wall, 260 sq ft of old tiles removed down to the cement bed, 80 sq ft of plasterboard partition and one truckload of waste.
  • Excludes drilling, electricity and water, kitchen and toilet, management fees and unlisted items.

How to calculate quantities

  1. Calculation: 260 × HK$30 = HK$7,800.
  2. Calculation: 50 × HK$69 = HK$3,450, above the HK$2,800 minimum.
  3. Calculation: 80 × HK$34 = HK$2,720, above the HK$1,850 minimum.
  4. Calculation: 1 × HK$4,200 = HK$4,200. The four items total HK$18,170.

The assumed scope totals HK$18,170. When comparing quotes, check that depth, minimum charges, haulage and lawful disposal are on the same basis.

This is the company's 2026 public price, not the market average; the wall, number of cars, bonding, management restrictions and concealment can all change the official quotation. [1][7]

Use your square footage instead and see a reference budget
Renovation work at Dandenong Mansion, Wan Chai | HK Create Design
Project photograph: renovation at Dandenong Mansion, Wan Chai, July 2026, HK Create Design Select an image to enlarge

04

Quotation, Protection and Management Office: Whether the same matter is split into the same set of responsibilities

Compare the removal depth (finish, cement bed or concrete), protection inside the flat and at doors, corridors and lifts, and whether waste is just stored or carried down, transported and lawfully disposed of. Agree who can stop work and reprice if concealed pipes, firmly bonded tiles, seepage or possible structural defects are found.

Check with the management office at the latest before entering the site to confirm working hours, freight elevators, corridor protection, deposits, parking and garbage arrangements; at the same time, keep photos of the original condition of indoor and public areas. A deed of mutual covenant or property management agreement handles building arrangements and does not replace professional verification of structural, electrical or plumbing.[1]

Do not fill in 0 with an unknown unit price or hide important risks in the total price. It can be written as "Based on 260 square feet; if you want to dig to the concrete, measure the price first; no construction will be done without written confirmation." The company's public prices can only correspond to the processes and conditions listed.[7]

  • Compare quotes for the same room, quantity and depth
  • Written confirmation of management and protection arrangements
  • Changes are based on photos, measurements, price revision, and construction after confirmation
Internal compartments and shelving in a custom wardrobe | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge

05

Clearance is not the last truck: classification, accounts, charges and traceability records

Materials generated from renovation, renovation and demolition and ultimately disposed of may be considered construction waste. Inert materials include construction debris, rubble, soil, asphalt and concrete; non-inert materials can include bamboo, wood, packaging and organic matter. The government's direction is to send inert materials to public fill areas and non-inert materials to landfills, and encourages classification first.[2]

Before using government-designated disposal facilities, construction waste generators must open a payment account; both renovation contractors and property owners can be considered generators. The official per ton rate, minimum charge and delivery record are not equal to the total private removal price, which may also include classification, drop-off, vehicle, route and management office time.[3]

Request an account of who holds the account, and keep records of date, material type, train number or shipment information, and disposal. Do not leave waste in public areas or hand it over to unknown destinations.

  • State classification, unit of measurement and account/disposal responsibilities
  • Save photos before and after removal and available delivery information
  • Let’s first ask about the procedures for mixed waste and extra trips.
From move-in to handover: What records should homeowners keep of decisions?

You can swipe left or right on your phone to view the complete table.

nodeConfirm firstKeep recordsStop and check firstavoid misjudgment
Before quotationRetention/demolition, kitchen and toilet, windows, common areasPhoto scope list, items not included, management office requirementsStructural, fire-resistant or common parts unknownInterior renovation does not necessarily need to be verified
Before starting workProtection, transportation routes, water and power cutoff responsibilitiesApproval, original condition photo, person in chargeUnclear boundaries of main switch, utility pipe or water meterDemolishers can replace professional engineering
Under demolitionDaily demolition volume, classification, temporary storage and number of trainsPhotos, change confirmation, clearance recordsCracks, vibrations, water seepage or unknown pipelinesVerbal "clearance" is enough
Before coveringSubstrate, concealed service routes and dimensionsOn-site verification recordsLeaking, damaged or unidentified items not dealt withThe board can be sealed after the garbage is removed
before handoverResponsibilities done, not done, and yet to be testedChanges, payment corresponding items, required certificatesThere are no corresponding documents for changes in electricity and waterVerbal assurances supersede information

This is a framework for communication and retention, not a statutory form; structural, electrical and water pipes must still be based on actual work and professional judgment. [1][2][4][5]

Project photo of kitchen cabinet installation | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge
Site photo of a completed custom bathroom cabinet | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge
Demolition and strip-out checklist illustrated | HK Create Design
Demolition and strip-out checklist | HK Create Design Select an image to enlarge

06

How to use your company’s 2026 price list: Make a starting point for your budget, don’t call it all-inclusive or average market price

The company's website lists 117 projects and supporting options in 8 categories, 116 items have reference unit prices, and 1 rooftop package is pending price revision.[6] Use it to list what needs removing, quantities and unresolved decisions. The quick estimate excludes complete kitchen and bathroom reconstruction, waterproofing, replumbing, rewiring, fitted furniture, finish tiles, sanitaryware, insurance and management fees.[6]

The detailed version gives separate units and minimum charges for tile removal, hacking floor screed, non-loadbearing masonry and plasterboard partitions, cabinets and rubble. Check whether carrying is included in each kitchen or bathroom strip-out item.[7] Entering the same set of measurement data item by item can better identify gaps than just filling in the unit number.

20% is a planning reservation, not an automatic price increase; multiplying the usable paint area by 3 is only a preliminary calculation.[6] Online estimates and enquiries are free. Site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against an order. Confirm whether your project qualifies. WhatsApp 5243 7747.

  • Save options, quantities and dates for communication drafts
  • Check minimum charges, owner-supplied materials, management fees and debris removal.
  • The official quotation shall be subject to the range after the measurement.
Worked example 2

Example 2: how classification affects the government disposal fee for two 1.4-tonne loads.

Assumptions

  • This is purely a rate demonstration, not a real project or removal quote.
  • Both are 1.4 metric tons: A is completely inert; B has no more than 50% inert components.
  • Only government disposal fees are included, and dismantling, classification, falling off buildings and vehicles are not included.

How to calculate quantities

  1. Calculation: 1.4 × HK$71 = HK$99.40.
  2. Calculation: 1.4 × HK$200 = HK$280.00.
  3. Calculation: HK$280.00 − HK$99.40 = HK$180.60.

The difference in this rate example is HK$180.60; the total price of the dump truck cannot be directly calculated.

The charging and acceptance criteria can be updated; there is a minimum charge for less than 1 metric ton, so it is not suitable to be directly applied to small-volume projects. [3]

Use your square footage instead and see a reference budget

07

After the demolition is completed, what is worthy of sealing, plastering or laying bricks?

Garbage leaving the site does not mean it can be covered. When the walls and floors are still exposed, check the dimensions, demolition boundaries, base layers, visible pipes, and windows, kitchen and toilets, floor drains and thresholds room by room to see if there is moisture or damage. Use photos and a list to list who handled it; trace it after sealing, waterproofing or laying tiles. The cost of rework will be higher.

Electrical or plumbing changes cannot be made by visual inspection in lieu of documentation. After new installation, addition, modification or repair, the electrical installation must be inspected, tested and issued a WR1 before being energized.[5] Plumbing work will be handled based on its minor nature and actual conditions.[4] This article does not set uniform water closure hours, slopes, or minimum construction periods.

  • Photograph all locations to be covered
  • Deal with water seepage, loose base and unknown pipes first
  • Save corresponding test or as-built files

08

When should we stop work immediately, rather than resorting to a "do it now" approach?

During demolition, if cracks suddenly expand, walls or floors are deformed, beams and columns are abnormal, window sills or exterior walls are loose, abnormal vibrations occur, water seeps continuously, or the lines are unknown, stop the affected process, protect the site, and notify the appropriate professionals. The feasibility and procedures of structural modifications must be handled in accordance with the requirements of the Buildings Department.[1]

Musty, damp, flaking or odors should not be masked by paint, aromatherapy or brief ventilation alone. First look for the cause of water seepage, drainage, condensation or materials. Cleaning and ventilation do not constitute a guarantee of formaldehyde, indoor air or immediate occupancy safety; if you have persistent discomfort or are sensitive, consider professional advice and postpone use.

  • Take photos to record the abnormal location and time and stop the connected process
  • Do not try to dismantle the structure, exterior walls, windows, electricity, water pipes, etc. by yourself
  • Do not treat surface modification as a guarantee until the root cause is clarified

FAQ

6 practical questions answered

01Do I need to apply to demolish a wall in my unit?

You can’t judge by just “interior walls”. The demolition and modification of structural walls, beams and columns must be carried out after assessment by an authorized person and a registered structural engineer, submission of drawings and approval. Non-structural walls in the unit may be exempted from approval, but must still comply with regulations.[1] First verify the nature and fire resistance requirements of the wall.

02If the management office has approved it, does it mean that the demolition must comply with government regulations?

no. Management approval of building arrangements such as work hours, freight elevators, maintenance or deposits does not replace statutory and professional verification of structural, electrical or plumbing. The Buildings Department also recommends checking the deed of mutual covenant and obtaining consent where necessary.[1]

03Does the Environmental Protection Agency charge per metric ton represent the entire fee payable by the dump truck?

no. HK$71, HK$175 and HK$200 per metric ton are the disposal fees under different government facilities and classifications. There are also minimum charges and measurement rules.[3] Private removals may also include categories, drops, vehicles, routes and trips.

04If the water pipes are sealed or modified during demolition, can the demolition workers handle it at the same time?

First check whether it meets the conditions of minor projects. Non-minor works must be applied to the Water Authority by a licensed plumber and carried out by a designated person.[4] Do not leave it up to the demolition team to define this.

05If you find wires after dismantling them, can you just cut them off or seal them?

It should not be handled by oneself. The electrical installation, modification, inspection, testing and maintenance involved in the renovation should be arranged by a registered electrical contractor; inspection and testing should be carried out and a WR1 should be issued before powering on.[5]

06Does the budget shown in the online estimate include complete demolition and full renovation?

No. The quick version estimates a specified example and excludes full kitchen and bathroom reconstruction, waterproofing, replumbing, rewiring, furniture, finish tiles and sanitaryware. The 20% is an owner's planning reserve.[6] The formal scope shall be subject to the written quotation after measurements.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Buildings Department: Alteration and addition works to domestic premises Accessed: 2026-10-21
  2. [2]Hong Kong Government One Stop: Construction Waste Accessed: 2026-10-21
  3. [3]Environmental Protection Department: Construction Waste Disposal Charging Scheme Accessed: 2026-10-21
  4. [4]Water Supplies Department: Minor works Accessed: 2026-10-21
  5. [5]Electrical and Mechanical Services Department: Household Electrical Safety Manual Accessed: 2026-10-21
  6. [6]HK Create Design: 2026 rapid renovation budget and service scope Accessed: 2026-10-21
  7. [7]HK Create Design: 2026 detailed project budget and demolition price list Accessed: 2026-10-21