01

Start by working backwards from the move-in date, but don’t promise to renovate the whole house with a fixed number of days.

Treat a moving date, tenancy expiry, school start or temporary stay as your desired move-in date. Work backwards through management approval, survey, procurement, demolition, concealed work, finishes, equipment installation, cleaning, defects and handover. Give each stage an owner, starting condition and completion evidence, such as written approval, a delivery record or photographs before enclosure.

Plan around dependencies. Confirm cabinet dimensions before closing service chases, inspect the substrate before fixing a painting date and check lift and waste arrangements before booking demolition. Ask whether any promised duration allows for paperwork, deliveries, site changes and repeat inspections before using it to plan your move.

  • Write down your desired move-in date, latest postponement date, and no-work date, but do not use them as a substitute for safety or legal procedures
  • For each milestone, add three columns: "Who confirms, what documents are submitted, and what will get stuck if it is not completed."
  • Record material supply and construction date separately; arrival does not mean that it has been inspected, can be installed, or has consistent dimensions
  • Reserve for leakage and secondary acceptance, but do not claim any reservation as a guaranteed construction period
Design rendering: Protected material handling routes within the building.
Design rendering: Protected material handling routes within the building. Select an image to enlarge

02

The first stop for house repossession: Divide what you want to do into things that can be done, those that need to be confirmed, and those that can’t be done directly.

First use photos, dimensions and original conditions to create a draft: electrical boxes, water switches, drainage, windows, air-conditioning positions, wall cracks or water seepage marks, beam and column locations and public pipes. Then check the unit’s approved plans and minor works records. The Buildings Department pointed out that this information can help to understand the structural layout, kitchen fire-resistant construction, room separation and drainage facilities; at the same time, you should also check whether the deed of mutual covenant and other documents require the consent of the corporation or management company first.[3]

Identify the type of wall before considering removal. For structural walls, beams or columns, the owner must appoint an Authorised Person and a Registered Structural Engineer to assess the work and submit plans. Obtain approval and consent before a registered contractor starts. Ordinary plastering, tiling and repair or replacement of sanitaryware may be exempt from prior approval but must still meet fire, structural and drainage standards.[3] Therefore, the "wall demolition" in the quotation should be marked as pending for confirmation, rather than being considered ready for construction just because the unit price is written.

Projects such as open kitchens, relocation of toilets or bathrooms, drainage improvements, window modifications and deck/rooftop projects are especially important to ask early. The Buildings Department reminds that kitchen enclosure walls and doors may be related to structure or fire resistance; modifications to kitchens and toilets may also involve drainage and waterproofing requirements.[3] Assess the feasibility of these options before demolition.

  • Keep photos of the property resumption and the date of measurement so that future changes can be compared to the original condition.
  • Obtain or inspect approved plans and minor works records, and mark any doubtful points on the floor plan
  • Next to each change state: whether it involves structural, fire-resistant, drainage, common parts or exterior walls
  • Any items marked as pending confirmation will not be dismantled without corresponding professional advice or procedures.
Divide the "demolition" quotation into five comparable columns

You can swipe left or right on your phone to view the complete table.

Engineering optionsKnown range/quantityCompany 2026 Pricing MethodItems that are clearly not included or yet to be verifiedSchedule, management or safety risks
A01 Remove wall/floor tilesRemove down to the cement bed. Compare measured working areas in sq ft rather than the flat's saleable area alone.HK$30 per sq ftOld bricks may need to be chipped until concrete is visible. An additional HK$10/sq. ft. is listed in the public terms. Management office fees and other unselected items are not included in this unit price.Once the demolition method is changed, the amount of clearance, base repairs and subsequent leveling will all change; do not think of this as the price of digging until you see the concrete.
A02 Remove the platform and floor tilesIncludes hacking the cement bed back to the concrete. Check depth and any recessed slab on site.HK$52 per sq ftDeep chiseling and caisson locations are negotiated separately; it should not be assumed that new floor leveling, tiling or management office deposits are includedIt is a deeper demolition scope, which will change the subsequent processes and the amount of scrap; do not use the unit price of A01 as a substitute for comparison.
A04 Remove non-main brick wallsValid for partition walls confirmed to be non-structural only; based on measured square feet, minimum spend applicableHK$69/square foot; minimum purchase HK$2,800Whether it is a non-structural wall cannot be determined by the quotation name; the trimming interface, file program and other restoration items must be clarified one by one.If structural walls, beams or columns are involved, they must first be assessed by qualified professionals and handled according to the procedures required by the Buildings Department. Construction cannot be started directly with this wall demolition project.
A11 Rubble removalPer truckload. Small jobs may be charged per bag, with a minimum of HK$2,000. Confirm the number of loads against site access, handling and building management requirements.HK$4,200 per truckloadThe kitchen or toilet demolition of A09/A10 has been listed and transported; whether other projects need to be cleaned and transported separately cannot be guessed based on the total priceMixed waste, loading and unloading, vehicle numbers and legal disposal arrangements can all cause changes in costs and dates; classification, delivery records and responsible persons are required to be listed

This table only compiles the 2026 reference unit prices and descriptions from the company's public detailed calculation page, and is not the market average price or official quotation. The scope of any demolition should be verified first with the site, plans and building requirements; construction waste should also be classified according to its nature and disposed of legally. [2][3][6]

Design renderings: Ordering materials and organizing the process on the desktop. There is no guarantee of construction time or real scheduling information.
Design renderings: Ordering materials and organizing the process on the desktop. There is no guarantee of construction time or real scheduling information. Select an image to enlarge
Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge
Renovation schedules: illustrated facts and figures | HK Create Design
Renovation schedules: key figures at a glance | HK Create Design Select an image to enlarge

03

Building management is not final administration: first obtain the conditions for admission

Building management rules affect deliveries, noisy work and debris removal. Check work hours, lift and corridor protection, goods routes, worker registration, waste storage, service shutdowns, fire access, deposits and handover. Add the answers to the programme and quotation comparison so protection in the flat and common areas is clearly allocated.

The Labor Department's Property Management Renovation and Maintenance Guidelines list that before construction, the management can require the contractor to submit valid third-party and labor insurance certificates, worker registration and safety training records, construction method descriptions and risk assessments, etc.; the details, foreseeable hazards and safety measures at each stage should also be discussed with relevant parties before the project begins.[5] Your management office may not necessarily use the same checklist item by item, but homeowners can use it to ask: What documents are actually required for this building, when will they be submitted, and who will approve them?

Do not book a non-refundable date for lifting, demolition or bulky materials without receiving a written reply. If the management office has additional requirements, immediately review their impact on the project scope, cost and critical path, and then update them in writing. This is not procrastination, but turning uncontrollable housing estate arrangements into trackable preconditions.

  • Ask the management office for the latest version of the renovation application form, codes, construction period and deposit requirements
  • Require contractors to list insurance, workers, construction methods and risk assessment documents that can be submitted
  • Confirm who installed the public area protection, when it was removed and whether there is any additional charge
  • Separately check the boxes for management office approval, freight reservation and worker admission, and do not replace them with verbal answers.
Worked example 1

Example one: estimating the paintable area of a 400 sq ft flat before a formal quotation

Assumptions

  • Assume the salable area of ​​the unit is 400 square feet.
  • The quick calculator uses saleable area × 3 as an initial estimate of the painted surface.
  • This is a fictitious calculation scenario, not a completed case by the company, and it does not deduct positions that do not need to be painted or add special grassroots treatments.

How to calculate quantities

  1. Calculation: 400 × 3 = 1,200.
  2. Use 1,200 square feet only to initially describe the possible wall and ceiling expansion to the contractor, and then verify it based on the on-site dimensions, wall condition, and workmanship.

The initial spread is 1,200 square feet; it helps compare paint coverage under the same assumptions, but not the actual work volume, unit price, or final total.

The public page clearly states that the "salable area × 3" is only a rough estimate. High ceilings, spacing, whether there is construction behind the cabinets, partial shoveling, water seepage repairs and tenant protection can all change the scope; it cannot be inferred from this that the move-in date or formaldehyde/odor is suitable for move-in. [1]

Use your square footage instead and see a reference budget

04

The core of quotation comparison: scope, quantity, unit, unincluded items and modified orders

Compare each location under five headings: work, quantity, rate or measurement, materials and exclusions. A tiling price might include just labour or also levelling, base materials, cutting, grouting, carrying or disposal. Painting may mean only the topcoat. Check stripping, repairs, primer and furniture protection before comparing totals.

The detailed calculator prices tile removal, hacking, non-structural wall demolition and waste removal separately. Check the units, minimums and items requiring a separate quote.[2] The value of this demolition method is that it allows you to see that "the same demolition platform" may not necessarily have the same project depth, rather than using one price to estimate the market situation in Hong Kong. The table above also demonstrates how to put together company prices, project quantities, unpackaged items and risks.

The formal quotation should have separate change procedures: who can request changes, what quantity and unit price should be listed before the change, which station will be affected, and how you will confirm it. Simply writing "negotiable on site" will cause the homeowner to lose the basis for comparison; a better way to write it is to clearly state the triggering conditions, such as finding loose foundation after disassembly, different measured lengths, or new protection requirements added by the management office, and then report the scope and impact before construction.

  • Each quote is compared item by item with the same list of locations, rather than just the total number of pages or total price.
  • Ask what measurement starts the charge, which minimum applies, and precisely which steps the unit rate includes and excludes.
  • Requires a listing of the responsibilities of the owner for supply of materials, contractor for supply of materials, transportation to the building, protection, removal, management office fees and maintenance
  • Convert verbal changes to writing: original scope, increase or decrease, amount, impact on date and confirmer
Internal compartments and shelving in a custom wardrobe | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge

05

When ordering materials, don’t just ask about the arrival date: lock in the size, interfaces and alternatives first

What really slows down a project with materials is often not that the truck is late, but that the size, door opening direction, socket location, or closing interface is discovered to be wrong after arriving on site. Create a card for each critical item: brand and model, size, color or sample, quantity, who placed the order, estimated arrival, delivery restrictions, inspector, out-of-stock substitutes, and latest decision date. Kitchen cabinets, doors, sanitary ware, lamps, air conditioners, floor materials and hardware should all be connected to the floor plan or elevation, rather than just by name.

Complete the actual measurement and confirm the drawings before placing the order, especially for cabinets, doors, stone materials and equipment that require reserved holes. If it is necessary to order early, the document should clearly indicate which dimensions need to be verified on site, and who will bear the risk of return, expediting or re-production after changes. Don't use "probably almost" instead of confirming the interface; a change in the location of a device may backfire on the order of plumbing, wall repair, and painting.

When selecting materials, it is also not advisable to directly equate odor, low VOC or other product claims with a guarantee of occupancy. You can obtain technical information and instructions for use of specific products, and arrange construction and ventilation according to product requirements. If you have concerns about indoor air or health, consider asking a qualified person or undergoing professional testing as needed.

  • The main material should be confirmed with model number, specifications and photos or samples, not just "same style" or "high quality"
  • Record the latest decision date and let the contractor indicate which process will be affected by the late decision
  • Check quantity, damage, color difference and accessories upon arrival, and keep photos and delivery notes
  • Specify an acceptable alternative for each critical material and who has the authority to approve it
Construction milestones that aren’t committed to a fixed number of days: What homeowners need to lock in at each stop

You can swipe left or right on your phone to view the complete table.

milestoneDecisions homeowners should lock indocument or confirmerNext step that will get stuckRisks to avoid
Design and before constructionSeparate "can be done, to be confirmed, and cannot be done immediately"; first decide whether there is any wall modification, kitchen and toilet location modification, drainage or window workApproval of plans, minor works records, and requirements of the Deed of Mutual Covenant/Management Office or Corporation; confirmed by qualified professionals when necessaryIf the nature of the project cannot be determined, the demolition date or material arrival date should not be regarded as completed.Avoid treating structural, fire resistance, drainage or covenant of mutual covenant restrictions as ordinary interior design issues
Before entering the buildingConfirm construction period, lift and corridor protection, worker registration, garbage storage and access arrangementsWritten requirements from the management office; if it is a high-risk project or a project required by the management office, the contractor shall submit insurance, construction method description, risk assessment and other informationDocuments have not been resubmitted or arrangements for public areas have not been completed, so workers and materials may not be able to enter as scheduled.Avoid insufficient protection, conflicts between the construction site and the movement of residents, or being asked to supplement documents after construction has started.
Before sealing the board or groove in the concealed projectConfirm sockets, electrical loads, lamp positions, water supply and drainage locations and future maintenance needs with drawings and photosWhen applicable, registered electrical contractors and registered electrical workers will handle fixed electrical installations; other processes should be checked with the corresponding person according to the nature of the project.Once the board is sealed, misalignment or omissions usually need to be disassembled and redone, which will also affect the paint, cabinet and installation.Avoid using visual inspection instead of recording, or handing over fixed electrical modifications to people who do not have the corresponding registration qualifications.
Demolition and removalSeparately record inert and non-inert materials, ask who arranges collection, when to leave the site and how to retain delivery informationContractor's removal arrangements; accounts and receipt requirements when involving government disposal facilities are verified by the responsible personAllow for sorting, temporary storage and vehicle loads. Otherwise debris can delay masonry or tiling and increase costs.Avoid mixing rubble, wood and packaging into one “clearance package” without disposal responsibility
Completion and handoverInspect each room and system item by item: door cabinets, drainage, sanitary ware, light switches, air-conditioning drainage, surface closing and change recordsDefect list, photos, repair period; if there is new installation, addition or modification of fixed power, WR1 will be chargedFailure to complete the inspection and document collection first makes it difficult to trace the scope and responsibility when problems are discovered after moving in.Avoid handing over just looking at appearance; safety or functional defects should be dealt with first, don’t cover up problems with cleaning

This is a dependency table, not a statutory or universal minimum duration. Building codes, site conditions, supplies, professional assessments and modification orders will all change the order and time required; ask the contractor to fill in the date, responsible person and completion criteria according to your scope of work. [3][4][5][6]

Made-to-measure kitchen cabinets and wall units | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

06

During construction, checkpoints are used instead of asking "how much did you do today?"

Every day on the calendar may not be comparable, as some processes must wait for prior confirmation. A practical approach is to set stopping points after demolition, before pipelines or wires are sealed, after waterproofing or base layer is completed, before cabinet installation, after equipment connection and before final cleaning. Only check what is visible at the current station at a time: location, size, material, surface condition, photo record, and starting conditions for the next station. This makes it easier to catch errors than asking about progress every day.

Before closing the boards, obtain drawings and photos of service locations. Check the actual appliances against loads, sockets, lighting and future maintenance access. EMSD advises arranging a feasibility assessment by a registered electrical contractor before installing, adding to or altering residential fixed electrical installations. After completion and before energising, a registered electrical worker must inspect and test the work and issue WR1. [4] Homeowners should not make electrical modifications on their own or reduce this step to a common closing process.

Use a one-page update sheet each week to handle exceptions: what was accomplished this week, which items are up for decision by whom, what restrictions will apply next week, and whether there are any verified costs or date changes. If there is water seepage, loose base, old illegal construction, or other hidden problems, stop at the affected area first and ask for an explanation of the cause, treatment options, amount, and subsequent impact; inspections should not be skipped just to keep the original date.

  • Take photos before sealing boards, grooves or coverings, and indicate the location and date on the plan map
  • Each stop inspection point only checks and accepts this process, and does not bring unsolved problems to the next process.
  • Fixed electrical works require appropriate registered persons to handle, test and return WR1 (if applicable)
  • Every time a hidden problem is discovered, get the scope, options, costs and date implications in writing before making a decision
Site photo of bathroom tiling and shower renovation | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge

07

Put budget reservations on the decision-making table and don’t mistakenly think that the contractor will definitely charge more.

The purpose of planning set asides is to provide homeowners with clear decision-making space when faced with variables that have been identified but cannot be accurately measured. For example, after taking it apart, you can see the condition of the base layer, changes in measured dimensions, or new requirements from the management office. It is not an "all-inclusive" statement and should not replace an itemized written quote. If the conditions for utilization are not clearly stated, the reservation can easily turn into a total balance that is difficult to verify later.

The company's quick estimate page explains that 20% of the upper limit is a planning reservation and not an additional charge; the budget on the detailed page allows users to choose different reservation ratios.[1] Example three shows how the 15% displayed on the calculator is worked out. It does not recommend the same percentage for everyone. Keep the base subtotal, allowance and formally approved changes in separate columns.

The basic whole-flat example excludes complete kitchen and bathroom reconstruction, waterproofing, replumbing and rewiring, fitted furniture and finish tiles. Use the stated scope when comparing it with other prices.[1] Online estimates and enquiries are free. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. Enquire on WhatsApp 5243 7747. Final confirmation depends on the site and the written scope.

  • Divide "Confirmed Project Subtotal", "Self-set Planning Reservation" and "Approved Change Order" into three columns
  • Each time a reservation is activated, the trigger reason, photo or metric, alternative options and confirmation date are recorded
  • Do not use reservations to cover up unlisted kitchen and bathroom, water, furniture, fabrics, insurance or management fees
  • If the total amount changes, first check whether it is a change in quantity, scope, specifications, or transportation and management arrangements.
Worked example 2

Example two: turning an assumed tile removal quantity into a checkable subtotal. This is an illustration, not a completed project.

Assumptions

  • Assume removal of 400 sq ft of old floor tiles down to the cement bed at the detailed calculator's A01 reference rate of HK$30 per sq ft.
  • Assume one truckload of rubble under A11 at the indicative rate of HK$4,200 per load.
  • This example deliberately does not superimpose A02 until the concrete is visible with A01 because the demolition depths of the two are different; it is also not assumed to include leveling, new bricks, management office fees or unlisted works.

How to calculate quantities

  1. Tile removal subtotal: 400 × HK$30 = HK$12,000.
  2. Assumed debris disposal: 1 × HK$4,200 = HK$4,200.
  3. Total: HK$12,000 + HK$4,200 = HK$16,200.

Under the very narrow assumptions above, the preliminary subtotal is HK$16,200. It separates the quantity, pricing unit and vehicle number, allowing homeowners to request on-site confirmation whether "400 square feet" and "1 vehicle" are valid.

This is not a market average price or official quote. The solidity of the old bricks, whether it is necessary to dig until the concrete is visible, the transportation distance, management office rules, classification, actual number of trucks and legal disposal can all change the result; the government's disposal charges per metric ton cannot be directly regarded as the contractor's clearing price per truck. [2][6]

Use your square footage instead and see a reference budget
Custom desk and storage cabinets | HK Create Design
Site photo: Custom furniture on site. HK Create Design. Select an image to enlarge

08

High-risk projects should be diverted early: professional planning is more important than rushing

Structural walls, beams, windows and external walls, fixed electrical, gas, drainage, demolition, height and rooftop work should not be handled at the pace of ordinary interior work. They may involve statutory procedures, professional assessments, specific building qualifications, management safety controls or weather conditions. Even if some simple works do not require prior approval from the Buildings Department, it does not mean that fire protection, structural, drainage and deed of mutual covenant requirements can be ignored.[3]

The Labor Department points out that property management companies can play the roles of employer, occupier, outsourced contractor employer and executor of the deed of mutual covenant during renovation and maintenance projects, and should coordinate hazard and safety measures before starting work.[5] For homeowners, the most practical approach is to separate high-risk projects from general finishing projects, require the appropriate person to confirm the feasibility, construction methods and documents within their scope, and do not remove windows, change electrical appliances, deal with high places or perform dangerous demolitions on their own.

If this involvesAluminium windows, provide the quantities, dimensions, photos of the fault, and details of the sill and outside conditions for the appropriate professional to assess. The company's public page explains that aluminium windows have no fixed unit rate. The fault, number of windows, site conditions and working arrangements need individual assessment.[1] Don’t misunderstand the lack of a fixed unit price to mean that you can add it on a quick budget, or that you have to deal with dangerous window parts yourself because you are rushing to move.

  • Prominently mark any structural, facade, window, electrical, gas, drainage, elevated or rooftop items on the bill of works
  • Ask the other party to explain who will make the assessment, what procedures will be applied, when the work can start, and what documents will be submitted upon completion.
  • If the site conditions are different from the original assumptions, the affected processes will be suspended and the risks and construction schedules will be updated.
  • Do not carry out structural demolition, electrical modifications, window removal or work at heights on your own
Worked example 3

Example three: distinguishing a planning allowance from company charges on the calculator

Assumptions

  • The company details page shows an example of a 400 sq. ft., 4 project, subtotal of HK$77,200.
  • Let’s say the homeowner chooses to set aside 15% on his or her plan, rather than treating it as an automatic fee added by the company.
  • This is only an arithmetic example of public computer footage and is not a representation of completed work, a committed price, or a one-size-fits-all solution for all projects.

How to calculate quantities

  1. Planning allowance: HK$77,200 × 15% = HK$11,580.
  2. Upper planning budget: HK$77,200 + HK$11,580 = HK$88,780.
  3. At the quotation meeting, record each range of HK$77,200 and the use of HK$11,580 separately; any changes should be noted first whether the reservation will be used.

The planning range in this example is HK$77,200 to HK$88,780, of which HK$11,580 is the 15% reservation set by the homeowner; the public page also explains that the reservation in the upper limit is not a fixed surcharge.

A contingency does not replace site measurement, professional assessment or a written variation. Excluded items remain separate: full kitchen and bathroom reconstruction, waterproofing, replumbing and rewiring, furniture, finish tiles, sanitaryware, works insurance, management deposits and administration fees. [1][2]

Use your square footage instead and see a reference budget
Renovation schedules: illustrated checklist | HK Create Design
Renovation schedules: checklist | HK Create Design Select an image to enlarge

09

Demolition and rubble: agree waste sorting, truckloads and responsibilities

The remaining materials generated from renovation, renovation and demolition are construction waste. The government considers rubble, soil, concrete, etc. as inert construction waste; bamboo, wood, packaging and other organic materials are non-inert construction waste. The government's disposal strategy is to send reusable inert materials to public fill areas and non-inert materials to landfills, and encourage sorting before disposal.[6] Therefore, homeowners should require clearing instructions to include classification, temporary storage, transportation, truck numbers and legal disposal, not just "clearance at a fixed price".

If government-designated disposal facilities are used, construction waste generators, which may include renovation contractors or premises owners, must open an account and pay fees as arranged.[6] Who opens a waste disposal account depends on the arrangement. Identify in the contract who handles it, who keeps the delivery and disposal records and which costs are included. Our published rubble rate is HK$4,200 per truckload. Confirm the number of loads against the site scope, handling and management rules.[1]

  • Ask clearly: How will the demolished bricks, wood, packaging and recyclables be separated?
  • Include the unit of account per truck or bag, minimum charge, handling restrictions and whether government disposal fees are included in the quotation
  • It is required to keep traceable removal arrangements and delivery information, and check whether it complies with the building's temporary garbage storage rules
  • Don’t take the government’s disposal fee per metric ton directly as the total residential removal price.

10

Property resumption is based on functions, documents and deadlines, not just whether the paint is new or clean

The last stop is to check and accept each room and system item by item: door cabinet opening and closing, floor level and surface, windows and hardware, sockets and light switches, air-conditioning drainage, sanitary ware, drainage, hot water, walls and ceilings. Each issue is accompanied by location, photo, date of discovery, severity, responsible person, and fix deadline. Priority will be given to issues that may affect safety or use, such as suspected water leaks, electrical abnormalities, window, gas or drainage problems; they will be inspected by qualified personnel when necessary.

Collect handover documents as applicable: final variation records, photos of concealed work, services layouts, material and equipment warranties, warranty terms and WR1. The Electrical and Mechanical Services Department explains that the registered electrical contractor and worker sign WR1 after inspection and testing. Keep it for future reference.[4] The Labor Department also recommends that at the end of each working day, representatives of the contractor and management company personnel inspect the construction site to ensure that the construction site is in good condition and safe before leaving.[5]

  • Safety and functionality before appearance; don’t let cleaning hide leaks, cracks or misalignments
  • The defect list is managed with photos, locations and deadlines, and a second inspection will be conducted after repairs.
  • Collect final drawings, change records, maintenance documents, photos and applicable WR1
  • Keep all records until completion of conservation demolition, common area inspection and deposit/handover arrangements with management office

FAQ

7 practical questions answered

01How long should the general residential renovation construction period be estimated?

It is not appropriate to apply a fixed number of days based on area alone, nor to regard any example as a minimum construction period. First, separate the drawings and management office, design finalization, material ordering, each process, testing, clearance and execution. Ask the contractor to list the starting conditions, responsible person and completion evidence for each step. The actual date will be affected by site conditions, materials, management office hours, professional procedures and order changes; when there is a deadline for check-in, temporary accommodation or other filings should be arranged as early as possible instead of skipping safety or acceptance.

02If the management office has approved it, does it mean that all projects can be done?

Doesn't mean. The management office's approval mainly deals with requirements related to the common areas of the building, construction arrangements and deed of mutual covenant; the project itself must still comply with applicable laws and technical requirements. The Buildings Department pointed out that projects involving structural walls, beams or columns must be assessed, submitted by authorized persons and registered structural engineers, and approved and approved before construction; generally exempted projects must still comply with fire protection, structural and drainage standards.[3] Therefore, the management office’s written requirements, approved drawings and corresponding professional opinions should be checked side by side.

03If the quotation says "demolishing non-main wall", can it be demolished directly?

Can't. The quoted name does not mean that the nature of the wall has been confirmed. Check the approved plans and site conditions first; if there are any structural doubts, the qualified assessment should not be replaced by a master's visual inspection or a low-cost project. The Buildings Department explains that the demolition of non-structural walls is generally exempt from approval, but there are different procedures for structural walls, beams or columns; kitchen enclosure walls and doors may also involve fire resistance or structural issues.[3] Confirm first before discussing the scope of disassembly, removal and subsequent restoration.

04Is WR1 important after changing outlets, adding appliances, or re-wiring some wires?

If it is a new installation, addition or modification of a residential fixed electrical installation, the Electrical and Mechanical Services Department points out that the feasibility assessment should be carried out by a registered electrical contractor first; after completion, it should be inspected and tested by a registered electrical engineer before powering on, and a WR1 should be issued by the registered electrical contractor and engineering staff. Users do not need to submit the certificate to the Electrical and Mechanical Services Department, but they should keep it.[4] Ask at the quote stage what is fixed electrical work, who is the registered person, whether testing and WR1 are included in the scope.

05Does entering a budget of 500 square feet online mean that the whole house is all-inclusive?

No. The company's quick version estimates a specified example. Its basic renovation excludes full kitchen and bathroom reconstruction, replumbing, rewiring, fitted furniture and tile finishes. Saleable area × 3 is only an initial paint-area estimate.[1] The quantity, unit and unincluded items should be checked item by item, and confirmed with a written range after measurement. Any website total cannot be supplemented by unselected items or management fees.

06Is the 20% planning reservation a mandatory surcharge for the company?

no. The company's public page states that 20% of the upper limit is a planning reservation, not a company charge or automatic surcharge; the detailed page allows users to choose different reservation ratios.[1] Homeowners should keep separate confirmed project subtotals, self-imposed reservations, and written-approved changes. If a new problem arises on site, obtain the scope, quantity, options, price, and date impact before deciding whether to use the reservation.

07If the quote includes one truckload of rubble, what else should I check?

You need to ask how the number of trains is calculated, whether there is a minimum charge, who will carry it to and from the building, when the management office will allow transportation, how to classify, whether the delivery information is retained, and how to confirm if there is more than one vehicle. Government information points out that renovation waste is construction waste, and inert and non-inert materials have different treatment directions; there are also account and fee arrangements before using government disposal facilities.[6] Therefore, the price per vehicle cannot be directly equivalent to the government's charge per metric ton, nor can it be assumed that any "clearance package" covers all on-site restrictions.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]HK Create Design 2026 Quick Renovation Budget and Estimation Instructions Accessed: 2026-10-21
  2. [2]HK Create Design 2026 detailed project budget and public price list Accessed: 2026-10-21
  3. [3]Buildings Department: Alteration and addition works to domestic premises Accessed: 2026-10-21
  4. [4]Electrical and Mechanical Services Department: Household Electrical Safety Manual - New Installation, Renovation or Renovation Accessed: 2026-10-21
  5. [5]Labor Department: Occupational safety and health management in renovation and maintenance works in the property management industry Accessed: 2026-10-21
  6. [6]Environmental Protection Department: Construction Waste Disposal Charging Scheme Accessed: 2026-10-21