01
You know by numbers: How common are renovation disputes?
In its February 2024 home renovation study, the Consumer Council reported 1,205 domestic renovation complaints from 2017 to 2023, exceeding HK$270 million in total and averaging almost HK$230,000 each.[2] The research brief lists the annual numbers: 210 cases in 2017, 177 cases in 2018, 159 cases in 2019, 131 cases in 2020, 186 cases in 2021, 173 cases in 2022 and 169 cases in 2023.[3]
After the Consumer Council revised its classification in 2026, “renovation and home maintenance works” showed 400 complaints in 2024, 347 in 2025 and 352 from January to September 2026.[1] In addition, there are 779 cases in the "furniture renovation" category in 2024.[1] It can be seen that consumer disputes related to renovation and furniture have always existed.
The Consumer Council also pointed out that the entry barriers to the renovation industry are low and the quality of operators varies. Hong Kong does not have a legal framework specifically regulating business operations in the home renovation industry. In the event of disputes, consumers can only rely on general consumer protection legislation and common law.[2] This means that the owners need to take care of themselves.
HK Create Design publishes all 117 prices. Quotations list quantities and units by work stage so you can check each item. WhatsApp 5243 7747 for a free consultation or book a visit. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.
Another figure worth noting is that the overall complaint volume of the Consumer Council itself is also very high: 40,839 complaints were received in 2024 and 38,187 in 2025.[1] Renovation only accounts for a small part of the total, but because each case involves a large amount of money and living arrangements, once something goes wrong, the impact on the family is often much greater than ordinary consumer disputes.
- Understand the Consumer Council’s complaint categories and frequently asked questions
- It’s not good to assume that “introduction from acquaintances” will definitely be fine.
- Before choosing a company, check how transparent its quotation is.

02
How bad things happen: four common scenarios
Scenario one: a large deposit is collected, the start date slips and the contractor becomes unreachable. Delays or non-delivery were the Consumer Council's second-largest category, with 336 complaints.[3] Such cases often involve a one-time large advance payment that is not linked to the progress of the project.
Scenario two: “hidden work” is discovered after the start and the contractor asks for a major increase before continuing. Vague wording such as “Bathroom renovationas a lump sum”, without defining the strip-out depth or waterproofing height, makes disagreement more likely. There were 120 price disputes.[3]
Scenario three: the work is finished but the quality falls short, and the parties disagree about what “complete” means. Service quality was the largest category, with 510 complaints.[3] The problem is often that the quotation does not include the material model and acceptance criteria.
Scenario four: the contractor suggests non-compliant work. In the Consumer Council's mystery shopping survey, about three quarters of companies suggested a wall could be removed based on a floor plan alone without verifying its nature.[2] Once the structural wall is demolished, the consequences are not only unfinished work, but also a violation of the Building Ordinance, which carries a maximum fine of $400,000 and two years' imprisonment for carrying out construction work without approval.[4]
- Avoid paying too much in advance
- The quotation should state clearly the demolition depth, waterproofing height, etc.
- Confirm the nature of the wall before demolishing it
You can swipe left or right on your phone to view the complete table.
| Risk point | Consumer Council data | something happens | Self-protection methods | Evidence to be preserved |
|---|---|---|---|---|
| Service quality | 510 complaints out of 1,205[3] | The process or materials are not clearly written down, and both parties have different standards after completion. | The quotation shall state the material brand, model, process and acceptance standards. | Quotation, material photos, acceptance records |
| Delay/non-delivery | 336 cases[3] | There is no construction period written down, no responsibility for delays, or the work has not started after receiving the money. | The contract states the start and completion dates and delay arrangements | Timetable, daily progress photos |
| price dispute | 120 cases[3] | The quotation is general and there is no written confirmation of additional work. | For each additional addition, please provide a written quotation before starting work. | Add project confirmation sheet |
| Insufficient quotation information | Only 38% of the quotations carefully list all details; 48% have no unit price for the process[3] | Difficult to compare and verify | It is required to have the same unit price based on the work sequence quantity. | Price comparison table |
| Advice on illegal projects | About three-quarters of companies suggested demolishing walls based on floor plans alone[2] | There is no verification that the wall is a structural wall | Before demolishing the wall, confirm the nature of the wall and require professionals when it comes to the structure[4] | Drawings, professional opinions |
Source: the Consumer Council's February 2024 home renovation study. The figures count cases brought to the Council, not every renovation dispute in Hong Kong. [2][3][4]


03
Choosing a company: Look at the company first and don’t fall for it.
First, look at the transparency of quotations. The Consumer Council analyzed 40 preliminary quotations and found that only 38% carefully listed all project details, 47% only listed some of them, 15% almost did not list them at all, and 48% did not provide the unit price of the process.[3] A good quotation should be based on the work sequence quantity, unit and unit price.
Second, check the completeness of the terms. Among the same batch of quotations, only 38% mentioned liquidated damages, 20% stated legal compliance, and only 8% stated compliance with property management requirements.[3] You can proactively request to include these terms.
Third, look at insurance. Only 42% of the quotations mentioned both labor insurance and contractor's comprehensive project insurance or third-party liability insurance, and 20% did not mention it at all.[3] A worker's injury in your flat or damage to a neighbour's property can be difficult to resolve without insurance. Our published L02 third-party liability and employees' compensation insurance for a whole-flat project is HK$6,700 per job. (see published rates)
Fourth, look at communication. Is there a dedicated person to follow up, is there a written record, is there a person who carefully looks at the scene and explains the risks when measuring. Our designers and masters with more than 15 years of experience will talk to you personally and give you a written quotation after measuring your measurements.
Fifth, see if he is willing to talk about risks. A good company will tell you directly when measuring what parts need to be dismantled, what processes may be added, and what requirements may not be in compliance. A survey by the Consumer Council found that about three-quarters of the companies said they could change the kitchen door to a sliding door, but this may violate fire safety regulations;[2] A company that talks about "getting" everything may not necessarily be thinking about you.
- It is required to have the same unit price based on the work sequence quantity.
- Check liquidated damages, compliance, insurance terms
- Confirm that there is a dedicated person to follow up and communicate in writing

04
Quotation: Please write it down before it becomes a dispute.
The Consumer Council recommends that the industry adopt a standard quotation template.[2] Before there is a standard, you can use the following principles to request a quotation: each process has a number, description, quantity, unit, and unit price; write down the brand model or specification for the material; indicate the items that are not included; indicate the validity period of the quotation.
The Consumer Council found that only one-third of companies provide preliminary estimates before detailed quotations, and the gap between estimates and actual quotations can range from −32% to +28%.[3] So it’s not easy to decide with a phone quote or online estimate.
Our AI quotation assistant and 117-item price calculator give preliminary estimates. The final price is confirmed in writing after our tradesperson measures the site. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.
When comparing quotes from several companies, first align the processes and then compare the totals. The one with the lowest total may have missing items; the one with the most expensive total may include items you don’t need.
The Consumer Council's survey also found that 58% of respondents found it difficult to compare quotes from different companies.[3] The solution is to make a comparison table yourself, with the processes listed on the left and a column for each company on the right. Fill in the quantity and price item by item. If you can't find the corresponding item, that's where you need to ask.
- Each item has a number, quantity, unit, and unit price.
- Specify the items not included and the validity period
- Align the processes and compare the totals
05
Contract: six things that must be written
First, the scope of the project: Attached is the quotation and drawings, listing what will be done in each space. Second, construction period: start date, estimated completion date, and handling of delays due to weather, management office, owner changes, etc. Third, payment: The amount of each period is the same as the corresponding completion node.
Fourth, additions are the same as changes: Any additions must be quoted in writing and signed by both parties before starting work. A Consumer Council survey found that 29% of respondents believed that there is no need to update the quotation even if there are changes in the project.[3] This concept is at the root of the price dispute.
Fifth, maintenance: maintenance period, scope, excluded items, and response time for leaks. Sixth, terminate the contract: If one party breaches the contract, a refund will be issued for the completed work.
We have another article that details renovation contracts and installment payments, which you can refer to together.
- Attached is the quotation and drawings
- Specify the construction period and deal with delays
- Please confirm in writing before adding
Example one: using Consumer Council figures to calculate the proportions and amounts involved in renovation disputes
Assumptions
- Using data from Consumer Council Research Briefs from 2017 to 2023. [3]
- The following is only a system calculation and does not represent any company or individual risk.
How to calculate quantities
- Annual average: 1,205 cases ÷ 7 years = approximately 172 cases.
- Service quality ratio: 510 ÷ 1,205 = approximately 42.3%; late/non-delivery: 336 ÷ 1,205 = approximately 27.9%; price disputes: 120 ÷ 1,205 = approximately 10.0%.
- Average amount per transaction: HK$276,968,339 ÷ 1,205 = approximately HK$229,849.
- The 352 cases from January to September 2026 already exceeded the full-year 2025 total of 347. [1]
Service quality and delays together accounted for about seven in ten cases. The average amount involved was roughly HK$230,000 per complaint, and more recent complaints have not shown a decline.
Complaint classifications are set by the Consumer Council, and the categories will be adjusted starting from 2026; [1] The figures only reflect cases that seek help from the Consumer Council. [1][3]

06
Payment: follow the progress, not the date
Tie each payment to a stage you can see and inspect, such as completion of concealed services, waterproofing and flood testing, masonry or fitted joinery. The amount paid then broadly reflects the work already complete.
Bespoke furnitureor ordering tiles, where materials must be purchased in advance, a partial materials payment may be reasonable. Ask for the order or delivery record.
Avoid paying in cash, try to use bank transfer, and indicate the name of the project and the number of the same period in the transfer notes. A receipt is required for every payment.
Retain the final balance until agreed defects are rectified.
Use the payee named in the contract. If asked to transfer money to an individual or a different company, get written authorisation from the contracting company first so there is a clear payment record.
- Each payment corresponds to the project node
- Prepayment for ordering materials requires proof of order
- Make a transfer and keep the receipt
07
During construction: evidence and communication
During the project, I took photos every time I visited, especially the hidden projects that would be covered, such as water pipes, wires, and waterproofing layers. Research by the Consumer Council pointed out that many disputes are difficult to resolve through negotiation, often because the agreement is unclear and the words are unsubstantiated.
Confirm design changes, extras and delays in writing by WhatsApp or email. Ask for a written variation price before agreeing to additional charges.
Set up regular progress updates, for example once a week, the contractor will report what has been completed, what will be done next week, and whether there are any problems.
During the construction period, we will regularly use photos to report the progress, and concealed works will be photographed and recorded before closure.
If the project has been suspended for a few days and no one has started work, don't wait. Please inquire in writing today about the reason and the date of resumption of work. Delays in initial processing are usually due to materials not arriving or manpower deployment issues; the longer the delay, the harder it is to distinguish responsibilities, and the easier it is to turn into a mess.
- Photo of the concealed project before closure
- Written confirmation of important decisions
- Regular progress updates
You can swipe left or right on your phone to view the complete table.
| stage | Processes to be completed | Acceptance method | Ask before payment | Risk warning |
|---|---|---|---|---|
| Sign a contract | Confirm quotation, drawings, materials and construction period | Signed by both parties | Written quotations and contracts | Avoid paying too much in advance |
| Demolition and services completed | Disassemble, change pipes, change electricity | Pipe pressure testing and electrical testing | Photos, WR1 (electricity) | Inspect services before concealment |
| Waterproofing and masonry complete | Waterproofing, water sealing, tile paving | Flood-test records and tapping checks for hollow areas | test photo | The waterproofing is done first by laying bricks |
| Carpentry and painting completed | Furniture installation and painting | Itemized acceptance checklist | Missing list | Completion is checked against the checklist |
| Completion and execution | Cleaning and clearing areas | Re-examination | Warranty terms | Retain part of the balance until defects are rectified |
The installment ratio is negotiated by both parties. This table only demonstrates the idea of payment based on acceptable nodes rather than dates; the Consumer Council recommends measures such as setting up a standard quotation template. [2] [2]

08
Additional project: The most explosive position
Older flat renovationCommon variations arise when tile removal reveals corroded pipes or opening a wall revealsageing electrical wiring, or finding a damaged waterproofing membrane after removing a bath. These discoveries do not necessarily mean a contractor is acting dishonestly, but changes should be handled transparently.
The correct process is: the contractor discovers a problem → takes a photo with you to confirm → proposes a plan and a written quotation → signs after you agree → start work. Additions without written confirmation can easily turn into arguments.
If the additional amount is large, you can ask for the relevant part to be suspended and find someone to get a second opinion.
Our quotation will pre-list the common hidden risks of old buildings, and we will also clearly explain the required openings when measuring, waiting for you to reserve a budget.
In addition, it is necessary to distinguish between "addition" and "change": addition refers to a new process, such as adding two more sockets; change refers to changing the original design, such as replacing the floor tiles with another one. Both may affect the price and construction period, so the difference between the old and the new must be written down in writing to see if it will affect the completion date.
- If you find a problem, take a photo first to confirm.
- Work will start first after adding a written quotation
- If you make a large additional payment, you can seek a second opinion.
09
Accident counting: processing steps
If the project is delayed or the contractor cannot be contacted, the first step is to compile all evidence: quotations, contracts, payment records, communication records, and on-site photos. The second step is to notify the contractor in writing, setting out the questions and requirements, so that a reasonable deadline can be met for response.
If you cannot reach an agreement through negotiation, you can complain to the Consumer Council. Although the Consumer Council has no enforcement power, it can mediate. The Consumer Council's research also mentioned that when mediation fails, the two parties can still resolve the matter through arbitration or expert ruling.[2] If the amount involved is relatively large or there is a breach of contract, you may consider the Small Claims Tribunal or seek legal advice.
If illegal works are involved, such as demolishing a structural wall, an authorized person or registered structural engineer should be hired as soon as possible to assess the safety.[4]
The most important thing is not to pay again, and not to record the on-site conditions before hiring someone to take over. Otherwise, it will be difficult to prove how much the original contractor has completed.
The Consumer Council surveyed 394 respondents, and 19% said they had had disputes with renovation companies; 74 of them responded to the results, 76% were resolved through negotiation, and 21% failed to resolve the dispute.[3] In other words, most disputes end up being negotiated by both parties, so it will be much easier to negotiate if there is a clear written record from the beginning.
- Organize evidence
- Written notice with deadline
- Ask the Consumer Council for help or seek legal advice

10
Completion acceptance: Don’t rush to settle the bill
Upon completion, check and accept space by space and process by process. Use a checklist to record the areas that need to be implemented, and both parties will sign for confirmation. After the leak is completed, recheck again.
Collect all the documents:WR1 the electrical work completion certificate, waterproofing test records, material warranty cards, furniture hardware warranty information and warranty terms.
After every order is completed, we will remove the trash, sweep the area, and do basic cleaning. Deep cleaning or formaldehyde removal will be followed up by a professional cleaning company we cooperate with, so you don’t have to worry.
Our custom furniture package includes layout and building services drawings, furniture drawings, VR views and production drawings. The agreed drawings give you a reference for checking the finished installation.
- Acceptance item by item and signed by both parties
- Complete the certificate and maintenance documents
- Use drawings as basis for acceptance
Example two: breaking payments for a hypothetical project into milestones
Assumptions
- Assume the total project cost is HK$200,000 (hypothetical figure, not quotation).
- The two parties agreed to pay according to five nodes, and the proportion is only for demonstration.
- This includes L02 third-party insurance and labor insurance of HK$6,700. [hkcd-pricelist]
How to calculate quantities
- Signing: 10% = HK$20,000.
- Demolition and plumbing and electrical work completed and inspected: 25% = HK$50,000.
- After completion and inspection of waterproofing and masonry: 25% = HK$50,000.
- Carpentry and painting completed: 30% = HK$60,000.
- Defects rectified: 10% = HK$20,000. Total HK$200,000.
Each payment period corresponds to a completion node that can be seen and verified. The amount paid by the owner at any time is roughly close to the completed work.
The actual proportion depends on the order materials (for example, custom-made furniture requires prepayment for production) and negotiation between the two parties; this example does not represent legal advice or our company's fixed payment terms. (see published rates)

11
Building management and neighbors: an easily overlooked source of disputes
Many renovation disputes are not between the owner and the contractor, but because the management office's requirements are not met, resulting in the project being stopped. Among the quotations reviewed by the Consumer Council, only 8% mentioned a statement of compliance with property management requirements.[3] Management offices often require worker registration and a deposit and control work hours and waste routes. Check these before work starts to avoid stoppages and delays.
Before starting construction, the owner should obtain the renovation code from the management office and provide it to the contractor to read clearly, and state in the contract that the contractor must abide by it. The deposit will be paid by the other party, and the other party will be responsible for damage to public areas. This must be discussed in advance.
As for neighbors, you can post a notice before the start of construction or notify them in person, stating the construction period and the noisiest days, and leaving a contact number. Many complaints come from neighbors who don't know how much patience they have to endure. Communication in advance can avoid a lot of trouble.
Before starting work, we will check the management office regulations with you, arrange for workers to register and protect public areas, remove garbage and clean the area after completion, so as to reduce delays due to management issues.
- Request the renovation code of the management office
- The contract states that the contractor must abide by the code of conduct
- Notify neighbors before work begins

12
Final check before signing: Ten-minute self-insurance checklist
Before signing the contract, please take ten minutes to check again: does the quotation indicate the quantity and unit price according to the work sequence? Does it indicate the material brand and model? Does it indicate the items that are not included? Does the quotation have a validity period? The Consumer Council found that only 50% of the quotations mentioned the validity period.[3] It's so easy to leak.
Then read the contract: start and completion dates, delay processing, payment nodes, additional processes, maintenance periods, contract termination arrangements, and insurance. In a Consumer Council survey, 68% of quotations mentioned maintenance periods, 60% mentioned extension arrangements, and 63% mentioned project change arrangements.[3] In other words, there is still a considerable proportion that has not been written, and you have to take the initiative to ask for it to be filled in.
Finally, check with yourself: Do you have an emergency fund reserved in your budget to deal with hidden projects? Do you have time to inspect the project regularly? Do all communications be in writing? If the owner is prepared, the contractor will take it more seriously.
WhatsApp 5243 7747 for a free explanation of the items and prices. The AI estimator and calculator provide an initial budget. Site measurement and a written quotation establish the final price.
- Check the validity period of the quotation and whether it includes the same items
- Confirm maintenance, extension, and change terms
- Set aside a contingency budget
FAQ
8 practical questions answered
01How many renovation complaints does the Consumer Council receive every year?
From 2017 to 2023, there were a total of 1,205 complaints about home improvement services, with an average of about 172 cases per year;[3] Under the revised 2026 classification, renovation and home maintenance works recorded 400 complaints in 2024, 347 in 2025 and 352 from January to September 2026.[1]
02What is the most common issue in renovation complaints?
Service quality (510 cases), delay/non-delivery (336 cases) and price disputes (120 cases).[3]
03How much should the deposit be?
The law does not stipulate the proportion. The principle is payment and acceptable project nodes to avoid large prepayments at one time; those who need to order materials can request proof of order.
04How far will the online valuation differ from the actual quote?
The Consumer Council’s mystery shopper survey found that the gap between the preliminary estimate and the actual price ranged from −32% to +28%.[3] The AI quotation assistant and calculator give preliminary estimates only. The written quotation after the tradesperson measures the site confirms the final price. (see published rates)
05The contractor said that the wall can be demolished without verification, is that right?
Nope. A survey by the Consumer Council found that about three-quarters of companies have such suggestions.[2] However, removing structural walls requires assessment by an authorized person and a registered structural engineer, and Buildings Department approval. Unapproved building works carry a maximum fine of HK$400,000 and two years' imprisonment.[4]
06If something happens, can I call someone?
You can first negotiate with the contractor in writing and then complain to the Consumer Council; the Consumer Council can mediate. If mediation fails, arbitration or expert ruling can be considered.[2]
07How do you reduce disputes?
Our 117 price items are all open to the public. The quotation is based on the work sequence quantity and the unit. A written quotation will be issued after the measurements are taken. Any additional items will be confirmed in writing first, and a full house drawing will be provided as the basis for acceptance. Welcome WhatsApp 5243 7747 for free consultation.
08What’s the problem if the quotation does not include a validity period?
There is no validity period. The contractor may need to re-quote if the price of materials increases. Only 50% of the quotations reviewed by the Consumer Council mentioned the validity period.[3] This should be stated on request before signing.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]Consumer Council: Complaint Figures (Complaint Statistics 2024-2026) Accessed: 2026-11-01
- [2]Consumer Council: 4 proposed measures to strengthen regulation of the home renovation industry (21 February 2024) Accessed: 2026-11-01
- [3]Consumer Council: Consumer Council’s Home Renovation Research Brief: Home Renovation Complaints Received by the Consumer Council Accessed: 2026-11-01
- [4]Buildings Department: Alteration and addition works to domestic premises Accessed: 2026-11-01
- PricesHK Create Design 2026 detailed project budget and public price list Accessed: 2026-11-01