01

First write the opening conditions as project boundaries instead of just setting a completion date

The first thing the customer has to decide is not the paint color card, but "what state can open the door?" The lease handover, shopping mall acceptance, merchant's own acceptance and official business operations are often different events. Write down the four dates one by one, and list the required drawings, cleaning, missing repairs, equipment testing, keys and documents next to them, so that the contractor can schedule the work with the same end point. If you only write a "completion date", it is easy for someone to think that it is completed, while the other party is still waiting for the property owner's approval or color correction.

The purpose of the store, the number of people it can accommodate, whether it shares systems with the mall, the duration of the project and the location of the change will all change fire safety considerations. The Buildings Department Code requires that means of escape enable safe evacuation of occupants and that openings or penetrations of fire barriers have adequate protection. This is not to apply the same approach to all retail stores, but to remind customers to identify changes that will affect escape or separation before the design is frozen.[2]

A practical approach is to create a one-page "opening conditions list": each item states the content, to whom it is submitted, the required date, evidence and alternatives if it is not completed. For example, being able to paint does not mean that the signboard can be powered on; being able to enter the property does not mean that the fire protection interface has been verified. This form should be updated with the quote, not just in the meeting minutes.

  • Separately list the dates of construction completion, property acceptance, business availability and missing correction dates
  • Obtain lease closing requirements, management office renovation manual, store floor plan and equipment list
  • Designate a person in charge and provide written evidence for each opening condition
Design renderings: retail space and display circulation.
Design renderings: retail space and display circulation. Select an image to enlarge

02

The first difference between shopping mall shops and street shops is who controls the construction window

The constraints of shopping mall projects are often not inside the store, but outside the store: whether the freight elevator can be used, where materials can be brought in and out, when they can be polished, during which time the garbage can be removed, how corridors and elevators should be protected, and whether common areas need to be restored after the night shift. These should not be assumed to be "night watch included". The customer should hand the original request from the management office to each bidder and ask for an itemized reply on who arranged the arrangement, who paid and when it will be completed.

Street shops may not necessarily have the same set of rules for goods lifts and hoardings, but exterior walls, signboards, windows, pavements, noise from neighboring shops and delivery times can still affect the design and process. Regardless of whether it is a shopping mall or a street shop, do not regard verbal statements from the property management as approval. Matters that have not yet been confirmed in writing should be listed in the quotation as a scope to be confirmed, rather than written as a fixed time commitment.

If it is expected that painting, sanding, assembly and disassembly, and cleaning will be carried out on different nights, the schedule should be based on "available working hours" rather than calendar days. Each update also deducts the time required for registration, moving, protecting, storing tools, cleaning and leaving the site; these are planning assumptions and should be verified by the property and site conditions. This article does not describe them as the general construction period in Hong Kong.

  • Get the latest construction hours, noise, freight elevator, garbage and security registration rules
  • Break down each change process, entry and exit, maintenance and cleaning responsibilities in the quotation
  • Logistics or time slots without written approval are marked as risks rather than established conditions.
Five types of project scopes that should be separated from the same quotation sheet

You can swipe left or right on your phone to view the complete table.

Project scopeMeasuring/valuing methodThe quotation must be clearly stated item by itemCommon non-coverage or risks
Wall and ceiling paintingAccording to the actual measured expansion area, list it in square feet or square meters; write the primer and topcoat separately.Substrate assumptions, partial or full stripping, skim coats, sanding, primer, topcoat count, brand and range, colour code, sample, protection and cleaningMistake the usable area as the actual amount of paint; dark coverage, color difference, water seepage sources and hidden surfaces cannot be included by default
Partial shoveling and repairAccording to area, location or tentative quantity, it should not be mixed with the general painting unit priceTreatment methods for blistering, powdering, mildew, cracks, and water seepage marks; photography, price revision, and approval procedures when assumptions are found to be exceededIf persistent water seepage or base defects are not dealt with first, new paint cannot replace radical treatment; scope disputes are prone to arise after construction starts.
Night construction and site protectionListed by every update, every night, accessible time period or designated protection itemsWho is responsible for entry, closing of work, noise processes, freight elevators, hoardings, corridor protection, ventilation, dust prevention, temporary garbage storage and resetting the next day?Just write "Night Watch" without time period or logistics restrictions; failure to remove materials or clean at the time specified by the management office may affect the next day's operations.
Property application and coordination of shared facilitiesDisaggregated by management office charge sheet, per-time or tentative itemsRenovation manual, plan/material submission, deposit, security registration, freight elevator reservation, test witness and who communicates with the management officeManagement office deposits, application fees, designated contractor fees and shared system arrangements should not be assumed to be included in the paint price
Fire protection and fixed power interfaceListed separately by professional engineering, testing and documentation scopeRetained or modified equipment, blackout windows, registered contractors, test projects, delivery documents and exclusionsIf openings through fire barriers, escape routes or fixed electrical changes are not verified, general renovation work cannot replace professional assessment.
Completion cleaning and defect repairList the work by list, scope or before and after the deliveryProtection removal, glass and sign surface cleaning, touch-up location, color difference judgment, missing period, document and key handoverOnly agree on "completion" without defining "property acceptance" or "available for business"; only discovering the deficiencies at the last night will reduce the space for corrections

This table is used to enable different contractors to quote prices based on the same boundaries and is not a price list. Fire barrier openings and fixed electrical connections need to be checked according to the actual design, property and qualified person requirements. [2] [3] [2][3]

Design renderings: The protection and site preparation for night shop projects do not replace site approval.
Design renderings: The protection and site preparation for night shop projects do not replace site approval. Select an image to enlarge
Wall condition before painting in Jordan | HK Create Design
Site photo: Painting in Jordan, June 2026. HK Create Design. Select an image to enlarge
Shopping mall fit-outs: illustrated facts and figures | HK Create Design
Shopping mall fit-outs: key figures at a glance | HK Create Design Select an image to enlarge

03

Paint decisions start with the substrate: the same color can be a completely different project

"Two coats of topcoat" only covers the last two steps. When the old wall has chalking, hollowing, blistering, oil stains, mildew spots, cracks or water marks, the customer should first ask: Is the problem a loose surface, partial repair, or is there still a water source? If the water source is not treated, moisture-proof primer or topcoat alone should not be described as a cure. The quotation should separately list inspection, partial shoveling, dust leveling, sanding and dust removal, sealing or priming, topcoat, repair and cleaning to provide a basis for changes.

Walls, ceilings, drywall, metal and wood have different substrates, and the same coating system cannot be applied to all locations. Customers can request a listing of the product range, gloss, color number and number of layers for each surface, and first see a swatch in real light. Dark colors, bright colors, signature back panels and high-touch locations should especially ask about covering, closing and future touch-up methods, rather than making decisions based on color cards alone.

The acceptance also needs to go back to the scope: under the agreed viewing distance, lighting and surface condition, who confirms the color difference, brush marks, sagging, sand marks, bumps or closing of the opening edge? It is more effective to write the acceptance method and repainting deadline into the missing list than to argue about "it looks about the same to the naked eye" after the completion.

  • Substrates and coating systems separated by wall, ceiling, metal, wood
  • It is required to indicate the boundary between partial repair and comprehensive shoveling and the change procedures.
  • Use on-site color test boards to confirm the color number, gloss and look and feel before large-scale construction

04

Low VOC, dry and ventilated: read the product information, but don’t turn it into a guarantee of stay

Hong Kong has VOC content limits for regulated construction paints. The values ​​listed by the Environmental Protection Agency are limits for product categories and are calculated based on ready-to-use conditions; they help verify the supply of products, but they do not mean that the odor in the store has dissipated, ventilation is adequate, or that anyone can start business safely immediately.[4] Therefore, before purchasing, you should obtain the technical information and safety information of the product to be used, and confirm whether it corresponds to the series listed in the quotation.

The product data sheet applies only to this product and under this condition. Taking Dulux Colorful Wall Paint A600 as an example, its technical data states that at 25°C and a relative humidity of 50%, a single layer will dry to the surface in about 0.5-1 hour and recoat in about 2-3 hours; it should not be applied when the substrate temperature is lower than 10°C or the ambient humidity is higher than 85%.[5] This example shows why the schedule should write "product, number of layers, temperature, humidity and ventilation conditions" instead of promising that all paint will dry overnight.

Don’t take “low odor,” “low VOC,” or any formaldehyde removal claim as a formaldehyde reduction percentage, health guarantee, or approval to open the door. During construction, ventilation, isolation, dust prevention, personal protection, and remaining materials must still be arranged according to the site; when to seal boards, cover, display goods, or allow employees to enter the site should be determined by product requirements, actual environment, and property rules.

  • Obtain the technical information and safety information of the actually used products from the supplier
  • Treat surface drying, recoating and ventilation conditions as schedule inputs rather than fixed commitments
  • Don’t use low-VOC labels to replace on-site odor, cleaning, ventilation and property inspection arrangements
Worked example 1

Quantity example one: estimating the area to paint in a 680 sq ft shop

Assumptions

  • This is an assumption for explanation, not a completed case by the company, nor a formal quotation.
  • The shop has 680 sq ft of saleable area. Use the quick calculator's saleable area × 3 rule for an initial estimate of the painted surface.
  • It is assumed that two pieces of floor-to-ceiling glass and one door opening total 96 square feet, and no painting is required; it does not take into account the two sides of the new partition wall, ceiling shape, cabinet back, signboard back panel, or whether the opening can actually be fastened.

How to calculate quantities

  1. Approximate wall and ceiling surface area: 680 sq ft × 3 = 2,040 sq ft.
  2. Provisional paintable area: 2,040 sq ft − an assumed 96 sq ft of openings = 1,944 sq ft.
  3. Submit 1,944 square feet to the contractor along with photos, floor plans and the location to be painted, and ask for confirmation wall by wall and ceiling by ceiling instead of directly multiplying the unit price per square foot.

Under the above assumptions, the tentative paintable area used for discussion is 1,944 square feet; it is only used to find out the range that needs to be measured, not the final work volume or budget.

Company "×3" is a quick version of the initial calculation rule. The actual measurement will be affected by the height of the building, the number of partitions, ceilings, door and window openings, whether the cabinet backs are painted and the condition of the substrate; any shopping mall protection, night watch, property fees, repairs or professional works are not derived from this calculation. [1]

Use your square footage instead and see a reference budget
Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge

05

How to use the area without distortion: the initial estimate, actual measurement and quotation should be divided into three levels

An initial estimate indicates project scale. The quick calculator uses saleable area × 3 for painted surface area to help clients budget before detailed plans are ready.[1] However, the actual measurements will be different due to the new partition walls on both sides of the store, floor height, ceiling, column positions, back of display cabinets, glass doors and windows, non-painting locations and construction at high places. Taking the initial estimate directly as the official contract quantity will make it difficult to judge subsequent additions.

The second level is the scale. A good scale doesn't have to be complicated, but it should at least separate walls, ceilings, partitions, door and window openings, special materials and locations. If the contractor advocates not deducting certain types of small openings, or calculating certain locations based on projected area, the rules should be noted in the same column; the purpose is to make the three quotations comparable, not to let the customer learn to do their own construction.

Then compare commercial terms: included steps, minimum charges, photos to confirm substrate problems, remeasurement rates and who can approve changes. Use provisional items for uncertain quantities and distinguish them from fixed prices.

  • Save the initial estimated area, on-site measured area and contracted pricing area separately.
  • Also attach floor plans, elevations or photos so that each quotation corresponds to the same batch of surfaces.
  • Specify rules for deducting openings, special heights, minimum charges and provisional quantities.
Floor grinding and levelling | HK Create Design
Site photo: Flooring work on site. HK Create Design. Select an image to enlarge

06

When comparing quotes, first compare “what’s not included”

The two totals are very different, so don't assume that one is particularly cheap or expensive. Put the two quotes into the scope of work table above and ask line by line whether it includes substrate, protection, night manpower, freight elevators and garbage, application fees and deposits, material brand, professional interfaces, testing, cleaning and defective repairs. If one of the items is not listed, it should be marked as "to be confirmed" instead of filling in zeros in the comparison table.

Payment arrangements, change orders, construction schedules, maintenance, insurance and termination terms shall be subject to written agreement between the parties. The customer can request that each change be accompanied by reasons, photos or drawings, scope, impact on amount, impact on construction period and approver. However, this article only provides general project management information and is not a legal opinion, nor does it draw legal conclusions on any contract provisions.

If water seepage, old lines, illegal modifications, concrete problems or unknown materials are discovered on site, the correct process is not to immediately verbally increase the price or force it to be done, but to suspend the affected area, record the current situation, have the appropriate person evaluate it, and then confirm the option. This not only guarantees the opening day, but also avoids burying risks that are not originally covered by the paint into a vague total price.

  • All quotations are required to be responded to according to the same drawing, the same scope table and the same delivery definition.
  • Separate basic projects, tentative projects, owner materials, property fees and items not included
  • Any changes must first obtain written confirmation of the scope, amount and impact on the construction period.
From data freezing to five delivery levels before opening the door

You can swipe left or right on your phone to view the complete table.

levelThings that customers need to confirmEvidence of completion that may be requestedDelayed or additional early signals
1. Status and Scope FreezeCurrent dimensions, lease delivery date, store usage, reserved equipment, design drawings, material samples and management office renovation manualDimensional floor plan, current condition photos, scope sheet and list of items to be confirmedThe plans do not match the current situation; all walls, ceilings or new partitions are measured based on salable area only
2. Property approval and construction windowWho submits information, construction period, noise restrictions, freight elevators, hoardings, garbage routes, security registration and depositWritten reply from the management office, reserved time slot and logistics arrangements; unapproved items are clearly marked in redTreat the verbal reply as approval; if the order or change has not been completed before approval, the process will need to be changed in the future.
3. Pre-concealment inspectionBefore boarding, trenching or ceiling sealing, check electrical wiring, pipes, access openings, fire separations and equipment that must be retainedOn-site photos, inspection records and change confirmation; follow-up by relevant professionals when necessaryNew wall trunking, air ducts or pipes are added without confirming fire protection; access openings are covered by renovations
4. Paint and functional testingSubstrate preparation, color testing, construction conditions for each layer, ventilation, odor management, and testing arrangements for lighting, sockets, signage, and air conditioning interfacesConfirmed test panels, product information, process records, test results and to-be-repaired listTreat the surface dryer as if it can be closed or opened immediately; no time is reserved for color difference, touch-up and cleaning.
5. Joint acceptance and preparation for openingDistinguish between the three dates of construction completion, property acceptance and opening; list who signed for the missing documents and keysJoint missing list, cleaning confirmation, maintenance information, drawings and applicable testing/certification documentsLeave unfinished property requirements or documents until opening day; missing no responsibility and completion date

Fire safety requirements and project duration are affected by building use, occupancy and actual changes; this table is a project management sequence and is not a substitute for statutory approval or professional advice. [2] [6] [2][6]

Completed custom floor-to-ceiling wardrobe | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge
Made-to-measure kitchen cabinets and wall units | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

07

The risk of night construction is not only in noise, but also in handover and protection

Night shift operations should be broken down according to risk. The conditions for sanding, shoveling, cutting or disassembling are different from those of low-noise touch-up, color testing, cleaning and document sorting; whether it can be done on the same night depends on the property period, ventilation, dust prevention, freight and operating requirements of the next day. The construction party and the customer should confirm the scope of work that can be done that night before each update, so as to avoid workers arriving at the scene to learn that the freight elevator cannot be used or dust cannot be generated.

Protection is not just "protection included". It is necessary to write down clearly what floors, glass, cabinets, signboards, corridors, elevators and fire-fighting equipment in the store will be protected, what methods will be used, who will inspect them daily and when they will be removed. Conservation work can neither be assumed to be of unlimited store-wide scope, nor can it be completely ignored just because it is not on the paint job.

A brief record should be left at the handover: areas that have been completed, areas that are wet or inaccessible, equipment that is still covered, materials that need to be brought in the next night, and any newly discovered damage. These records will not replace a formal acceptance, but will allow the store, management and contractors to have the same version of the current situation for the next shift.

  • Confirm the construction area, noise restrictions, freight elevator and garbage departure time before each update
  • Define the boundaries of responsibility within the store, common areas and existing equipment in the protection list
  • After each update, photos and short lists are used to record completions, restrictions and to-do items.

08

Electricity, fire protection, demolition and modification: first check the professional scope, and then talk about renovation and closing

When adding new display cabinets, signboards, air conditioners or equipment, you should not just ask how many sockets there are. The installation, inspection, testing, repair and modification of fixed electrical installations are electrical works, and the Electrical and Mechanical Services Department points out that they should be carried out by registered electrical contractors; the work involved must also coordinate sufficient power outage time and temporary arrangements.[3] Customers can ask the other party to explain the load verification, power outage window, work scope, testing and documentation, but they should not change the wiring or handle the live equipment by themselves.

The interfaces between fire partitions, escape routes, fire doors, air ducts, wire troughs and pipes should not be obscured by decorative sealing boards. The Buildings Department's Code requires that equipment openings passing through fire barriers be protected by appropriate fire barriers or other fire barriers to maintain the required fire resistance.[2] Therefore, relevant openings and maintenance arrangements must be checked before sealing; whether application, testing, or handling by a designated contractor should be confirmed based on actual project and property requirements.

Partitions, signage, windows, facades and certain minor building works may be subject to different regulatory and project restrictions. The Buildings Department explains that minor works are divided into three levels according to their nature, scale, complexity and safety risks, and are carried out by prescribed construction professionals or prescribed registered contractors.[6] Shop renovations can fall into different categories. Ask for the classification to be checked before demolition or alteration. For work involving structural elements,Aluminium windows, external walls, work at height, suspect materials or demolition, do not attempt or demonstrate the work yourself.

  • List new equipment, expected load, power outage needs and registered contractor information
  • Before sealing the board or closing the opening, check the fire separation, penetrations, access openings and equipment that need to be retained.
  • Confirm the applicable project type and property requirements before removing walls, signboards, windows or other modifications
Worked example 2

Quantity example two: using a product data sheet to estimate the theoretical quantity needed for two topcoats

Assumptions

  • This is an assumption for illustrative purposes, not a completed case by the company, nor a purchase or product recommendation.
  • The 1,944 square feet that can be painted are used in the previous example, assuming only two coats of topcoat are applied; excluding primer, repair, color test, loss, dark color topcoat, spray loss and remaining materials.
  • Just to show you how to read the technical sheet, let's assume you are using Dulux Ultra Color Wall Paint A600; the data sheet lists a theoretical coating of 13-16 square meters per liter per coat, the actual coating will be affected by the surface and application method.

How to calculate quantities

  1. Area per coat: 1,944 sq ft ÷ 10.7639 = 180.6 m².
  2. Area across both coats: 180.6 m² × 2 coats = 361.2 m²-coats.
  3. Theoretical quantity: 361.2 ÷ 16 = 22.6 litres and 361.2 ÷ 13 = 27.8 litres.

Under this narrow assumption, the theoretical consumption of two top coats is approximately 22.6–27.8 liters. Before purchasing, the construction party should still review the product packaging, color, substrate and on-site loss.

A600's 13–16 m²/litre/lane is a theoretical figure for a specific product and is not a general coverage for any paint. The drying and recoating times in this data sheet are only valid under the specified temperature and humidity, and cannot be deduced into the mall's opening date or healthy occupancy guarantee. [5]

Use your square footage instead and see a reference budget
Shopping mall fit-outs: illustrated checklist | HK Create Design
Shopping mall fit-outs: checklist | HK Create Design Select an image to enlarge

09

Use a missing list for delivery acceptance instead of relying on "almost done"

It is advisable to arrange a pre-inspection before handover so that the client, construction party and, if necessary, property representatives can view the same areas at the same time. The checklist should include location, problem description, photos, completion criteria, person responsible, and completion date. Paint can include color difference, damage, sagging, opening edge closing, masking residue and cleaning; engineering interfaces include visible equipment, access openings, labels, switches and information that needs to be handed over.

Don’t turn a missing list into an open-ended requirement. Each item must be returned to the confirmed drawings, samples, quotations and management requirements; new design expectations will be dealt with separately. Conversely, if documentation, testing, or management requirements are not yet complete, don’t cross them out just because the store looks tidy.

The final inspection before opening should review whether passages, exits, fire equipment perimeters, materials and protection are blocked, and confirm that all unfinished work is safely isolated and clearly arranged. This article does not issue a certificate of conformity for any project; the required professional testing or certification must be provided by the appropriate person based on the actual project.

  • Create a missing list with location, photo, completion criteria, responsible person and date
  • Separately handle missing and new requirements within the contract scope to avoid confusion
  • Pre-handover verification of documents, cleaning, protection of demolition and safety arrangements for unfinished work

10

How to use the company’s online tools: Make an initial estimate first, then take the problem to scale

The company's 2026 online estimator and enquiries are free. The quick version gives three examples: basic whole-home renovation, repainting and floor tiling. The catalogue lists 117 options in 8 categories. Of these, 116 have indicative unit prices and 1 rooftop package is priced on enquiry.[1] This information can be used to organize the projects you want to ask about, but it is not the automatic all-inclusive price of shopping mall shops, nor is it the average price in the Hong Kong market. Detailed version for shops or special projects or directly confirmed according to on-site conditions.

Pay particular attention to the exclusions from the quick schemes: complete kitchen and bathroom rebuilds, waterproofing, replumbing and rewiring,Bespoke furniture, tiles, sanitaryware and other finishes. A total budget does not establish that these items, works insurance, management deposits or renovation administration fees are included.[1] The "useful area x 3" for painting is only a preliminary calculation; 20% is reserved for customer planning and is not an automatic additional fee charged by the company.[1]

A site visit can be arranged if required. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. Online estimates and enquiries are free. Before enquiring or booking on WhatsApp 5243 7747, gather the address and floor, site photos, dimensions, management rules, target opening date, equipment and power requirements, and materials already chosen or still undecided.[1] The formal scope, price and constructability are still subject to on-site verification and written quotations from both parties.

  • Use the initial estimate to sort out the scope first, but don’t treat the example plan as an all-inclusive quotation for the mall.
  • Bring dimensions, photos, management requirements, opening date and equipment information to measure
  • Verify the process, materials, exclusions, changes and delivery conditions in writing after measuring.

FAQ

7 practical questions answered

01Do shopping mall stores have to be constructed at night?

uncertain. Whether construction can be carried out during the day or at night shall be subject to the shopping mall management office's requirements for the protection of noise, odor, freight elevators, security, hoardings, garbage and public areas. Even if night shifts are allowed, the actual entry, transportation, available work procedures, completion of cleaning and departure times must be clearly stated. Do not just write "night construction" in the quotation. If the approval or construction window has not yet been confirmed, it should be marked as a pending risk rather than committing to a certain minimum construction period.

02Is it enough to quote "all-inclusive paint"?

Usually more detail is needed. Specify surfaces and measured areas, local or full stripping, skim and sanding requirements, primer and topcoat products and counts, colour samples, protection, night shifts, ventilation, cleaning and touch-ups. List unconfirmed seepage, concealed defects, high-level work, property fees and specialist work as exclusions or provisional items.

03After choosing low-VOC or low-odor paint, is it guaranteed to open the next day?

No such guarantee can be made. The VOC content limit is an indicator of regulated products and is not a guarantee of store air quality, odor dissipation, ventilation effectiveness or suitability for all people to enter.[4] The product's surface drying and recoating time are also affected by temperature, humidity and coating conditions; for example, the time listed in the A600 data sheet only applies to specified conditions.[5] Scheduling should be based on intended product information, site ventilation, property rules, cleaning schedules and actual construction status.

04Why are the paint prices per square foot of two contractors similar, but the total amount can still be very different?

The most common reason is that the pricing area and project boundaries are different. One party may only count the walls, and the other party may include ceilings, partitions, doors and windows, protection or night shifts; or one party may assume that the base is in good condition, and the other party may have included partial shoveling and repairs. Comparison can only be made by comparing the area tables, number of floors, products, protection, logistics, cleaning, changes and items not included on both sides line by line. Uncertain items should not be filled in with zero, nor should a total amount be used to force judgments.

05If a socket or signboard is installed in the store to provide power, do I need to check WR2?

Work involving fixed electrical installations should be handled by a registered electrical contractor and checked for load, outage and testing needs.[3] If the allowable load of fixed electrical installations in general commercial premises exceeds 100 amps, inspection, testing and WR2 must be arranged at least every 5 years; individual designated premises or high-voltage installations may have requirements every 12 months.[3] You cannot judge whether it is suitable due to the small size of the store or the small amount of work. The contractor should confirm based on the store's installation and actual changes.

06In what order should painting, sealing and fire/electrical connections be handled?

Confirm the design and property requirements first, and then check concealed wiring, pipes, maintenance and fire separation before sealing boards or grooves; Buildings Department regulations require that equipment openings that pass through fire barriers should be properly protected.[2] Painting can be arranged overlapping with other processes, but the interfaces that need to be inspected or modified should not be obscured to achieve color effects. Finally, patching, cleaning, functional testing and file handover are completed according to the same missing list. When it comes to structural, fire protection or fixed electrical, let the appropriate professionals decide on the technical approach.

07Do I have to pay extra for the 20% reservation estimated by the company online?

no. The company's public page states that the 20% included in the upper limit is a planning reservation by the customer and is not an automatic surcharge by the company; the actual amount must still be confirmed based on measurements, processes and formal written quotations.[1] This approach is appropriate for thinking of undetermined scope separately from confirmed items, but it does not replace formal verification by management of deposits, insurance, materials, professional engineering, or other unselected items.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]HK Create Design 2026 Quick Renovation Budget and Pricing Instructions Accessed: 2026-10-21
  2. [2]Buildings Department: Fire Safety Code for Buildings 2011 (2024 Edition) Accessed: 2026-10-21
  3. [3]Electrical and Mechanical Services Department: Electrical Installations in Buildings—Regular Inspection and Maintenance Accessed: 2026-10-21
  4. [4]Environmental Protection Department: Volatile organic compound content limits for regulated construction paints Accessed: 2026-10-21
  5. [5]Dulux Colorful Wall Paint A600 Product Technical Data Sheet Accessed: 2026-10-21
  6. [6]Buildings Department: Minor Works Control System Accessed: 2026-10-21