01

What published Hong Kong restaurant fit-out prices are available?

Yue Lee Engineering's February 2026 budget table listed renovation of an ordinary restaurant of around 500 to 1,000 sq ft at HK$500,000 to HK$900,000. This is that company's published range for a whole fit-out. A partial booth refurbishment should be priced by the actual number of units and operations.[1]

  • Separate renovation work, kitchen equipment and professional fees.

02

Budget the takeover premium, construction work and opening working capital separately

The premium may include equipment and furniture. Obtain a handover list, models, proof of ownership and service records. Rectification, repairs or relocation after handover are separate. Allow for rent, deposits and expenses during closure.

03

When is the kitchen worth keeping?

Consider reuse if the menu, cooking positions and utilities are close to the existing setup. Have a qualified contractor inspect, measure and test the equipment and keep the results. Equipment that powers on still needs checks for load, extraction, heat dissipation and service access.

Worked example 1

A Hong Kong-style café retaining its existing kitchen

Assumptions

  • Assume the existing menu and cooking positions stay the same.

How to calculate quantities

  1. Confirm model numbers and test operation. Arrange cleaning in place or repairs.
  2. Count booths and light fittings separately before comparing front-of-house quotations.

Prepare separate lists of items to retain and items to provide new.

Illustrative scenario. Repairs, licensing and site conditions still need verification. [2]

Use your square footage instead and see a reference budget

04

Compare two schemes for the same shop

Mark “retain”, “new” and “to check” on the same plan. Price shared protection, handling and clearance on the same basis. Include specialist fees for altered ductwork or custom stainless steel equipment in the relevant option.

Two quotations for the same shop

You can swipe left or right on your phone to view the complete table.

ItemRetain the back kitchenAlter the back kitchen
Cooking equipmentList usable models after testingList selection, delivery and commissioning
VentilationCheck condition and cleaning accessCheck available service routes, approvals and alterations
Reception areaThe same seating planThe same seating plan

Illustrative comparison. Confirm what can be kept through a site assessment. [2]

Ceiling wiring for pendant lights above dining tables
For lighting refurbishment, confirm supply, installation, cabling and maintenance access. Select an image to enlarge

05

Break down the work into verifiable quantities

Ask for separate lines for strip-out and protection, front-of-house furniture and finishes, commercial equipment, ventilation and grease interception, plumbing, electrical and fire services, handover and commissioning. Each needs quantities, units, specifications, installation inclusions and interface responsibilities.[2]

  • For a new refrigerator, for example, ask separately about old unit disposal, carrying the replacement upstairs, connections, commissioning and warranty.
Compare delivered totals

You can swipe left or right on your phone to view the complete table.

Quotation line to checkQuestions to ask
Remove existing fittingsIs equipment removal included?
SupplyEx-factory price or delivered price at the shop?
HandoverWho handles commissioning, training and after-sales support?

Based on the comparison method in the owner's handbook. [2]

06

Allow for the cost of closing the shop

Ask management about work hours and the goods lift. Two-person tables can be delivered in batches, while ductwork and electrics may need separate testing. Record delivery and approval waits separately from construction days.

Worked example 2

A small shop switching to hot food

Assumptions

  • Assume the new menu adds more frying and wok cooking.

How to calculate quantities

  1. List equipment running simultaneously at peak times, then review electrical power, fume extraction and make-up air.
  2. Have a specialist contractor assess feasibility before comparing the cost of a kitchen upgrade with finding different premises.

Compare two opening scenarios before deciding whether to lease.

Confirm the applicable licences and approvals for the case. [3]

Use your square footage instead and see a reference budget

07

When can the total price be confirmed?

Attach confirmed drawings, model numbers and supplier prices to the quotation version. For inaccessible ducts or concealed pipes, list a provisional sum, who confirms it and when. Before approving extras, explain price and handover date changes.

08

Which information is most useful for a quotation?

Send a whole-shop floor plan, front- and back-of-house photos, proposed menu, equipment to retain and target reopening date. Start with theCompare items on the restaurant renovation service page, then send the information to the same project lead.

FAQ

6 practical questions answered

01Can I multiply a per-foot price by the entire shop area?

Use it for initial planning only. Ducts, power upgrades, kitchen equipment and handling must be priced for the actual scope.

02Does taking over the equipment include its warranty?

Ask the seller for purchase documents, remaining warranty and transfer terms, and check them with the service provider.

03Can I renovate only the front of house?

You can request prices for booths, tables, chairs, finishes and lighting first. Separately check whether the changes affect approved drawings or other systems.

04How do I compare two totals?

Align quantities, units and delivery terms, add missing items, then compare the two delivered and installed totals.

05When should I set the opening date?

Set it once the landlord, management, equipment delivery, commissioning and licensing milestones each have an owner and confirmed date.

06Can some items be excluded from the initial quotation?

Yes. Specify the excluded items, who will price them and any effect on the opening date.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Yue Lee Engineering | Hong Kong restaurant fit-out costs explained (27 February 2026) Accessed: 2026-11-24
  2. [2]HK Create Design | Restaurant premises and quotation handbook Accessed: 2026-11-24
  3. [3]Food and Environmental Hygiene Department | Guide to the type of licence required Accessed: 2026-11-24