01
Determine the scope first: local improvements, partial repaving, or whole-house redesign?
"Whole-house wiring replacement" is not the inevitable answer, nor should it be just a sales name. You can ask four things first: whether the existing sockets are hot, scorched, loose or tripping repeatedly; whether induction cookers, ovens, water heaters, air conditioners, washing and drying equipment will be added to the new renovation; whether new partitions or cabinets will cover the original sockets; whether old wiring, grounding and circuit markings are no longer traceable. If only a small number of positions are adjusted and the inspection results support the continued use, the project may be partial; if the loads, intervals and line conditions change at the same time, the scope must be upgraded to an overall assessment.
Do not dismantle the distribution box, pull out the wall cable, or use "the socket has power" to judge safety. The Electrical and Mechanical Services Department classifies fixed distribution boxes, wiring and lighting as fixed electrical installations; any work related to their installation, calibration, inspection, testing, maintenance, modification or repair is classified as electrical engineering.[2] If there is a burning smell, electric shock sensation, immersion in water, abnormal heating of sockets or switch surfaces, frequent switch jumps, etc., you should stop using the device in question and arrange for a registered person to inspect it.
Whole-home planning need not put every appliance on a dedicated circuit. Give the designer appliance ratings, models or manuals and explain what will run together. The responsible professional then designs for the site's supply, cable routes, protection and applicable requirements. Ask for those assumptions in writing.
- Take pictures of the inside and outside of the existing distribution box, circuit markings, abnormal sockets and traces of old maintenance; do not take pictures or touch live parts.
- List the fixed electrical appliances purchased and planned to purchase, with models, ratings, expected locations and simultaneous usage scenarios.
- Divide "must add", "hope to reserve" and "may add in the future" into three columns to avoid taking the reservation as the confirmed construction volume.

02
Drawing an electricity consumption map based on life processes: the number of sockets is only the last step
First place the beds, desks, dining tables, TV cabinets, refrigerators, washing machines, kitchen cabinets and air conditioners on the furniture plan, and then mark where people charge, work, cook, clean and store. The socket should avoid being completely covered by the fixed cabinet back; at the same time, space should be reserved for safe plugging and unplugging and future maintenance. This reduces reliance on extension cords and temporary extension strips more than "an average of two sockets per wall."
Secondly, power consumption points are divided into three categories: general portable equipment, fixed or high power consumption equipment, and weak current/communication equipment. The Electrical and Mechanical Services Department reminds that new in-wall circuits must be protected by appropriate enclosures, such as being placed in electrical conduits; power lines must also be separated from telephone and telecommunications lines, unless specific safety requirements are met.[3] Therefore, the TV or network panel is not just "one more switch". It must be clearly stated in the quotation whether it only includes the panel and wiring, whether it involves communication service connection, and how to separate the strong and weak electricity.
Finally, all points are turned over to the electrician to turn into a circuit and protection plan. Large electrical appliances should be powered by independent sockets, and there should be enough sockets indoors.[3] This is a planning principle and does not mean that the homeowner specifies the circuit breaker rating, wire size, or breaking capacity. Giving equipment information and usage methods to the person in charge is more reliable than requiring a certain "standard safety number".
- Color-code the locations of general sockets, fixed electrical appliances, lighting/switches and TV/network on the floor plan.
- Write down what equipment will be connected to each location, whether it will be plugged in for a long time, and whether it can be started at the same time.
- Ask the quotation to give separate quantities and units for sockets, lighting points, switches, data/low-voltage points and dedicated circuits.
You can swipe left or right on your phone to view the complete table.
| Project scope | Pricing unit/public reference price | Publicly listed include | May not be included or need to be checked first | decision risk |
|---|---|---|---|---|
| Electrical inspection | HK$770 per session; HK$1,650 for comprehensive inspection of multi-circuit or open kitchen | Trip switch, leakage and circuit inspection; preliminary report | Rerouting, grooving, parts and repair work discovered after inspection | The preliminary report is not a renovation quotation; the fault location and hidden lines still need to be confirmed on site |
| Added 13A unit socket (concealed pipe) | HK$640 per group | Wall chasing, cabling, back boxes and faceplates, with skim-coat reinstatement | Check whether extra circuits, distribution board capacity changes, furniture relocation or special finishing are needed. | Treating "a set of sockets" as a capacity that can be infinitely increased will ignore circuit and load assessment. |
| Added 13A dual-bit/TV/network bit | HK$1,200 per group | Wall chasing, cabling, back boxes and faceplates, with skim-coat reinstatement | On-site feasibility of telecommunications service connection, equipment body, routing and isolation from strong electricity | TV, network and electricity need to be understood separately; they cannot be compared only by the number of panels. |
| Add a dedicated circuit | HK$3,350 per trip | Special circuit and main switch connection for water heater, induction cooker or oven | Increase the capacity of entering the house, as well as the actual specifications of electrical appliances and on-site wiring restrictions | Placing an order just because you "want to be independent" does not necessarily mean it is feasible or sufficient on site. |
| Replace the distribution board | HK$6,800 each | Modification of old fuse box to MCB/RCD and circuit marking | Existing power supply conditions, circuit design, circuit breaker model, power outage and any repairs | Changing the box does not mean that all the entrance wires have been re-routed; circuit tables and testing/certification arrangements should be requested |
These are HK Create Design's October 2026 rates and descriptions for initial budgets only. They do not represent market averages, fixed packages or formal quotes. A site visit and written quotation establish the actual price. Record quantities, product models, scope boundaries and variation approval before signing. [8]



03
Kitchen, Bathroom and Outdoors: Let’s Explain Water, Heat and Maintenance Spaces First
It is not advisable to rely on floor plans to estimate distances in bathrooms. The Electrical and Mechanical Services Department stipulates that the sockets in the bathroom must be at least 0.6 meters away from the bathtub and shower tank, and the socket circuits must be protected by current leakage circuit breakers; the switches for the lights, exhaust fans and electric water heaters in the bathroom should be installed outside the bathroom.[3] Registered personnel should be allowed to verify bathtubs, showerheads, doors, cabinets, windows and actual wet areas on site rather than requiring relocation after tiling.
The kitchen should list the usage methods of cooking stoves, gas switches, faucets, sinks, range hoods, refrigerators and small appliances at the same time. The official manual states that sockets should not be installed near faucets, gas switches or cooking stoves.[3] "Nearest water source" does not necessarily mean "nearest water source"; homeowners can provide kitchen cabinet drawings and electrical appliance dimensions first, and let the on-site plan deal with height, avoidance and maintenance openings.
Outdoors, on the terrace, or in locations where there is a chance of being exposed to water, the official manual requires lights, sockets, and switches to be waterproof.[3] Work involving an external wall, window, podium, roof or common area needs additional checks beyond adding a socket. Check the deed of mutual covenant, building rules and any other legal or professional requirements. Do not removeAluminium windows, drill into an external wall or work on any live electrical installation.
- Mark the actual locations of the bathroom wet area, shower, bathtub, wash basin, water heater and extractor fan on the map.
- Provide dimensional drawings of kitchen cabinets, stoves, refrigerators and range hoods, with water points, air switches and maintenance openings marked.
- If you need electricity on the balcony, window or outdoors, please ask the management office and professionals first, rather than extending based on indoor practices.
04
Distribution boxes and protection devices: understand the information, but do not select or modify it yourself
The distribution box is a location where various circuits, isolation and protection arrangements are centrally managed. The Electrical and Mechanical Services Department points out that there must be signs inside the boxes indicating the purpose of each power line.[3] Homeowners can require labels to clearly correspond to living room sockets, lighting, air conditioners or designated equipment, and keep the final circuit list. This will greatly reduce the chance of accidentally turning off other positions when the switch trips in the future, and will also make it easier for the next person responsible for maintenance to interpret.
You will see labels such as MCB, RCD, RCBO, Type A, 30mA, 6kA or 10kA on the market. They are products and design materials, not answers that homeowners can substitute a slogan for design. For example, the specified Schneider Electric Acti9 iC60H RCBO A9D11832 is listed with ratings of 32A, 30mA, Type A, and 10,000A.[5] This only shows the model itself. It cannot be inferred that every Hong Kong residential circuit should choose 32A, 30mA or 10kA, nor does it mean that it is the only suitable product.
The quotation should indicate whether the distribution box is to be replaced, the purpose of each circuit, the brand and complete model of the protective device, and whether marking, testing and power outage arrangements are included. Don't accept a description that only says "change the water and air switch" without model number and circuit range. If site conditions indicate that it is necessary to adjust the in-house power supply or the existing box configuration, written explanations and quotations should be obtained first, rather than verbal additions during construction.
- An on-site assessment of existing cabinets, available locations, circuit markings, and any known trip records is required.
- Write the "product category" and "complete brand, model, and rated information" separately in the quotation, avoid just writing the abbreviation.
- Before completion, check whether each circuit label can correspond to the actual location and equipment.
Example 1: an initial budget for additional electrical points using published rates
Assumptions
- This is a hypothetical example to illustrate the planning method. It is not a completed case by our company, nor is it a formal project quotation.
- Illustrative scope after a survey: 2 new single 13 A socket sets, 1 new double 13 A socket, TV or network point, 2 new dedicated circuits and one basic electrical inspection.
- The company's 2026 public prices are adopted: HK$640/group, HK$1,200/group, HK$3,350/circuit, HK$770/time; no increase in entry capacity, structural engineering, management fees or unknown repairs are assumed.
How to calculate quantities
- Calculation: 2 × HK$640 = HK$1,280.
- Calculation: 1 × HK$1,200 = HK$1,200.
- Calculation: 2 × HK$3,350 = HK$6,700.
- Calculation: 1 × HK$770 = HK$770. Subtotal: HK$1,280 + HK$1,200 + HK$6,700 + HK$770 = HK$9,950.
- A homeowner's optional 20% planning allowance is HK$9,950 × 20% = HK$1,990, bringing the planning total to HK$11,940. It is not an automatic company charge.
For these assumed quantities, the published rates total HK$9,950. With the owner's optional 20% contingency, the indicative upper figure is HK$11,940. Confirm that both dedicated circuits are necessary, that the distribution board and supply can accommodate them, and how the new routes will be run and finished.
The company's website clearly states that the online estimate is not a formal project quotation, and the actual estimate is confirmed based on measurements, processes and formal quotation. This example does not include the appliance itself, any capacity upgrades, structural/fireproof component treatments, management fees, furniture relocation or hidden faults; it cannot be used for market price comparison. [7][8]

05
Who can do it and who is responsible for signing it: Registration checks and WR1 should not be left to the end
The Electrical and Mechanical Services Department maintains a register of registered electrical contractors for the purpose of allowing the public to check the information and authenticity of contractors registered to carry out electrical works in Hong Kong.[1] Before placing an order, you can check the company name or registration information, and request a quotation listing the information and work arrangements of the registered electrical engineers actually responsible for the project. Do not use your company’s self-identification, social media photos, or referral reviews as proof of registration.
Official guidance requires the registered electrical contractor to arrange inspection, testing and certification by an employed registered electrical worker before energising a completed fixed installation. This also applies to affected parts of an existing installation after repair, alteration or addition. The specified form isWR1. WR1(A) applies to some installations. The registered electrical worker responsible and the registered electrical contractor both endorse the certificate. The contractor can then issue it to the owner.[2]
This doesn't mean that every time you change a lightbulb or repair a portable appliance, it automatically becomes the same procedure; the key is whether the work involves fixed electrical installations. You can directly ask in the contract: Which parts of this project are fixed electrical installations? What testing will be done before completion? Which document will be submitted? Who will sign and when will it be submitted? If the answer is just "there must be evidence", it is still not enough to replace the written scope.
The Electrical and Mechanical Services Department also requires relevant test records, plans and documents to be kept for at least five years, and points out that the contractor should issue a copy of the test and inspection results records to the owner.[2] Homeowners should keep their own copies, final circuit diagrams, and photos of hidden wiring; this is information for future repairs and is not intended to increase administrative procedures.
Our standard wiring commonly uses Hilly and ei8ht single- and double-insulated cable, data cable and control cable. Options include Prysmian or Nexans, and Belden for data and signal cables. We select brands with product certifications such as 3C. Installation follows EMSD's Code of Practice for the Electricity (Wiring) Regulations. A registered electrical worker inspects and tests the work and issues the Work Completion Certificate (Form WR1)[9]. Schneider Electric switches and sockets are commonly used.
- Check the contractor's information in the Electrical and Mechanical Engineering Works Register and save a screenshot of the verification date on file.
- Before signing, write down who will be responsible for inspecting, testing, issuing and delivering applicable documents on the project.
- Ask for a copy of the test record, circuit table, material model and hidden location photos during handover.

06
Once you have to cut grooves, knock down walls or modify the kitchen: Risks other than electricity need to be addressed at the same time
Electrical planning often encounters "making grooves for wiring" or "removing walls and re-installing the kitchen". But whether the wall can be modified cannot be judged verbally by the renovation. The Buildings Department pointed out that if the demolition of structural walls, beams or columns is involved in private building units, the owners must appoint an authorized person and a registered structural engineer to conduct an assessment, submit drawings and obtain approval and consent before construction can be carried out by a registered contractor.[4] The electrician's wiring needs to match this premise, rather than in turn requiring the removal and modification of the structure for the socket location.
Some home renovation and simple works may be exempted from approval, but they must still comply with fire protection, structural and drainage standards.[4] Therefore, "no need to approve first" does not mean "can be chiseled at will". If non-structural partition walls, kitchens, bathrooms, drainage or fire protection components are involved, first check the approved plans, management office rules and required professional advice. The building's deed of mutual covenant or management office may have other construction period, protection, deposit and reporting requirements, which will also affect the quoted price.
Especially don’t knock down walls first to create an open kitchen. The Buildings Department reminds that the walls or doors enclosing the kitchen may have structural or fire-resistant functions; you should check the approved plans before making any changes and seek professional advice as appropriate.[4] This article only provides project coordination issues and does not constitute legal or construction professional advice.
- Mark all proposed grooves, wall demolition, door openings, kitchen and toilet modifications on the drawings.
- Check with the management office for renovation application, construction period, lift protection, insurance and deposit arrangements.
- If you have structural, fire-resistant, exterior wall, window or drainage concerns, seek confirmation from a qualified person before arranging electrical wiring.


07
A quote is not a total: Comparing five tiers with the same requirements list
Provide the same floor plan, appliance list and site assumptions to each bidder. Compare quantities for sockets, lights, switches, low-voltage/data points and dedicated circuits, along with conduits, cables, faceplates and protection. Itemise chasing, wiring, closing and painting, distribution board, labels, tests, certificates, protection, outages, haulage, management procedures and warranty. Ask which site-dependent items are in the total.
The table gives our published electrical rates and work descriptions. A socket and a dedicated circuit are different units of work. These figures are company references only. Any supply capacity upgrade for a new circuit is separately priced. ReplacingDistribution board replacement and adding a socket do not automatically renew all existing wiring.[8] Therefore, the lower total price may simply miss certain areas, rather than being a better deal for the same project.
The quick calculator offers examples for basic whole-flat renovation, repainting and floor tiling. The basic scheme excludes full kitchen and bathroom reconstruction, replumbing and rewiring, fitted furniture and finish tiles. Entering floor area gives a preliminary estimate for that scope.[7] Electrical work must be verified by location, circuit and site conditions in a detailed version or formal quote.
- Each item is required to have quantity, unit, unit price, material/model, included content and excluded content.
- Next to any "negotiable" or "on-site", write the trigger conditions, who approves and how to record.
- Before comparison, delete different projects or fill in the missing items before looking at the total amount.
You can swipe left or right on your phone to view the complete table.
| node | Information required by the landlord | What contractors/professionals should make clear | Credentials that can be retained | Nothing can be substituted |
|---|---|---|---|---|
| Pre-construction survey | Floor plan, location of furniture, photos of electrical appliance nameplates/instructions, photos of existing electrical boxes and switch records | Range of lines to be used or replaced, power outage arrangements, slotting and repair locations, and unknown conditions | Written scope, circuit sketches, on-site photos | Verbal promises over the phone cannot replace scope and assumptions |
| Qualification check | Company name and contact information | Information on registered electrical contractors, registered electrical workers responsible for the project and their applicable scope of work | Electrical and Mechanical Engineering Directory Search Results, Responsible Person Information and Quotation Documents | Company name, website claims or friend introductions cannot replace official verification |
| Construction and alterations | Furniture Protection, Construction Periods and Management Office Rules | Which circuits are affected, materials/models, quotation and written confirmation procedures after hidden problems are discovered | Supplement quotations, photos, material models and modification records | Unspecified "package package" cannot replace consent to changes. |
| Testing and Handover | Try it out bit by bit according to the requirements list | Inspection, testing, marking and certification arrangements for affected parts | Circuit identification, copy of test record, WR1 or WR1(A) if applicable, wiring photo | Just turning on a light or having power in an outlet is not a substitute for inspection, testing and documentation |
| Structural/kitchen changes | Approval of plans, building deed of mutual covenant and management office requirements (if any) | Whether it involves structural walls, fire-resistant components, drainage or needs to be handled according to the minor works system | Professional advice, approval/notification and confirmation records (if applicable) | The naked eye judgment that "it is not the main wall" cannot replace professional verification. |
The Electrical and Mechanical Services Department provides a list of registered electrical contractors for public inspection. After the fixed electrical installation is completed and before it is energized for use, the registered electrical contractor must arrange for the registered electrical workers employed by the registered electrical worker to inspect, test and issue a designated certificate. This also applies to the repair, modification or addition of existing installations to the affected parts. When it comes to structural or kitchen changes, there are also Buildings Department regulations and building documents to deal with. [1][2][4]
08
Use an online computer: think of it as a list of questions, not a commitment letter
Use the free online calculator by entering the flat's saleable area or selecting work items. Enquiries are free. Site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against an order.[7] WhatsApp query is 5243 7747. These arrangements can help you sort out your needs first, but the official price still depends on the dimensions, scope of work and written quotation.
The computer currently lists 117 projects and supporting options in 8 categories, 116 items have reference unit prices, and the other 1 rooftop package is yet to be revised.[7] This means that it is a split-item tool, rather than automatically including 117 things into one unit. Aluminum windows do not have a fixed unit price and need to be evaluated separately based on the problem, size and on-site safety arrangements; do not put it secretly into the electricity or quick budget.
The quick version estimates paint area from saleable area × 3 and flooring from total saleable area. The 20% is an owner's planning reserve.[7] This "quantify without pretending to be precise" approach also applies to electricity: use assumptions to figure out the questions to ask, and then use on-site surveys to confirm the true quantity, scope and feasibility.
- Confirm you are entering saleable area and keep the calculator's selected options and assumptions.
- List the water, electricity, kitchen and toilet, furniture, fabrics, management fees and engineering insurance that are not included in the quick budget separately. Do not default to zero.
- Before measuring, floor plans, photos, distribution boxes and electrical appliance information are provided via WhatsApp to reduce errors in estimating based on area alone.
09
How to manage changes during construction: Hidden issues should be confirmed in writing first
Hidden old wiring, seepage, debonded finishes, concealed services and areas that cannot be chased often affect the budget more than the switch plates. For a variation, request photos, location, diagnosis, options, price and timing. Agree it in writing before adding it to the scope.
The order of arrangement is especially important if there are also plumbing, waterproofing, tiling or painting. The location of the electrical power must be confirmed before sealing, plastering, laying bricks and making furniture; however, the source of water seepage has not been dealt with and cannot be claimed to have been solved by repainting or replacing the control surface. Formaldehyde removal or completion of cleaning cannot provide a guarantee of health or immediate occupancy, and judgments should be made based on actual materials, ventilation and personal conditions.
Our company's public price list states that for hidden problems such as pipe leakage, hollowing, etc., we will first take photos and notify you with a quote. No further work will be done without confirmation. This is the company's public statement of practice. The actual price is still subject to the official quote confirmed by both parties.[8] No matter which party they approach, the homeowner should write the same "explain first, then confirm, then start work" into the communication process.
- Before the project starts, agree on who can approve changes, how to confirm them, and how to keep records.
- Every time when a problem is found during disassembly, we first require panoramic and close-up photos, location markings and the impact on the original range.
- Don’t lump waterproofing, water leakage repair, mildew removal, paint and formaldehyde removal into the same “deal”.
Example 2: the cost difference when adding a dedicated circuit to the same socket schedule
Assumptions
- This is a hypothetical example comparing differences in project quantities, and is not a case that has been completed by our company.
- Assuming that there has been an on-site assessment, the common parts of the plan are to add 4 sets of 13A unit sockets, 2 sets of 13A double/TV/network bits, and replace 1 electrical box.
- Option A adds 1 dedicated circuit and Option B adds 2. Both use published rates of HK$640, HK$1,200, HK$6,800 and HK$3,350, assuming all listed items apply and excluding unlisted work.
How to calculate quantities
- Common items: 4 × HK$640 = HK$2,560 and 2 × HK$1,200 = HK$2,400. Add the HK$6,800 distribution board for a total of HK$11,760.
- Option A: HK$11,760 + 1 × HK$3,350 = HK$15,110.
- Option B: HK$11,760 + 2 × HK$3,350 = HK$18,460.
- Difference: HK$18,460 − HK$15,110 = HK$3,350.
Under these assumptions, one extra dedicated circuit adds HK$3,350 at the published rate. Check which fixed appliance needs it, its actual rating, and whether the board and supply can support it before deciding.
The published dedicated-circuit item says increased incoming supply capacity requires separate assessment. Breakers, conductors, protection and layout need professional design and confirmation against site conditions, appliance ratings, applicable rules and tests. [8]

10
Completion acceptance: from bit by bit use to file traceability
The acceptance should be carried out by room and circuit, rather than just seeing whether the light is on after the main switch is turned on. With the original floor plan, check the sockets, switch-controlled lamp positions, TV/network positions, fixed electrical appliance positions, panel flatness, box markings and maintenance space with the cabinet one by one. Take photos of each new installation or modification; these photos are an important reference to avoid drilling into the wall in the future, but they are not a guide for DIY repairs.
Also confirm arrangements for inspection, testing and documentation of affected fixed electrical installations. The Electrical and Mechanical Services Department's guidelines require contractors to retain relevant test records, plans and documents for at least five years, and to issue a copy of the test/inspection results records to the owner.[2] Therefore, homeowners can request copies of applicable test records, circuit tables, main material models, photos of hidden wiring, and WR1/WR1(A) arrangements instead of just receiving a receipt.
If the project documents have not yet been submitted, the circuits are not marked, or a certain location does not match the drawings, a written list should be made before the final payment or handover confirmation, indicating the person in charge and the completion date. This is general project management advice and is not a conclusion on contractual rights or legal responsibilities. If there is any dispute, independent professional advice should be sought based on the signed documents and needs.
- Try it room by room and check it on the floor plan. Do not open the electrical box or remove the panel for inspection.
- Check that the electrical box label and circuit table are consistent with the actual control location.
- Put the formal quotation, supplementary quotation, test records, supporting documents and completion photos in the same cloud folder.
11
When not to wait: Separate safety issues from renovation decisions
If there is a burning smell, smoke, electric shock, power abnormality after being soaked in water, the socket or switch surface is obviously hot, repeatedly jumps, or is exposed to damage, the priority is to stop using the suspicious device and seek help from a qualified person, rather than waiting for the renovation period to deal with it all. Do not replace faulty inspections by replacing beautiful panels, adding extension boards or repeatedly resetting them.
If the problem is related to the structure, kitchen refractory components, exterior walls, aluminum windows, drainage or shared locations, they should also be diverted to the appropriate professionals. A statement from the Buildings Department pointed out that even if general home renovation is an exempted project, it must still comply with fire protection, structural and drainage standards.[4] Electrical engineering and these issues will interact with each other, but no one can make conclusions for another professional field without verification.
Start with safety checks and arrest any damage. Confirm the scope, drawings and restrictions before concealing services, laying tiles or making cabinets. Collect the documents at handover. This sequence keeps defects visible while they can still be addressed.
- Stop using suspicious devices when encountering obvious abnormalities, and do not unbox, change cables, or bypass protective devices by yourself.
- Write down photos of the power failure, the time of occurrence and equipment used at the same time for interpretation by the inspector.
- Separate your budget for emergency safety treatments from aesthetic upgrades to avoid skipping inspections to rush work.
FAQ
6 practical questions answered
01Generally, if one or two new sockets are added to a house, does it have to be rewired throughout the house?
uncertain. The judgment depends on the existing line condition, grounding, loop and protection arrangements, the load of the new equipment, the wiring in the wall and whether it can be traced. It is first checked by the registered person, and then the parts that can be used, changed and tested are written into the scope. If you just look at the number of sockets or the age of the old building and conclude that the whole house must or must not be resurfaced, it is not enough to replace an on-site assessment.
02Can I specify "all use a certain ampere rating" or directly specify a certain RCBO model?
You can express your preferences, request complete models, and request product information, but you should not apply a product rating to all circuits. Taking Schneider A9D11832 as an example, the product page lists 32A, 30mA, Type A and 10,000A, which are only specifications for this model.[5] The actual selection must be consistent with the electrical information, circuit, existing power supply conditions, applicable regulations and test results, and shall be confirmed by the person in charge.
03Is it ok to just place the bathroom socket further away from the faucet?
You can’t just rely on visual inspection. The Electrical and Mechanical Services Department stipulates that bathroom sockets should be at least 0.6 meters away from bathtubs and shower tubs. Socket circuits must be protected by current leakage circuit breakers. The switches for lights, exhaust fans and electric water heaters in the bathroom should be outside the bathroom.[3] The final location must still be checked by the registered person based on the actual bathroom size, wet area, cabinets and equipment; do not move or change the wiring by yourself.
04Do I have to pay WR1 every time I renovate? How should I ask without being vague?
For completions, repairs, modifications or additions related to fixed electrical installations, official guidelines require that the affected parts be inspected, tested and issued a designated certificate by a registered electrical worker before being energized for use; WR1 or WR1(A) is used depending on the work situation.[2] You can ask directly on the quotation: Which parts of this project are fixed electrical installations? Checked and signed by who? Which documents and test records will be delivered? Don’t just accept the vague answer of “documented.”
05Can a budget calculated online for 500 sq ft serve as an all-inclusive price for the flat or its plumbing and electrical work?
No. The quick whole-flat estimate excludes complete kitchen and bathroom reconstruction, plumbing and wiring replacement, furniture and tile finishes. Saleable area × 3 is an initial paint-area estimate. The 20% is an owner's contingency.[7] Online results are suitable for sorting out issues and scope, with formal amounts to be confirmed by on-site measurements, procedures, materials and written quotations.
06Besides receipts, what else should you take with you when you’re finished?
At least keep the final itemized quotation and supplementary quotation, electrical box information marked by circuit, a copy of the test record of the affected part, applicable WR1/WR1(A) arrangement, main material models and hidden wiring photos. Official guidelines require contractors to retain relevant test records, plans and documents for at least five years and to issue copies of test and inspection results records to owners.[2] Give these documents to the new person in charge before making any future changes.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]Registered Electrical Contractor | Electrical and Mechanical Services Department Accessed: 2026-10-21
- [2]Instructions for Registered Electrical Contractors | Electrical and Mechanical Services Department Accessed: 2026-10-21
- [3]General Installation Instructions | Household Electrical Safety Manual | Electrical and Mechanical Services Department Accessed: 2026-10-21
- [4]Alteration and addition works to domestic premises | Buildings Department FAQs Accessed: 2026-10-21
- [5]Acti9 iC60H RCBO A9D11832 product information | Schneider Electric Hong Kong Accessed: 2026-10-21
- [6]Code of Practice for Electricity (Wiring) Regulations | Electrical and Mechanical Services Department Accessed: 2026-10-21
- [7]HK Create Design Quick Estimate 2026 Company Price List Accessed: 2026-10-21
- [8]HK Create Design 2026 Renovation Project Price List Accessed: 2026-10-21
- [9]Safety information | Electrical and Mechanical Services Department Accessed: 2026-11-02
Photos from our projects
Tai Kok Tsui · Plumbing and electrical project photograph
Photograph of wall chasing and conduit installation. It does not document completed electrical testing or acceptance.