01

How the scope affects a rewiring schedule

Clients often ask, “whole-home rewiringtake?” A single figure rarely captures the job. Rewiring can involve the board, circuits, switches, outlets, concealed conduits and finishes. The scope determines the programme.

In our team's experience, adding one or more outlets generally takes up to one day. ADistribution board replacementwith local wiring alterations generally takes one to two days. A full rewire needs to be coordinated with chasing, plastering, painting and the overall renovation schedule.

An H01 electrical inspection helps establish the scope and programme. It costs HK$770 per visit, or HK$1,650 for a comprehensive inspection of multiple circuits or an open kitchen. The findings show which wiring can stay and how much needs replacing.[1]

Start by distinguishing a full rewire, partial replacement and extra outlets. Give contractors the same list of circuits and electrical points to get comparable prices and schedules. For a budget, seeRewiring pricesCheck each item in the programme. The date cables are installed can be well before plastering, painting and final handover.

  • Establish whether you need local work or a full rewire
  • Start with an H01 inspection
  • Coordinate electrical work with the other trades
Indicative timings for different scopes of electrical work

You can swipe left or right on your phone to view the complete table.

Project scopeMain itemsIndicative programmeCan you stay in the flat?
Add one or more socket outletsH02 / H03 wall chasing, pulling cable and making good plasterUsually within one dayYes, with only the affected circuit isolated
Distribution board replacementH09 replacement of a fuse box with MCB and RCD protection and labelled circuitsAbout one to two days including local rewiring.Yes, but the whole flat loses power during a board change
Add a dedicated circuitH06 dedicated circuit for an induction hob, oven or water heaterDepends on the cable route and amount of chasingYes, with work in stages
whole-home rewiringReplace the board and rewire circuits, light switches and sockets.Coordinate chasing, plastering and painting with the overall renovationBest avoided because of power cuts, dust and noise
An increase in incoming supply capacity is requiredApply to the electricity supplier for a change of loadAllow time for CLP's application processDepends on the scope above

Timings reflect HK Create Design's experience. The written quotation confirms the actual schedule. See CLP for the electricity supplier's process. [1][6] [1][6]

02

What happens at each of the seven stages?

Start with an electrical inspection covering the circuits, earth leakage and distribution board. Then mark out sockets, switches and dedicated circuits room by room. Confirm furniture and large appliance positions now to avoid cutting new chases later.

The third stage covers management registration and, if extra supply capacity is needed, an application to the electricity supplier. Fourth comes safe isolation. The Labour Department calls for a qualified registered electrical worker and a supply that is switched off, locked out and marked with a warning notice.[4]

The fifth stage covers chasing, fitting conduits and pulling cable. Concealed wiring needs protection, and power cables are routed separately from telephone, television and data cables.[7] The sixth stage is board replacement and connection. Circuits must be labelled by use and socket outlet circuits must have RCD protection.[7]

The seventh stage is testing and issuing the WR1 and making good. EMSD requires a registered electrical worker to inspect and test the completed installation before energising it. The work completion certificate is Form WR1.[2] After testing, make good and paint the chases. Check each point at handover.

  • Agree point locations before work starts
  • Before work, isolate the supply, lock it out and display a warning notice
  • Photograph cable routes before the chases are filled
  • Test before energisation and issue WR1.
Electrical conduits being relaid in the floor at Dandenong Mansion, Wan Chai
Site photo of concealed electrical conduits laid out in the floor. This work takes place early, before the floor is laid. Select an image to enlarge

03

What is most likely to extend the programme?

First, consider the wall finish. Chases in a painted plaster wall are relatively quick to make good. A tiled wall needs replacement tiles and a tiler, so coordinate with retiling where possible. Second, standalone rewiring may require an extra painting visit.

Third, consider the incoming supply. A CLP change-of-load application requires a rising mains agreement from the building management office or rising mains owner. CLP processes the application after receiving the agreement.[6] If management needs time to issue the agreement, the flat may still be waiting for power after the internal work finishes.

Fourth, moving outlets after chasing means fresh cutting and repairs. Fifth, an occupied flat adds time for working by area and clearing up daily. Sixth, management restrictions on noisy work can reduce how much chasing can be done in a day.

  • Coordinate tiled areas with the tiler
  • Apply for a load increase early
  • Confirm the layout before starting
  • Check permitted working hours with building management
Electrical accidents investigated by EMSD(Unit: cases)
2024 (actual)
595
2025 (actual)
590
2026 (estimate)
590

2026–27 Estimates, Head 42, EMSD performance indicators. These figures cover all types of electrical accidents and do not measure the risk in an individual flat. [8] [8]

「For a 400–500 sq ft flat, a full rewire generally takes one to two weeks, including cutting chases, pulling cable, making good plaster and testing.」

HK Create Design electrical works supervisor

04

Can you stay during the work?

Yes, for local work. We can work area by area and restore some circuits before leaving so you have lighting and refrigeration at night. Wall chasing creates dust and noise, and there will be power cuts during the day.

It is usually possible to stay during local socket or board work. A board replacement cuts power to the whole flat for a time, so plan for refrigerated food and internet equipment. A full rewire is easier in an empty flat because moving and protecting furniture and cleaning each day can prolong the work.

The best time is before moving in or during a full renovation. Open walls, ceilings and floors allow chasing and making good to be coordinated with other trades and spare your household the daily dust and outages.

  • You can stay during local work
  • Plan for refrigeration and internet before the board change
  • Schedule a full rewire before moving in where possible
Worked example 1

Example 1 — scheduling a supply capacity increase

Assumptions

  • Change-of-load application submitted to CLP on 9 November 2026
  • Rising mains agreement from building management

How to calculate quantities

  1. CLP says postal confirmation takes about one week. For a 9 November application, this would be around 16 November. [6]
  2. The agreement is due within one month of applying, around 9 December in this example. [6]
  3. In this example, speak to management in early November so the agreement is ready in time.
  4. Internal rewiring can proceed in parallel, but the electricity supplier schedules the final connection at the increased capacity.

In this example, submit the agreement by around 9 December. If renovation is due for completion in mid-December, arrange the paperwork early so you are not left waiting for the upgraded supply.

Actual CLP processing times vary. This example uses the timings published on its website. [6]

Use your square footage instead and see a reference budget
New electricity meter box and main switch in a Tai Wai village house
Site photo: New electricity meter box and main switch installed in a village house in Tung Lo Wan Village, Tai Wai, July 2026. HK Create Design. Select an image to enlarge

05

Where rewiring fits into a full renovation

In a full renovation, concealed electrical work must be completed before walls, ceilings and floors are closed. Strip-out is followed by plumbing and electrical chases, conduits and cables, then tiling and waterproofing, ceilings, joinery and painting. Light fittings and switch and socket faceplates go on last.

Plan electrical points with the design before work begins. Discovering a missing point after painting means opening the wall again and redoing part of the finish.

The completed electrical work is inspected, tested and certified before the installation is energised.[2] Once the faceplates and lights are in, check each point at handover and confirm that the circuits and quantities match the quotation.

  • Schedule concealed wiring early
  • Finish pulling the cables before closing the walls
  • Fit the faceplates last
Seven stages of a full rewire

You can swipe left or right on your phone to view the complete table.

SequenceApplication stageWhat is it for?What to check
1Electrical inspectionH01 inspection of circuits, earth leakage and the distribution boardDecide which circuits can stay and which need rewiring
2Mark out electrical points and prepare the quotationList sockets, light switches and circuits room by roomConfirm the furniture layout and appliance list first
3ProcedureRegister with management and apply for extra supply capacity if neededRising mains agreement due within one month
4Isolate the electrical supply.Switch off, lock out and display a warning notice.The Labour Department's safety guidance calls for
5Cut chases, fit conduits and draw in cablesConduits concealed in walls with cables drawn through themTake photos of the cable routes before closing the chases
6Distribution board replacement and connectionsInstall MCB and RCD protection and label the circuitsRCD protection for socket outlet circuits
7Testing, WR1 and making goodInspect and test before energising, issue the WR1, then make good and paintKeep the original WR1

Typical sequence. See the Labour Department and EMSD guidance for electrical safety requirements. [4][2][7] [4][2][7]

Rewiring and new conduits at Royal Peninsula, Hung Hom | HK Create Design
Site photo: Electrical work at Royal Peninsula, Hung Hom, July 2026. HK Create Design. Select an image to enlarge

06

Planning a supply upgrade to avoid waiting for power

An induction hob, oven, tumble dryer, electric water heater and several air conditioners may exceed the existing supply capacity. CLP asks applicants to consult a registered electrical contractor and specify the required load.[6]

CLP says the confirmation letter should arrive by post in about one week. Submit the rising mains owner's agreement within one month of the application.[6] Establish whether a capacity increase is needed at the design stage and discuss the agreement with building management.

The H06 dedicated-circuit rate excludes work and procedures to increase the incoming supply capacity. That scope needs a separate assessment.[1] Have a registered electrical contractor calculate the load before deciding whether to apply. This helps spot inadequate capacity before work finishes.

  • List high-load appliances to calculate demand
  • Determine capacity requirements at the design stage
  • Submit the rising mains agreement within one month
Wall chases for electrical conduits at a flat in Tai Kok Tsui
Site photo of channels cut for concealed conduits during rewiring. The cable routes are photographed before the channels are filled. Select an image to enlarge

07

Rewiring times in older buildings, newer flats and public rental housing

Flats in older buildings often havewall renderingthicker walls and may have surface wiring, old metal trunking or connections added over the years. Allow extra time for strip-out and assessment. An original fuse box often needs replacing and the circuits may need rearranging. Coordinate this work withOlder flat renovationtogether so that wall chasing, making good and painting can be done in one visit.

In a newer flat, the electrician may be able to pull new cables through existing concealed conduits, reducing chasing and shortening the job. Moving kitchen appliances or adding network points to a study may require extra circuits and outlets, so allow time for each new position.

Electrical alterations in public rental housing can require prior approval. Allow time before work starts. We can submit an application and prepare plumbing and electrical drawings. In private flats and Home Ownership Scheme flats, check management rules on working hours and contractor registration because these affect daily progress.

An open kitchen or a flat with several high-load appliances needs a load calculation and a plan for dedicated circuits. Each dedicated circuit costs HK$3,350 including connection at the board. Apply for a supply upgrade if the resulting demand exceeds the approved load.[1][6]

  • Older buildings — allow time for strip-out and sorting existing wiring
  • Newer flats — existing concealed conduits may be reusable
  • Public rental housing — allow time for prior approval
  • Many high-load appliances — check demand at the same time
Worked example 2

Example 2 — budgeting to repaint after chasing

Assumptions

  • Rewiring separately from whole-flat painting
  • In one example chasing affects 180 sq ft of wall. The alternative assumes 400 sq ft.

How to calculate quantities

  1. E02 making good, applying a moisture-resistant treatment, sanding and painting — HK$21 per sq ft, minimum HK$4,650. [1]
  2. 180 sq ft × HK$21 = HK$3,780. The HK$4,650 minimum charge applies.
  3. 400 sq ft × HK$21 = HK$8,400. This exceeds the minimum charge, so the total is HK$8,400.

Painting after a standalone rewire costs around HK$4,650–HK$8,400 in these examples. Doing it with whole-flat painting avoids another visit.

Areas are illustrative. Repairs to tiled walls are priced separately. [1]

Use your square footage instead and see a reference budget
Renovation work in progress on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge

08

How the end of the Code transition in 2026 affects scheduling

EMSD published the 2025 Code of Practice for the Electricity (Wiring) Regulations with a one-year transition. Installations complying with the 2020 edition qualify if completed and connected by 31 December 2026. Beyond that deadline, new work follows the 2025 edition and any specific transition provisions.[5]

If work will be completed in 2027, check which edition of the code applies. From 1 January 2029, residential socket-outlet circuits require AFDDs in new installations or alterations involving a distribution board. Consider reserving space when replacing the board.[11]

We use cable brands with product certification such as CCC, follow EMSD's Code of Practice for the Electricity (Wiring) Regulations and provide a WR1 on completion. If work crosses the transition date, we explain which edition applies and how it affects the board design.

  • Check which Code applies if the work spans the year end
  • Ask about AFDD provision when replacing the board
  • Collect the WR1 on completion
What affects the schedule and how to reduce delays

You can swipe left or right on your phone to view the complete table.

FactorsHow this adds timeHow to address it
Wall materialChasing a tiled wall requires replacement tiles and a tiler's visitAlongside tile replacement
Concurrent worksA separate job needs a separate painting visitCoordinate with the full renovation
Increase the approved loadAllow time for the electricity supplierArrange the application and rising mains agreement at the outset
Outlet positions still undecidedMoving points during the works means cutting new chasesConfirm furniture and appliance positions before work starts
Living in the flatWork by area and restore the flat at the end of each dayPreferably before moving in
Building management requirementsRestricted working hoursCheck building renovation rules before work begins

See CLP's website for the change-of-load procedure. [6] [6]

09

Official guidance on safety steps that apply even on a tight schedule

EMSD's Household Electrical Safety Handbook requires a registered electrical contractor to arrange new installations, additions and alterations. A registered electrical worker inspects and tests the work before energising it. The contractor and worker certify it on Form WR1. Keep the form for your records. Routine submission of the WR1 to EMSD is unnecessary.[2][3]

EMSD's Electricity News reminds owners that the Electricity Ordinance requires a registered electrical contractor for work on fixed installations. You can ask workers to show their registration certificates.[10] Hong Kong registered electrical workers have grades A, B, C, H and R. Each registration covers a different scope of work.[9]

The Labour Department calls for safe isolation of the electrical supply during electrical work, including switching off, locking out and displaying a warning notice.[4] The 2026–27 Estimates record 595 electrical accidents investigated by EMSD in 2024, with a revised estimate of 590 for 2025.[8] These safety steps take a relatively small part of the programme. A quotation that promises to omit them to save time warrants checking.

  • Hire a registered electrical contractor
  • Ask to see the registration certificate.
  • Inspection and testing before energising
  • Isolate, lock out and tag the supply.
Worked example 3

Example 3 — one visit or two?

Assumptions

  • Add three 13A outlets during the full renovation
  • Alternative — add the same three outlets after moving in

How to calculate quantities

  1. During the renovation, 3 × HK$640 = HK$1,920, included in the overall job. [1]
  2. After moving in, the HK$1,920 subtotal falls below the HK$2,000 minimum job charge, so HK$2,000 applies. A separate day's work and clean-up are also needed. [1]
  3. The difference is HK$2,000 − HK$1,920 = HK$80, plus a separate power cut, more wall chasing and another clean-up.

The price difference is small, but doing the work together avoids another visit, another power cut and another clean-up.

Repainting the wall chases after move-in is charged separately under E02. [1]

Use your square footage instead and see a reference budget

10

Common problems with promised completion dates

First, a quotation may promise a three-day rewire without saying whether it includes making good and painting. The cables may be in after three days, with finishes still outstanding. Second, if the schedule overlooks the electricity supplier's process, the renovated flat may still lack the capacity to run its appliances.

Third, moving outlets after work begins means cutting new chases each time. Fourth, agree how an occupied flat will be supplied during the works. Longer power cuts can disrupt refrigeration and internet access.

Fifth, check the quotation includes testing and the WR1. Both are part of completing the electrical work.[3] Before signing, ask for the stages, exclusions and schedule in writing so the completion date has a clear basis.

  • Allow time for making good and painting
  • Allow for the electricity supplier's process
  • Mark out the electrical points before work starts
  • Record arrangements for an occupied flat
  • Specify WR1.
Wall chased for rewiring at a flat in Ho Man Tin Estate
Site photo: Wall channels for new wiring in a Ho Man Tin Estate flat, from the May 2026 plumbing and electrical project. HK Create Design. Select an image to enlarge

11

Six checks on handover day

First, check that each socket and light switch works. Second, read the circuit labels on the front of the distribution board.[7] Third, use the RCD test button to verify that it trips. Fourth, collect the original WR1 and check the address and scope of work.

Fifth, collect photos of the cable routes before the chases are closed, for future drilling or cabinet work. Sixth, check that the plaster and paint finish is even.

Our work carries a one-year warranty from completion, excluding deliberate damage. Send photos on WhatsApp if an outlet, switch plate or connection develops a problem during that period.

  • Test each point.
  • Circuit identification on the distribution board
  • RCD testing
  • Obtain WR1.
  • Obtain cable route photographs.
  • Check the finish of the repaired areas
Living in the flat during staged work or moving out temporarily

You can swipe left or right on your phone to view the complete table.

compareStay in the flat while work proceeds by areaWork before moving in or while the flat is empty
Power interruptionPower cuts during the day, with some circuits restored each eveningThe contractor can isolate power as each task requires
Dust and noiseChasing creates dust and noise and requires daily cleaningCoordinate the work and clean once at the end
DurationAllow more time for clearing up and protecting furnitureEasier to coordinate successive trades
Refrigeration and internet equipmentArrange temporary power and protectionLess disruption
suitable forLocal work only, with limited time availableFull rewire and full renovation

Based on HK Create Design's project experience. The site conditions and quotation determine the arrangements. [12]

Project photo of plumbing work at Yat Man House, Ho Man Tin Estate | HK Create Design
Project photograph: plumbing at Yat Man House, Ho Man Tin Estate, May 2026, HK Create Design Select an image to enlarge

12

Book a site survey and agree the programme

For a free quotation from the HK Create Design team, WhatsApp 5243 7747 or visit our Wong Tai Sin shop, Monday to Saturday, 10:00–18:00.

Book a visit for whole-flat rewiring or rewiring combined with other work. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. For one or two extra outlets, send photos on WhatsApp for an initial quotation. The minimum charge for small jobs is HK$2,000.[1]

The quotation sets out stages, exclusions and dates. If the supply needs upgrading, we also flag the document deadlines so you can plan your move-in date.

  • WhatsApp 5243 7747
  • Prepare the flat's floor area and appliance list.
  • Confirm the move-in date

Advice from our tradespeople

「For a 400–500 sq ft flat, a full rewire generally takes one to two weeks, including cutting chases, pulling cable, making good plaster and testing.」

HK Create Design electrical works supervisorHK Create Design project team

「Some power cuts are needed. Staying is possible but disruptive. Households with older people or young children may prefer temporary accommodation for a few days.」

HK Create Design's partner registered electrical contractorHK Create Design's partner electrical subcontractor

「We coordinate with the plasterers and painters so chases can be cut and made good in sequence without a long wait between visits.」

Project Manager, HK Create DesignHK Create Design project team

FAQ

12 practical questions answered

01How long does a full rewire take?

There is no fixed duration for a full rewire. Coordinate chasing, plastering and painting with the full renovation. Adding sockets usually takes up to one day. A board replacement with local rewiring takes around one to two days.

02How long is the power cut during a board replacement?

Expect a power cut throughout the flat during the change. A board replacement with local rewiring generally takes one to two days. We aim to restore circuits by the end of the day where possible. H09 costs HK$6,800 per board.[1]

03Can I stay in the flat during rewiring?

For local work, the contractor can work in stages and restore some circuits each day. A full rewire brings repeated outages, dust and noise and is easier before moving in or during a full renovation.

04How long does it take to increase supply capacity?

CLP says to expect confirmation by post in about a week and to submit the rising mains agreement within one month of applying. CLP processes the application after receiving that agreement.[6]

05At what stage of a renovation should rewiring take place?

After strip-out and before the walls and ceiling are closed. The cables are concealed. Faceplates and lights go on last.

06Can the cables go in now and the painting wait?

Yes. The chases must be made good first. A separate E02 painting visit is HK$21 per sq ft, minimum HK$4,650.[1]

07When is the WR1 issued?

After completion and before energising, a registered electrical worker inspects and tests the work. The contractor and worker certify it on the WR1, which the owner should keep.[2]

08What if the work finishes in 2027?

Installations complying with the 2020 Code must be completed and connected by 31 December 2026 to qualify under the transition. For a job crossing year end, check which edition the design and quotation follow.[5]

09How can I shorten a rewiring project?

Agree point locations before work begins, coordinate with the full renovation and tiling, and apply early for any supply capacity increase.

10Which cable brands are used?

Our standard wiring commonly uses Hilly and ei8ht. Higher-specification options include Prysmian and Nexans, with Belden available for network cables and Schneider for switches and sockets. We use cable brands with product certification such as 3C, install them in line with the Electrical and Mechanical Services Department's Code of Practice for the Electricity (Wiring) Regulations, and issue form WR1 on completion.

11Is there a warranty after completion?

HK Create Design provides a one-year warranty after completion, excluding deliberate damage.

12How can I make an appointment?

On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. WhatsApp 5243 7747.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]HK Create Design 2026 published rates: electrical work H01–H09 Accessed: 2026-11-03
  2. [2]Electrical and Mechanical Services Department: Household Electrical Safety Handbook, new installations, additions and alterations Accessed: 2026-11-03
  3. [3]Electrical and Mechanical Services Department: new electrical installations, additions and alterations Accessed: 2026-11-03
  4. [4]Labour Department: safety tips for owners and tenants on renovation, maintenance, alteration and addition works Accessed: 2026-11-03
  5. [5]EMSD: Code of Practice for the Electricity (Wiring) Regulations, 2020 and 2025 editions Accessed: 2026-11-03
  6. [6]CLP Power: changing the approved loading for residential customers Accessed: 2026-11-03
  7. [7]EMSD Household Electrical Safety Handbook: general tips for electrical installations Accessed: 2026-11-03
  8. [8]Hong Kong SAR Government, 2026–27 Estimates, Head 42, Electrical and Mechanical Services Department (electrical incident and periodic test certificate indicators) Accessed: 2026-11-03
  9. [9]Electrical and Mechanical Services Department: registration as an electrical worker Accessed: 2026-11-03
  10. [10]Electrical and Mechanical Services Department: Electricity News, issue 38 (October 2025) Accessed: 2026-11-03
  11. [11]EMSD: summary of revisions to the Code of Practice for the Electricity (Wiring) Regulations, 2025 edition Accessed: 2026-11-03
  12. [12]HK Create Design rewiring service — stages and timings Accessed: 2026-11-03

Photos from our projects

Tai Kok Tsui · Plumbing and electrical project photograph

Wall chasing and conduit installation
Wall chasing and conduit installation

Photograph of wall chasing and conduit installation. It does not document completed electrical testing or acceptance.