01
How are rewiring costs calculated?
Many homeowners ask, “whole-home rewiringcost?” A 400 sq ft flat might need eight socket outlets or 15. Some use gas for cooking while others have an induction hob and oven. Boards, circuits, sockets and switches vary, so we price each at its published unit rate.[1]
Common items include H01 electrical inspection at HK$770 per visit, or HK$1,650 for a comprehensive multi-circuit inspection, and H09 replacement of theDistribution board replacement (HK$6,800), H06 new dedicated circuit (HK$3,350 per circuit), H04 replacement switch and wiring (HK$430 each), H02 new 13 A socket (HK$640 per point), and H03 double socket, TV or data point (HK$1,200 each). H05 pendant or ceiling light installation is HK$670 each, H07 LED strip HK$150 per linear foot and H08 spotlights HK$310 each.[1]
Multiply the quantity needed at home by each unit price, then add the results. Three worked examples follow. You can also adjust the quantities in the website calculator.
- List all sockets, light switches and major appliances in the flat.
- Check whether the existing board is still a fuse box.
- Ask for the quantity and rate for each quotation item.
You can swipe left or right on your phone to view the complete table.
| No. | Item | Company rate | Already included | Excluded or separately charged |
|---|---|---|---|---|
| H01 | Electrical inspection | HK$770 per inspection, or HK$1,650 for a comprehensive multi-circuit inspection. | Trip switch, leakage and circuit inspection, preliminary report | Circuits identified for repair or replacement after inspection |
| H09 | Replace the distribution board | HK$6,800 per unit | Convert a fuse box to an MCB/RCD board and label the circuits. | AFDDs and incoming supply upgrades |
| H06 | Add a dedicated circuit | HK$3,350 per circuit | Dedicated circuit with connection at the distribution board | Apply to the electricity supplier for increased capacity and associated works. |
| H04 | Replace a light switch and its wiring | HK$430 per unit | Remove the old switch, install the new one and connect the wiring. | Light fittings themselves |
| H02 | New 13 A socket with concealed conduit | HK$640 per set | Chasing, wiring, back box, faceplate and filling the chase | Chasing tiled walls and repairing tiles |
| H03 | Double socket, TV or data point | HK$1,200 per set | Chasing, wiring, back box, faceplate and filling the chase | Networking equipment and router |
| H05/H07/H08 | Light fitting installation | Pendant lights HK$670 each, LED strip HK$150 per linear foot and spotlights HK$310 each | Installation and wiring (H07 and H08 also include supply) | The client supplies the pendant light fitting. Complex ceilings are priced separately. |
Source: our published rates. Repainting chases can be priced under E02 filling and repainting. [1] [1]
02
Running new cables or replacing the existing ones: agree the quotation scope first.
A quote for “whole-flat wiring” may cover new dedicated circuits, partial replacement or full rewiring. Confirm whether existing concealed wiring, board, lighting points and wall repairs are included. Have a registered electrical contractor assess the installation and list items to keep or replace in the quote.[2]
List sockets, switches and data points room by room. Separate the board, dedicated circuits, chasing, filling, repainting and tile repairs. Our three examples use different quantities. Even two 400 sq ft flats can have different scopes.[1]
Alongside the budget, agree whether the flat will be occupied, acceptable power interruptions and how work fits with other trades. Read more aboutRewiring schedule and power interruptions, then give contractors the same scope for comparison.
- State whether each circuit is retained, rewired or added.
- Check socket, switch and data point counts in each room.
- Specify chasing and filling, repainting and tile repairs separately.
- State occupancy, power interruption and move-in constraints upfront.
03
Why consider a wiring inspection or replacement in 2026?
Fire Services Department figures attribute 739 fires in 2020, 827 in 2021, 846 in 2022, 1,000 in 2023 and 1,014 in 2024 to electrical faults.[8] In its 2025 year-end review, the Fire Services Department reported 2,000 building fires causing damage. Electrical faults and human factors accounted for approximately 42% and 25% respectively.[9]
These figures cover different types of fire and cannot diagnose one home. Simultaneous use of induction hobs, ovens, dryers, air conditioning and water heaters can place more demand on older wiring and boards than originally envisaged. Rewiring can match cable sizes and protection to current use.
If you are planningWhole-flat renovation, the walls and ceilings will already be opened, making this a practical time to rewire. Waiting until after moving in means reopening chases, repainting and a further round of cost and disruption.
- More major appliances mean the load should be recalculated.
- Coordinate rewiring with the whole-flat renovation.
- If unsure, start with an H01 inspection.
「When comparing whole-flat rewiring quotes, check circuit and socket counts, board replacement and WR1. A lower total may cover less work.」

04
Step 1: H01 electrical inspection to establish what needs replacing
Not every flat needs full rewiring. An MCB/RCD board and concealed wiring that passes testing may only need extra sockets. An old fuse box, deteriorating insulation and unlabelled circuits may point to more extensive replacement. Arrange an inspection to check.
H01 costs HK$770 for a single visit, covering circuit, tripping and earth leakage checks and a preliminary report. A comprehensive multi-circuit or open-kitchen inspection costs HK$1,650.[1] An inspection identifies wiring that can remain and circuits that need replacement, providing a measured basis for the quotation.
Before adding to or altering an installation, EMSD recommends a feasibility assessment by a registered electrical contractor. Take future demand into account when deciding whether to apply to the electricity supplier for increased approved loading.[2] An inspection is the starting point for avoiding unnecessary or insufficient work.
- For an isolated issue such as one room's circuit tripping, start with H01 at HK$770.
- HK$1,650 comprehensive inspection for a whole flat or open kitchen
- After inspection, ask for a list of circuits that can remain and those to rewire.
Example 1: rewiring an older 400 sq ft one-bedroom flat
Assumptions
- Original fuse box and ageing wiring. The owner chooses a whole-flat replacement.
- The water heater and induction hob each require a dedicated circuit in this example.
- Six light switches, eight 13 A sockets and two double socket or TV points throughout the flat.
- Painted, rendered walls. No chases in tiled walls. [1]
How to calculate quantities
- H01 comprehensive electrical inspection: HK$1,650.
- H09 distribution board replacement: 1 × HK$6,800 = HK$6,800.
- H06 dedicated circuits: 2 × HK$3,350 = HK$6,700.
- H04 light switches and wiring: 6 × HK$430 = HK$2,580.
- H02 13 A sockets: 8 × HK$640 = HK$5,120.
- H03 double sockets or TV points: 2 × HK$1,200 = HK$2,400.
- Total: 1,650 + 6,800 + 6,700 + 2,580 + 5,120 + 2,400 = HK$25,250.
Under these assumptions, rewiring is about HK$25,250, excluding light fittings, repainting chases and an incoming supply upgrade. [1]
Quantities are illustrative. The actual circuit and point counts depend on a site survey and written quote. [1]
05
Distribution board and dedicated circuits: the two largest budget items
H09 distribution board replacement costs HK$6,800, including conversion of an old fuse box to an MCB/RCD board and labelling each circuit.[1] EMSD's general installation guidance requires each circuit's purpose to be labelled at the distribution board and socket circuits to be protected by a residual current device (RCD).[4]
H06 new dedicated circuits are HK$3,350 each for major appliances such as water heaters, induction hobs and ovens, including connection at the distribution board.[1] EMSD recommends that each high-power appliance have its own socket.[4] An induction hob, oven and electric bathroom water heater might require three separate circuits: 3 × HK$3,350 = HK$10,050 in this example.
If new appliances will exceed the flat's approved loading, apply to the electricity supplier for a change. CLP requires consent from building management or the owner of the rising mains, consultation with a registered electrical contractor and details of the required loading.[7] These procedures and works fall outside the H06 rate and require separate assessment.[1]
- List all major appliances and their power ratings.
- Confirm whether an incoming supply upgrade is needed.
- Label the purpose of each circuit at the board.
You can swipe left or right on your phone to view the complete table.
| Plan | Suitable for the situation | Main items | Worked examples in this article |
|---|---|---|---|
| Board replacement plus local additions only | Concealed wiring passes testing, but the flat has an old fuse box or too few sockets. | H01 + H09 + a few H02 outlets | About HK$9,730 |
| Rewiring a one-bedroom flat | Older flat of about 400 sq ft with ageing original wiring | H01 + H09 + 2 H06 circuits + 6 H04 switches + 8 H02 outlets + 2 H03 points | About HK$25,250 |
| Three-bedroom flat rewiring with lighting points | About 700 sq ft, alongside a whole-flat renovation | H01 + H09 + 3 H06 circuits + 12 H04 switches + 14 H02 outlets + 5 H03 points + 12 H08 spotlights | About HK$42,340 |
Quantities are illustrative. Count actual items on site. [1] [1]
06
Sockets, switches and data points: compare quantities
H02 concealed-conduit 13 A single sockets are HK$640 per point. H03 double sockets, TV or data points are HK$1,200 each. Both include chasing, wiring, back box, faceplate and filling. H04 is HK$430 per switch with wiring, including removal, replacement and connection.[1]
Count points and agree heights room by room, including bedsides, desk, TV wall, kitchen worktop, fridge and washing machine. Adequate permanent sockets reduce the need for chained extensions. EMSD advises using only one adaptor or extension board per socket to avoid overload.[4]
We commonly use Schneider Electric switches and sockets. We can quote a requested colour or model separately. Choose the faceplate before chasing so the back box matches.
- List socket quantities and heights for each room.
- Data and TV points are priced under H03.
- Confirm faceplate styles before chasing.

07
Cable materials: standard specification and upgrades
Agree materials before concealment. Our standard ranges commonly include Hilly and ei8ht single- and double-insulated cables, data cables and control cables. Prysmian and Nexans are upgrade options, as is Belden for data and signal cables.
We use cable brands with product certifications such as 3C and install to EMSD's Code of Practice for the Electricity (Wiring) Regulations. At completion, WR1. [5][2] Product certification applies to the cable itself. A registered electrical worker must also install, inspect and test the work in accordance with the code.
The registered electrical worker selects cable size to suit the circuit load. EMSD guidance requires suitable protection for new concealed wiring, such as conduit, and separation of power circuits from telephone and telecommunications lines.[4] H02 and H03 therefore include concealed conduit and the back box as well as cabling.
- Specify the cable brand and range in the quotation.
- Run power and data cables in separate conduits.
- Concealed wiring requires conduit protection.


08
Three examples: 400 sq ft, 700 sq ft and a partial upgrade
Example 1 is an older 400 sq ft one-bedroom flat: H01 HK$1,650, H09 HK$6,800, two H06 circuits HK$6,700, six H04 switches HK$2,580, eight H02 outlets HK$5,120 and two H03 points HK$2,400, totalling HK$25,250.[1]
Example 2 rewires a 700 sq ft three-bedroom flat during full renovation. It adds a third dedicated circuit, 12 switches, 14 sockets, five data or TV points and 12 spotlights, totalling HK$42,340.[1] Example 3 replaces only the board and adds two sockets: 1,650 + 6,800 + 1,280 = HK$9,730.[1]
The three totals differ because quantities and scope vary. Use the same schedule of quantities to compare contractors. Full calculations appear at the end of the article.
For a combined kitchen, bathroom, painting and furniture estimate, see A 400 sq ft whole-flat renovation example. That example's electrical subtotal covers only the items listed. Its outlets, circuits and inspection scope differ from this whole-flat example. The totals are for different specifications.
- Use the same quantities to compare quotes.
- Check the assumptions behind each example.
- Verify quantities on site.
Example 2: rewiring a 700 sq ft three-bedroom flat and fitting spotlights during a whole-flat renovation
Assumptions
- Whole-flat renovation with walls and ceilings refinished at the same time.
- Three dedicated circuits for the induction hob, oven and water heater.
- 12 light switches, 14 socket outlets, five double sockets/TV/data points and 12 spotlights. [1]
How to calculate quantities
- H01 comprehensive electrical inspection: HK$1,650.
- H09 distribution board replacement: HK$6,800.
- H06 dedicated circuits: 3 × HK$3,350 = HK$10,050.
- H04 light switches and wiring: 12 × HK$430 = HK$5,160.
- H02 13 A sockets: 14 × HK$640 = HK$8,960.
- H03 double sockets, TV or data points: 5 × HK$1,200 = HK$6,000.
- H08 spotlights: 12 × HK$310 = HK$3,720.
- Total: 1,650 + 6,800 + 10,050 + 5,160 + 8,960 + 6,000 + 3,720 = HK$42,340.
Under these assumptions, the reference price is HK$42,340. For whole-flat projects, L02 third-party liability and employees' compensation insurance are priced separately. [1]
Suspended ceilings, lighting coves and LED strips are separate. If total demand exceeds the approved load, apply to the electricity supplier first. [7] [1][7]
09
Exclusions: capacity upgrades, AFDDs, tiling and light fittings
First, supply capacity. Apply to the electricity supplier if the load exceeds the approved limit and obtain the rising mains owner's consent. Procedures and associated work are priced separately.[7][1]
Second, arc fault protection. Under EMSD's 2025 wiring code, from 1 January 2029 new installations and alterations involving a distribution board must provide arc fault detection devices (AFDDs) on socket-outlet circuits in residential flats.[6] Consider allowing board space for an AFDD. H09 excludes the device, which is quoted separately if required.
Third, chasing tiled walls affects the tiles, so coordinate it with replacement tiling. Filling chases in painted, rendered walls is included. Fourth, clients supply pendant and ceiling lights. H05 is installation only.[1] Fifth, repainting after chasing can be priced under E02 local filling, sanding and moisture-resistant painting at HK$21/sq ft, minimum HK$4,650.
- Ask whether any capacity upgrade is separate.
- Ask about space for an AFDD when replacing the board.
- Chasing tiled walls and replacing affected tiles require a separate quote.

10
EMSD guidance on rewiring
EMSD's Household Electrical Safety Handbook states that new installations and new or altered parts of existing installations must meet current statutory safety requirements. Following installation, addition, alteration or repair, a registered electrical worker must inspect and test before energisation.[3]
After inspection and testing, the registered electrical contractor and worker issue the EMSD Work Completion Certificate (WR1), confirming compliance with statutory safety requirements. The owner keeps it and need not send it to EMSD.[3][2] Registered electrical workers are graded A, B, C, H and R. For example, Grade A covers low-voltage fixed installations with maximum demand not exceeding 400 A.[10]
The Labour Department advises owners and tenants to engage a qualified registered electrical worker. The supply must be safely isolated, switched off, locked out and identified with a warning notice.[11] These are basic requirements for electrical works and should be covered in the agreed scope.
- A registered electrical worker inspects and tests before energisation.
- Obtain and retain WR1 at completion.
- Isolate and lock off the supply and display a warning notice during the work.
You can swipe left or right on your phone to view the complete table.
| Factors | How it affects the price | How to control it |
|---|---|---|
| Number of circuits | HK$3,350 per dedicated circuit | List major appliances first and add circuits where required. |
| Socket and switch counts | By number of sets or items | Mark out each room to avoid future additions. |
| Distribution board condition | H09 fuse box replacement required | Start with H01 inspection and decide on the work afterwards. |
| Wall material | Chases in tiled walls require tile repairs, priced separately. | Alongside tile replacement |
| Incoming supply capacity | Apply to the electricity supplier if the approved loading will be exceeded. | Arrange an initial assessment by a registered electrical contractor. |
| Concurrent works | For standalone works, price repainting after chasing separately. | Coordinating with the whole-flat renovation saves repeat work. |
For capacity upgrades, see CLP's change-of-loading application. [1][7] [1][7]
11
Five common omissions in rewiring quotations
First, “whole-flat rewiring” without quantities makes additions hard to price. Second, omitted cable brands and product ranges cannot be checked after concealment. Third, clarify how chases will be made good, including filling, repainting and who repairs tiles.
Fourth, check for WR1. The quotation should specify inspection and testing by a registered electrical worker and issue of the WR1 completion certificate.[2] Fifth, identify exclusions such as supply upgrades, AFDDs and light fittings in writing, even when the project does not require them.
If a contractor proposes connecting new wiring to the old fuse box, check the proposed protection carefully. EMSD requires residual-current protection for socket circuits and identification of each circuit at the distribution board.[4]
- Itemised quantities in the quotation
- Specify cable brands.
- Specify the extent of making good after chasing.
- Specify WR1.
- List the exclusions.
Example 3: replacing the board and adding two sockets
Assumptions
- The H01 inspection confirms that most concealed wiring is sound and can be kept.
- Convert the fuse box to MCB/RCD protection and add two socket outlets only. [1]
How to calculate quantities
- H01 comprehensive electrical inspection: HK$1,650.
- H09 distribution board replacement: HK$6,800.
- H02 13 A sockets: 2 × HK$640 = HK$1,280.
- Total: 1,650 + 6,800 + 1,280 = HK$9,730.
The example is about HK$9,730, above the HK$2,000 small-job minimum. [1]
Retained wiring must pass testing. If defects require replacement, obtain a separate quote. [1]
12
Rewiring public rental, HOS and private flats: procedures to check first
For a private flat, check the deed of mutual covenant and management rules on working hours, worker registration and drawings. A capacity increase requires the consent of building management or the rising mains owner under CLP's application process.[7]
Electrical alterations in public rental flats require prior approval. We can prepare plumbing and electrical drawings and submit the application on your behalf. Check management rules for HOS and private developments.
Regardless of flat type, a registered electrical worker must carry out and test the work and WR1 is issued on completion.[3] Confirm required applications early to avoid stopping work while waiting for approvals.
- Private flats: check building management renovation rules.
- Public housing: prior application required. We can prepare services drawings and submit it for you.
- For a capacity upgrade, obtain the rising mains consent form first.
You can swipe left or right on your phone to view the complete table.
| stage | What is it for? | Indicative time |
|---|---|---|
| 1. Inspection | H01 inspection to decide what wiring can be retained and what needs replacing | One site visit |
| 2. Mark out positions and prepare the quotation | Room-by-room quantities for sockets, switches and circuits | At the time agreed with the client |
| 3. Applications and approvals | Register with building management. Apply to the electricity supplier if a capacity increase is needed. | CLP sends an acknowledgement in about one week. Submit the rising mains consent form within one month of applying. |
| 4. Construction | Isolate the supply, chase walls, install conduit and cable, and replace the board. | Adding a socket is usually completed within a day. Board replacement with local work typically takes one to two days. Schedule whole-flat rewiring with the renovation. |
| 5. Testing and WR1 | A registered electrical worker inspects and tests before energisation and issues WR1. | At completion |
| 6. Reinstatement and handover | Fill and paint the walls and test each point. | According to reinstatement scope |
Work durations reflect our general experience. Confirm dates in the written quotation. Electricity supplier timings follow CLP's website. [7][3] [7][3]

13
Handover: what to check after rewiring
At handover, operate each socket and switch, including both sides of double switches. Check visible board labels and circuit counts against the quote, test that the RCD trips using its test button, and obtain the original WR1 showing the correct address and scope.
Fifth, ask for cable route photos before chases are filled. We photograph concealed conduit routes for future reference when hanging pictures or fitting cupboards. Sixth, check the filled chases are level and free of obvious cracks.
Our works have a one-year warranty after completion, excluding deliberate damage. If a socket, switch plate or connection develops a problem during this period, send photos on WhatsApp for follow-up.
- Test each socket and light switch.
- Circuits labelled at the board
- RCD trips when the test button is pressed.
- Obtain the original WR1.
- Obtain cable route photographs.

14
How can I reduce rewiring costs while maintaining safety?
Coordinate rewiring with whole-flat renovation while walls and floors are open. Chasing and reinstatement can then be combined with painting and masonry. Rewiring later may mean reopening and repainting walls. Test concealed wiring first so sound circuits can be retained.
Third, plan all points together. Returning later to add two sockets can cost more because of the HK$2,000 small-job minimum.[1] Fourth, retain the specified safety standard for cables, distribution boards and protection. Savings are easier to make on finishes such as faceplates and light fittings that can be changed later.
Select the H-series items in the website calculator for an initial figure. The site measurement and written quotation establish the price.
- Alongside a whole-flat renovation
- Inspect before deciding the scope.
- Mark out all positions together.
You can swipe left or right on your phone to view the complete table.
| Check | Why | What to look for |
|---|---|---|
| Board model and circuit count | Determine protection and future expansion capacity. | Number of MCBs and RCDs, and purpose of each circuit |
| Cable brands and specifications | Difficult to replace after concealment in the wall | Select the brand and cable size appropriate to the circuit. |
| Socket and switch counts | Priced by quantity | Room-by-room quantities |
| Extent of making good after chasing | Who handles filling, repainting and tile repairs? | State whether repainting is included. |
| WR1 | Statutory completion certificate | Specify completion inspection, testing and issue of WR1 by a registered electrical worker. |
| Excluded items | Avoid extra work and charges. | List capacity upgrades, AFDDs and light fittings. |
For WR1 requirements, see EMSD's safety guidance. [2] [2]
15
Book a quotation and site measurement
For a free quotation from the HK Create Design team, WhatsApp 5243 7747 or visit our Wong Tai Sin shop, Monday to Saturday, 10:00–18:00.
Book a visit for whole-flat rewiring or rewiring combined with other work. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. For a small job such as adding one or two sockets, send photos on WhatsApp for an initial quotation. The minimum charge for small jobs is HK$2,000.[1]
We list board, circuit, socket and switch quantities, cable brands, exclusions and WR1 arrangements so you can compare quotations.
- Send photos or book on WhatsApp at 5243 7747.
- Prepare the flat's floor area and appliance list.
- Compare quotations using the same schedule of quantities.
Advice from our tradespeople
「When comparing whole-flat rewiring quotes, check circuit and socket counts, board replacement and WR1. A lower total may cover less work.」
「Each circuit requires insulation resistance and earth leakage tests. WR1 should only be signed when the tests are complete and satisfactory.」
「We number and price each electrical point, so additions and removals are easy to trace. There is a one-year warranty after completion.」
FAQ
13 practical questions answered
01Roughly how much does whole-flat rewiring cost in 2026?
There is no fixed whole-flat price. Our example is about HK$25,250 for a 400 sq ft one-bedroom flat or HK$42,340 for a 700 sq ft three-bedroom flat with spotlights. Quantities of boards, circuits, sockets and switches determine the price.[1]
02Does running new cables cover the same work as replacing all wiring?
Clarify whether the quote covers whole-flat rewiring, partial rewiring or extra circuits. Check retained wiring, the board, electrical point counts, reinstatement of chases and exclusions. A site inspection confirms the actual scope.[1][2]
03How much does it cost to replace a distribution board?
H09 board replacement is HK$6,800, including conversion from a fuse box to MCB/RCD protection and circuit labels. AFDDs and incoming supply upgrades are separate.[1]
04How much does one extra dedicated circuit cost?
H06 is HK$3,350 per dedicated circuit for appliances such as water heaters, induction hobs and ovens, including connection at the distribution board.[1]
05Does the entire flat need rewiring?
Not necessarily. Start with H01 inspection at HK$770, or HK$1,650 for multiple circuits. If concealed wiring passes testing, it may be retained while the board is replaced or extra points are added.[1]
06Does the rewiring price include painting?
H02 and H03 include filling the chase. Repainting is generally separate and may be priced under E02. Chasing and repairing tiled walls are priced separately.
07What cable brands do you use?
Our standard range commonly uses Hilly and ei8ht. Options include Prysmian and Nexans, or Belden for data cable. We select cable brands with product certifications such as 3C, install to EMSD's Code of Practice for the Electricity (Wiring) Regulations and provide WR1 at completion.
08Which documents do I receive after rewiring?
After a registered electrical worker inspects and tests the installation, the contractor and worker issue WR1. The owner keeps it and need not submit it to EMSD.[3]
09How much does a supply capacity upgrade cost?
The cost depends on electricity supplier requirements and the rising mains and is excluded from our rate. Obtain consent from the rising mains owner before applying.[7]
10Do I need an AFDD now?
From 1 January 2029, residential socket-outlet circuits require AFDDs in new installations or alterations involving a distribution board.[6] Allow space at board replacement. Obtain a separate quote.
11What is the charge for just one or two extra sockets?
H02 is HK$640 per point. Small jobs have a HK$2,000 minimum, so adding one or two points alone is charged at HK$2,000.[1]
12Is rewiring covered by a warranty?
HK Create Design provides a one-year warranty after completion, excluding deliberate damage. Send photos via WhatsApp at 5243 7747 for follow-up.
13How do I start a quotation?
On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. For small jobs, send photos on WhatsApp for an initial quotation.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]HK Create Design 2026 published rates: electrical work H01–H09 Accessed: 2026-11-03
- [2]Electrical and Mechanical Services Department: new electrical installations, additions and alterations Accessed: 2026-11-03
- [3]Electrical and Mechanical Services Department: Household Electrical Safety Handbook, new installations, additions and alterations Accessed: 2026-11-03
- [4]EMSD Household Electrical Safety Handbook: general tips for electrical installations Accessed: 2026-11-03
- [5]EMSD: Code of Practice for the Electricity (Wiring) Regulations, 2020 and 2025 editions Accessed: 2026-11-03
- [6]EMSD: summary of revisions to the Code of Practice for the Electricity (Wiring) Regulations, 2025 edition Accessed: 2026-11-03
- [7]CLP Power: changing the approved loading for residential customers Accessed: 2026-11-03
- [8]Fire Services Department statistics: fire causes, 2020–2024 Accessed: 2026-11-03
- [9]Government press release: Fire Services Department review of its work in 2025 Accessed: 2026-11-03
- [10]Electrical and Mechanical Services Department: registration as an electrical worker Accessed: 2026-11-03
- [11]Labour Department: safety tips for owners and tenants on renovation, maintenance, alteration and addition works Accessed: 2026-11-03