Assumptions for the illustrative flat
This example uses a hypothetical but typical 400 sq ft flat with two bedrooms, a living room, a 7 ft kitchen run and a roughly 35 sq ft bathroom. The building is about 30 years old. The kitchen and bathroom tiles and pipes are 20 to 30 years old, there is an old fuse box, local wall cracking and original floor tiles.
The brief is for two people. The main bedroom needs a 6 ft wardrobe and the smaller room doubles as a study and guest room, with aPlatform bedsand a 4 ft wardrobe. The living room needs a TV cabinet and the entrance needs shoe storage. The owners plan to move out for the work.
All figures in this illustrative example use HK Create Design’s published 2026 rates[1]. These figures assume no special offers or discounts. Actual wall areas, kitchen lengths and pipe conditions vary. Each section shows the calculation so you can substitute your own measurements.
We chose 400 sq ft because it is common in private estates, Home Ownership Scheme flats and some public rental homes. Adapt the scope to your own flat.
- 400 sq ft saleable area, two bedrooms and a living room
- 7 ft kitchen run and 35 sq ft bathroom
- About 30 years old, with an old distribution board
- Worked estimate for a hypothetical flat
- kitchenHK$70,400。
- BathroomHK$55,540。
- Surface finishesHK$58,200。
- furnitureHK$51,800。
- electricityHK$19,410。
- Cleaning and insuranceHK$13,100。

02
How the full renovation reaches HK$268,450
Full renovation example total, HK$268,450[1]. The six categories include full kitchen HK$70,400 (26.2%), full bathroom HK$55,540 (20.7%), finishes including painting, floor, ceiling and room doors HK$58,200 (21.7%) andBespoke furniture HK$51,800 (19.3%), electrical work HK$19,410 (7.2%) and cleaning and insurance HK$13,100 (4.9%).
The average is approximately HK$671 per sq ft. For the same 400 sq ft flat, retaining or rebuilding the kitchen and bathroom can move the price from about HK$300 to over HK$670 per sq ft. Compare individual scopes and quantities.
The Consumer Council reported that home renovation complaints from 2017 to 2023 involved more than HK$270 million[2]. An unclear scope can lead to disputes. The Consumer Council recommends stating the works, materials, quantities and unit prices[3]. Each item below shows its code, quantity and rate so you can compare it with another quotation.
- Total HK$268,450
- About HK$671 per sq ft
- Remove and replace kitchen and bathroom tiles and pipes, fit two wardrobes and a platform bed
- Compare more than the price per square foot
You can swipe left or right on your phone to view the complete table.
| Category | Main items | Amount | Share |
|---|---|---|---|
| kitchen | Strip-out, waterproofing, pipes, tiles, cabinets and quartz | HK$70,400 | 26.2% |
| Bathroom | Strip-out, waterproofing, tiles, pipes, fittings and vanity | HK$55,540 | 20.7% |
| Surface finishes | E02 painting, SPC flooring, false ceiling and room doors | HK$58,200 | 21.7% |
| Bespoke furniture | Two wardrobes, a platform bed, TV cabinet and shoe cabinet | HK$51,800 | 19.3% |
| electricity | Distribution board, sockets, circuits and spotlights | HK$19,410 | 7.2% |
| Cleaning and insurance | Formaldehyde treatment and third-party liability insurance | HK$13,100 | 4.9% |
| Total | — | HK$268,450 | 100% |
Illustration based on HK Create Design’s published 2026 rates for a hypothetical flat. [1]

03
Kitchen HK$70,400 for a full renovation with a 7 ft run
The kitchen is the largest item. The full example includes A09 kitchen strip-out and removal at HK$9,950 including haulage, C03 kitchen waterproofing at HK$4,300 and G03 replacement hot- and cold-water pipes at HK$13,300[1].
Wall tiling: about 120 sq ft × HK$78 = HK$9,360. Floor tiling: about 35 sq ft × HK$78 = HK$2,730[1]. Kitchen cabinets: FUR14 base units, 7 ft × HK$1,300 = HK$9,100. FUR15 wall units, 7 ft × HK$1,250 = HK$8,750. FUR20 quartz worktop, 7 ft × HK$1,200 = HK$8,400[1].
Add K04 cooker hood installation at HK$860 and F05 aluminium kitchen ceiling at HK$3,650[1], totalling HK$70,400.
If the kitchen tiles are sound, there is no seepage and the pipes have not corroded, replacing only the cabinets can bring the cost below HK$30,000 (see the budget option below). Check under the cabinets and sink for water marks, listen for hollow wall tiles, and check the water pressure. A hollow sound when tapping a tile gently with a coin may mean the adhesive has come away.
- Strip-out and haulage, HK$9,950
- Waterproofing and plumbing, HK$17,600
- Tiling, HK$12,090
- Kitchen cabinets and quartz worktop, HK$26,250
- $268,450Full renovationExample
- $119,520Lower-cost optionExample
- 7–9 weeksDurationFull renovation
Examples based on HK Create Design's published 2026 rates.
「For a 400 sq ft flat, deciding whether to gut the kitchen and bathroom often has the biggest impact. I would inspect the pipes before choosing. If they are corroded, replacing them now can avoid opening new tiling later.」

04
Bathroom HK$55,540 for a full renovation
The full bathroom example starts with A10 strip-out and removal at HK$9,950 and C02 Bathroom waterproofing HK$4,850 for the full floor, walls up to 6 ft, full height in the shower and a 24-hour pond test[1].
Wall and floor tiling: about 185 sq ft × HK$78 = HK$14,430. G04 bathroom hot- and cold-water pipes HK$13,300. K06 full sanitary fitting installation HK$5,650. FUR25 vanity base with seamless worktop, 2 ft × HK$3,250 = HK$6,500. K05 shower screen installation HK$860[1]. Total HK$55,540.
Allow for bathroom waterproofing and a pond test. Seepage may mean retiling and paying for repairs below. The Consumer Council recommends specifying waterproofing areas, the material, upstand height and whether water testing is included[3].
Use qualified people for plumbing work. The Water Supplies Department website provides information on licensed plumbers[9].
- Strip-out and haulage, HK$9,950
- Waterproofing and water test, HK$4,850
- Wall and floor tiling, HK$14,430
- Plumbing, HK$13,300

05
Electrical work HK$19,410 for essential safety and supply items
Many 30-year-old flats still have old fuse boxes without residual-current protection. In this example, H09 replaces theDistribution board replacement HK$6,800 to fit MCB and RCD protection and label the circuits[1].
H02 additional 13 A single sockets: 4 × HK$640 = HK$2,560. H03 twin, TV or network points: 3 × HK$1,200 = HK$3,600. H06 dedicated induction hob circuit: HK$3,350. H08 spotlights: 10 × HK$310 = HK$3,100[1]. Total HK$19,410.
The HK$19,410 electrical allowance covers only the listed distribution board, new socket points, dedicated circuit and spotlights. H01 full electrical inspection and complete rewiring of existing concealed circuits are outside this allowance. If inspection shows a need forwhole-home rewiring, count each circuit and point afresh. SeeRewiring pricesCost each item and add the required items to the overall budget.[1]
The Electrical and Mechanical Services Department states that new electrical installations, additions and alterations must be undertaken by registered electrical contractors and registered electrical workers[5]. Electrical work accounts for 7.2% of the example total, yet it underpins safety throughout the flat. Do not skip it to save a few thousand dollars. After the distribution board is replaced, circuit labels make it easier to track down the cause of a trip.
Plan sockets with the furniture layout. Both sides of the bed, desks, TV cabinets and kitchen worktops are common locations where outlets run short.
- Distribution board replacement — HK$6,800
- Additional socket points, HK$6,160
- Induction hob circuit, HK$3,350
- Work carried out by a registered electrical contractor

06
Finishes HK$58,200 for painting, floor, ceiling and room doors
Painting: about 1,200 sq ft of walls and ceilings using E02 local filling, moisture-resistant preparation, sanding and painting at HK$21 per sq ft, total HK$25,200[1]. The walls in the example are largely sound, with local cracks, so E01 stripping at HK$39 per sq ft is unnecessary.
Flooring: lay J01 SPC flooring directly over the existing tiles in about 340 sq ft of living and bedroom space. At HK$60 per sq ft including labour and materials, the total is HK$20,400. J04 skirting: 150 linear ft × HK$10 = HK$1,500[1]. Retaining the existing floor tiles saves strip-out and debris charges.
Living room ceiling: 100 sq ft of F01 metal-framed plasterboard false ceiling at HK$51 per sq ft totals HK$5,100 and provides space for spotlight wiring[1]. Room doors: replace two plywood doors under L03 at HK$3,000 each, totalling HK$6,000[1].
Finishes total HK$58,200 or 21.7%. The area involved has a major influence, and the wall preparation can be adjusted to suit the condition.
- E02 painting, HK$25,200
- SPC flooring, HK$20,400
- False ceiling, HK$5,100
- Room doors, HK$6,000
Example: full renovation of a 400 sq ft flat
Assumptions
- Full renovation of a 7 ft kitchen run and 35 sq ft bathroom
- Walls generally sound
- Existing floor tiles are level
How to calculate quantities
- Kitchen: 9,950 + 4,300 + 9,360 + 2,730 + 13,300 + 9,100 + 8,750 + 8,400 + 860 + 3,650 = HK$70,400
- Bathroom: HK$55,540
- Electrical: 6,800 + 2,560 + 3,600 + 3,350 + 3,100 = HK$19,410
- Finishes: 25,200 + 20,400 + 1,500 + 5,100 + 6,000 = HK$58,200
- Furniture: 17,400 + 11,600 + 8,840 + 7,500 + 5,800 + 660 = HK$51,800
- Cleaning and insurance: 6,400 + 6,700 = HK$13,100
- Total: HK$268,450
Illustrative total HK$268,450, about HK$671 per sq ft.
Hypothetical flat. A firm price requires a site survey and written quotation. [1]
07
Custom furniture HK$51,800 for the two bedrooms and living room
Main bedroom: FUR05 wardrobe, 6 ft × HK$2,900 = HK$17,400. Small bedroom: FUR05 wardrobe, 4 ft × HK$2,900 = HK$11,600, plus a FUR06 platform bed covering about 26 sq ft (6.5 × 4 ft) × HK$340 = HK$8,840[1].
Living room: FUR10 low TV cabinet, 6 ft × HK$1,250 = HK$7,500. Entrance: FUR12 tall shoe cabinet, 2 ft × HK$2,900 = HK$5,800. FUR42 delivery costs HK$660, with furniture and kitchen cabinets delivered together[1]. Total HK$51,800.
HK Create Design's custom furniture service includes design and full drawings for the flat: floor plans, ventilation, fire services, plumbing and electrical layouts, furniture designs, VR visualisations and production drawings. ENF-grade boards with formaldehyde emissions of ≤0.025 mg/m³ are standard, at no extra charge.
The Environmental Protection Department notes that new furniture and finishes can emit volatile organic compounds. Maintain ventilation before moving in[6]. A platform bed can provide large storage compartments in the smaller bedroom of a 400 sq ft flat. If it may become a child’s room, allow for platform height and steps when planning.
- Main bedroom wardrobe, HK$17,400
- Small bedroom wardrobe and platform bed, HK$20,440
- TV cabinet and shoe cabinet, HK$13,300
- ENF-grade boards as standard


08
Cleaning and insurance, HK$13,100
L01 RenoClean Post-renovation cleaningand formaldehyde treatment, 400 sq ft × HK$16 = HK$6,400. L02 third-party and employees’ compensation insurance costs HK$6,700[1].
Insurance protects against risks including injury to workers or damage to neighbouring property during renovation. The Labour Department also reminds owners and contractors to attend to safety during repair and alteration works[8].
Renovation leaves fine dust that can be difficult to remove. Allow for post-construction cleaning, the specified formaldehyde treatment and good ventilation. Where possible, ventilate for another one to two weeks before moving in.
- Cleaning and formaldehyde treatment, HK$6,400
- Insurance, HK$6,700
- Protect workers and neighbours
You can swipe left or right on your phone to view the complete table.
| Category | Full renovation | Lower-cost option | Difference |
|---|---|---|---|
| kitchen | HK$70,400 | HK$28,300 | HK$42,100 |
| Bathroom | HK$55,540 | HK$6,900 | HK$48,640 |
| electricity | HK$19,410 | HK$9,360 | HK$10,050 |
| Surface finishes | HK$58,200 | HK$36,300 | HK$21,900 |
| Bespoke furniture | HK$51,800 | HK$25,560 | HK$26,240 |
| Cleaning and insurance | HK$13,100 | HK$13,100 | HK$0 |
| Total | HK$268,450 | HK$119,520 | HK$148,930 |
Examples based on HK Create Design's published 2026 rates. [1]
- Weeks 1–2Strip-out, plumbing and electrics
- Weeks 3–4Waterproofing and tiling
- Weeks 5–6Painting and furniture
- Weeks 7–8Finishing and acceptance checks
09
8-week programme, week by week
Allow about seven to nine weeks for the full example, depending on furniture production and weather. A typical programme starts in week 1 with protecting the entrance and lift, stripping out the kitchen and bathroom and chasing service routes. Week 2 covers pipework, wiring and plastering.
Week 3 covers kitchen and bathroom waterproofing and pond tests. Week 4 covers tiling and the living room false ceiling. Week 5 covers filling and primer throughout. Week 6 covers fitting kitchen cabinets and furniture and laying SPC flooring.
Week 7 covers finish coats, fittings, switches and spotlights. Week 8 covers cleaning, formaldehyde treatment, owner inspection and defects. Custom furniture usually goes into production as soon as site work begins, so approve the drawings beforehand. We send weekly progress photos.
The Environmental Protection Department publishes answers to common questions about domestic renovation noise[7]. Strip-out and chasing are among the noisiest works. Follow building management’s permitted hours.
- Weeks 1–2: strip-out, plumbing and electrical work
- Weeks 3–4: waterproofing and tiling
- Weeks 5–6: painting and furniture
- Weeks 7–8: finishing and acceptance
- Full renovationKitchen and bathroom combined, 46.9%
- Lower-cost optionKitchen cabinet replacement, bathroom fittings, whole-flat repainting and one wardrobe

10
Lower-cost option at HK$119,520, covering essentials
If there is no seepage and the kitchen and bathroom tiles are sound, consider the lower-cost scope. In this separate 7 ft kitchen estimate, A06 old cabinet removal is 7 ft × HK$170 = HK$1,190. With base and wall units, quartz worktop and cooker hood installation, the total is HK$28,300[1].
Bathroom refresh retaining tiles: K06 fitting installation HK$5,650 plus E05 local mould treatment HK$1,250 = HK$6,900. Electrical: distribution board HK$6,800 plus 4 sockets HK$2,560 = HK$9,360[1].
Finishes: E03 repainting, 1,200 × HK$12 = HK$14,400, SPC flooring HK$20,400 and skirting HK$1,500. Furniture: a 6 ft main bedroom wardrobe HK$17,400, TV cabinet HK$7,500 and delivery HK$660. Cleaning HK$6,400 and insurance HK$6,700[1].
The lower-cost option totals HK$119,520, about HK$299 per sq ft and HK$148,930 below the full example. It retains the old kitchen and bathroom tiles and pipes, which may need opening up later. Consider a G01 opening-up inspection of the supply and waste pipes at HK$930 first[1]. The inspection report and photos can help you decide whether a full kitchen and bathroom renovation is worth the extra HK$90,000.
- 7 ft kitchen cabinet replacement example, HK$28,300
- Bathroom fitting works, HK$6,900
- Whole-flat repainting and SPC
- Total HK$119,520
11
Calculate the works allowance by dividing the total budget by 1.2
HK Create Design suggests dividing the total budget by 1.2 to obtain the works allowance. Retain 20% of that allowance as a separate contingency. Any money not spent stays with the owner.
For the HK$268,450 full example, a total budget around HK$322,000 gives a reserve (268,450 × 1.2 ≈ 322,140). A total budget of HK$250,000 gives a works allowance around HK$208,333, calling for an intermediate scope.
An intermediate option could include a full bathroom if seepage warrants it, kitchen cabinet replacement, E02 whole-flat painting, SPC, a distribution board and two wardrobes. Add or remove individual items to fit the available works allowance.
- Total budget ÷ 1.2 = amount available for the works
- Allow about HK$320,000 for a full renovation
- The owner holds the contingency
- Choose an intermediate scope
12
Which items have the biggest effect on price?
First, decide whether the kitchen and bathroom need a full renovation. In this example, full renovation totals HK$125,940, while the budget option costs HK$35,200: a difference of over HK$90,000[1].
2. Wall condition. For 1,200 sq ft, E01 stripping at HK$39 per sq ft totals HK$46,800, while E03 repainting at HK$12 per sq ft totals HK$14,400. The difference is HK$32,400[1].
3. Furniture quantity and height. For full-height wardrobes over 2,400 mm, add HK$100 per linear foot for each additional 100 mm[1]. Fourth, floor finishes. Removing and replacing tiles adds demolition, debris removal and screeding costs. Laying SPC over a suitable base avoids these items.
5. Building restrictions. Some buildings limit hours, require extra protection and collect deposits. Walk-ups may need stair carry charges under FUR43 at HK$300 per floor[1].
- Kitchen and bathroom scope makes a difference of around HK$90,000
- Wall condition: a HK$30,000 difference
- Furniture quantity and height
- Building restrictions
Example: economy option and total budget
Assumptions
- Kitchen and bathroom free of seepage
- Walls in good condition
- Keep only the main bedroom wardrobe and TV cabinet
How to calculate quantities
- Kitchen cabinet replacement: 1,190 + 9,100 + 8,750 + 8,400 + 860 = HK$28,300
- Bathroom: 5,650 + 1,250 = HK$6,900. Electrical: 6,800 + 2,560 = HK$9,360
- Finishes: 14,400 + 20,400 + 1,500 = HK$36,300
- Furniture: 17,400 + 7,500 + 660 = HK$25,560. Cleaning and insurance: HK$13,100
- Total: HK$119,520
- Suggested total budget: 119,520 × 1.2 ≈ HK$143,424
Lower-cost example about HK$119,520, with a suggested total budget around HK$143,000.
Keeping the original kitchen and bathroom tiles and pipes can mean reopening them later. The owner holds the contingency separately. [1]
13
Common mistakes when renovating a 400 sq ft flat
1. Comparing quotes using the square-foot figure alone. Two firms may quote HK$500 per sq ft while one rebuilds the kitchen and bathroom and the other replaces only cabinets. Align the scope, including strip-out, debris removal, waterproofing tests, cleaning and insurance.
2. Starting before furniture drawings are approved. Custom pieces need production time and late decisions may delay handover. In the Consumer Council study, delays were the most common renovation dispute (61%)[2].
3. Skipping the pond test. After bathroom waterproofing, test for 24 hours and confirm there is no seepage before tiling. Rectifying a later leak can cost much more.
4. Too few usable sockets. In a 400 sq ft flat, furniture can block several outlets. Lay out the electrical points alongside the furniture during design.
Mistake 5: spending the whole budget. If work uncovers problems with pipes or walls after demolition, a budget with no contingency leaves little choice but to compromise. In a 400 sq ft flat where the budget is already tight, a reserve is particularly important.
- Check the scope behind the square-foot rate
- Approve furniture drawings before starting
- Include a pond test
- Allow a contingency
14
How to adapt this example to your flat
1. Measure your kitchen run. This example uses 7 ft. At 6 ft, deduct one foot each of base cabinets (HK$1,300), wall cabinets (HK$1,250) and quartz worktop (HK$1,200), reducing this itemised example by HK$3,750. The separate 6 ft design package is HK$28,200.[1].
2. Estimate wall and ceiling area. Three times the saleable area gives an initial allowance, so the 400 sq ft example uses 1,200 sq ft. A site measurement allows for doors, windows and tiled kitchen and bathroom walls.
3. Assess the walls. After resolving damp or mould, peeling finishes may need E01 stripping. Generally sound walls with local cracking may suit E02. Walls in good condition may suit E03 repainting[1]. In the same flat, choosing the wrong approach can cost tens of thousands of dollars more.
4. List furniture items and approximate widths, for example a 6 ft main bedroom wardrobe and 6 ft TV cabinet. Multiply by the relevant linear foot rate. Tall, medium-height and low cabinets have different rates.
Step 5: add cleaning, insurance and transport. These small items are easy to overlook and together can amount to around HK$10,000. Multiply the total by 1.2 for the suggested overall budget.
- Measure the kitchen run
- Estimate the wall area
- Assess the condition of the walls
- List the furniture required
- Add the minor items, then multiply by 1.2 for the planning reserve
You can swipe left or right on your phone to view the complete table.
| Week | Main work stages | Owner's responsibilities |
|---|---|---|
| Week 1 | Kitchen and bathroom strip-out, protection and service chases | Approve furniture drawings |
| Week 2 | Plumbing, wiring and plastering | Confirm socket positions |
| Week 3 | Waterproofing and pond testing | Review water-test photos |
| Week 4 | Tiling and false ceiling | Confirm tile selections |
| Week 5 | Local filling and primer | Confirm the paint colour |
| Week 6 | Furniture installation and SPC flooring | Inspect furniture on site |
| Week 7 | Finishing paint, fittings and lights | Prepare the appliance schedule |
| Week 8 | Cleaning, handover and defect rectification | Inspect each item at handover |
Illustrative programme. Furniture production, management rules and weather affect actual dates. [1]

15
Documents and information to prepare before renovation
Before starting, obtain the flat plan from management or the developer, the building’s renovation rules, the management application form and deposit details. Many buildings allow work only at specified hours from Monday to Saturday and restrict work on Sundays and public holidays.
For an older building, ask management about major works in progress or planned, such as pipe replacement or façade repairs. Coordinate the flat renovation to avoid clashes.
Select built-in appliances such as ovens and dishwashers before starting. Use their dimensions and ventilation requirements to plan kitchen openings. Decide air-conditioner positions early because they affect false ceilings and electrical points.
HK Create Design supplies a pre-start checklist identifying what owners need to prepare and approve so items can be resolved before site work begins.
- Flat floor plan
- Building renovation rules and deposits
- Will building-wide works overlap?
- Built-in appliance models
16
Ask HK Create Design to estimate your flat
No two 400 sq ft flats are identical. Kitchen length, bathroom area, wall condition, building age and management rules all affect the price. HK Create Design has served Hong Kong owners since 2019 with designers and tradespeople with over 15 years’ experience.
We quote each item for your flat, specifying scope, materials, quantities and unit prices. A limited offer provides free site measurement for two or more work items until 31 December 2026.
Shop 16, G/F, Fu Yau Building, 61 Po Kong Village Road, Wong Tai Sin, Kowloon. WhatsApp 5243 7747. HK Create Design provides a one-year warranty and has a HK$2,000 minimum charge.
- Itemised quote with a clear scope
- Limited-time free site measurement for two or more work items
- WhatsApp 5243 7747
Advice from our tradespeople
「For a 400 sq ft flat, deciding whether to gut the kitchen and bathroom often has the biggest impact. I would inspect the pipes before choosing. If they are corroded, replacing them now can avoid opening new tiling later.」
「A platform bed and wardrobe turn the smaller bedroom into usable storage space. Plan sockets and bedside lighting with the furniture. A two-way bedside light switch allows control from bed. In a small flat, even an inch of clearance can matter.」
FAQ
12 practical questions answered
01How much does a whole-home renovation cost in a 400 sq ft flat?
At HK Create Design’s published 2026 rates, the full renovation example costs about HK$268,450 and the lower-cost option about HK$119,520[1]. Confirm actual quantities at a site measurement.
02How long does a whole-home renovation take in a 400 sq ft flat?
A full renovation takes about seven to nine weeks. An economy refurbishment retaining the kitchen and bathroom usually takes about three to five weeks.
03Is this an actual client project?
No. This is an example flat costed from published rates for reference. Actual prices vary by flat.
04How can I calculate an accurate price per square foot?
Check whether full kitchen and bathroom renovation is included before using a square-foot rate. The full example is about HK$671 per sq ft and the lower-cost example about HK$299[1].
05Do the kitchen and bathroom both need full renovation?
If there is no seepage, the tiles are sound and the pipes are in good order, changing only cabinets and fittings may be enough. If unsure, G01 opening-up inspection costs HK$930[1].
06Can SPC flooring go directly over existing floor tiles?
Yes, if the existing tiles are sound and sufficiently flat. J01 SPC flooring costs HK$60 per sq ft including materials and installation[1].
07Is a budget of HK$250,000 enough?
With a total budget of HK$250,000, the works allowance is about HK$208,333. A mid-range option might fully renovate the bathroom and replace kitchen cabinets.
08Do I have to move out during renovation?
Full renovation requires removing the kitchen and bathroom, so residents usually move out. An economy refurbishment may allow work in zones.
09How much is the 6 ft kitchen cabinet package?
Removing one linear foot each of base cabinets, wall cabinets and quartz worktop reduces this itemised example by approximately HK$3,750.[1].
10How can I estimate the wall area?
For an initial estimate, multiply saleable area by three. The 400 sq ft example gives 1,200 sq ft of painted surface. Confirm by measurement.
11Which details should I look for in the quotation?
The Consumer Council recommends specifying scope, materials, quantities, unit prices, payment arrangements and warranty[3].
12How should I choose panels based on formaldehyde emissions?
HK Create Design uses ENF-grade board as standard, with formaldehyde emissions ≤0.025 mg/m³. Keep the flat ventilated before moving in[6].
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]HK Create Design published 2026 rates and work item descriptions Accessed: 2026-11-03
- [2]Consumer Council: 4 proposed measures to strengthen regulation of the home renovation industry (21 February 2024) Accessed: 2026-11-03
- [3]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-03
- [4]Buildings Department: 2026–27 Estimates reply on numbers of private buildings by age Accessed: 2026-11-03
- [5]Electrical and Mechanical Services Department: Household Electrical Safety Handbook, new installations, additions and alterations Accessed: 2026-11-03
- [6]Environmental Protection Department: Indoor Air Quality Information Centre FAQs Accessed: 2026-11-03
- [7]Environmental Protection Department: FAQs on noise from renovation in residential premises Accessed: 2026-11-03
- [8]Labour Department: repair, maintenance, alteration and addition works — guidance for owners and tenants Accessed: 2026-11-03
- [9]Water Supplies Department: Licensed Plumber Accessed: 2026-11-03