Bathroom waterproofing prices in 2026: what HK$4,850 covers

HK Create Design’s published bathroom waterproofing price is HK$4,850 per room of about 30–40 sq ft. It covers the entire floor, 6 ft wall upstands, full-height shower walls, two coats of Sika 107 and a 24-hour ponding test. Additional area above 40 sq ft costs HK$39 per sq ft.

The word “waterproofing” could mean the floor alone, a floor with a one-foot wall upstand, or shower walls treated to the ceiling. Costs and protection differ substantially. The Consumer Council recommends stating the areas, material, waterproofing height and leak test. Of 11 contractors invited to quote, only 7 specified areas and fewer than half listed materials, height and testing.[1]

To compare bathroom waterproofing prices, check the areas, wall heights, material, number of coats and ponding test line by line. A lower total may leave part of the work out.

This article explains bathroom waterproofing prices and how to choose a scope. For detailed guidance on inspecting waterproofing and checking for seepage, see HK Create Design’s separate bathroom waterproofing inspection guide.

  • Confirm the areas to be waterproofed
  • Confirm how far the waterproofing extends up the walls
  • Confirm the product and number of coats
  • Confirm the ponding test
Site photo: bathroom stripped to its substrate, ready for base repairs and new waterproofing.
Site photo: bathroom stripped to its substrate, ready for base repairs and new waterproofing. Select an image to enlarge

02

Related rates for area-based waterproofing, testing and a full strip-out

C01 Waterproofing costs HK$39 per sq ft, with a minimum of HK$2,350. The work includes cleaning and dampening the substrate, reinforcing internal corners and pipe penetrations, and applying two coats of SikaTop Seal-107 in crossing directions. A third coat costs an additional HK$10 per sq ft. This rate applies, for example, to balconies or the part of a bathroom over 40 sq ft.

C04 is a standalone 24–48-hour ponding test at HK$1,400 per test. The drain is sealed and the floor flooded to a depth of 2–3 cm. The water level and ceiling below are monitored and photographed. A test is already included in C02 bathroom waterproofing. C04 can be booked separately to investigate an existing bathroom or retest after other work.

C05 costs HK$13,000 per bathroom for strip-out and renewed waterproofing. It includes removing tiles to the substrate, repairing the base, applying two waterproofing coats and ponding testing. Retiling is excluded. Demolition and testing are included, so the same work in that bathroom is not charged again under C01, C02, C04 or A10.

A10 Bathroom strip-out and clearance costs HK$9,950 per room, including removal and transport of wall and floor tiles, sanitaryware and the vanity. D09 costs HK$2,050 per shower enclosure with kerb, including construction to site dimensions, tiling and waterproofing.

  • Charge the area above 40 sq ft under C01
  • Ponding test included in C02
  • C05 is an option for a full strip-out
  • C05 does not duplicate A10 or C02 charges
HK Create Design bathroom waterproofing prices (2026)

You can swipe left or right on your phone to view the complete table.

ItemPriceincludeExclusions and points to check
C02 Waterproof one bathroom (about 30–40 sq ft)HK$4,850Entire floor, 6 ft wall upstands, full-height shower walls, two coats of Sika 107 and a 24-hour ponding testArea above 40 sq ft charged under C01. C04 testing included.
C01 SikaTop Seal-107 waterproofing, priced per sq ftHK$39/sq. ft. (minimum HK$2,350)Clean and dampen the substrate, reinforce internal corners and pipe penetrations, and apply two coats in crossing directionsAdditional HK$10/sq.ft. for third floor
C04 flood test (24–48 hours)HK$1,400 per testSeal the floor drain, pond to a depth of 2–3 cm, monitor the water level, inspect the ceiling below and photograph the results.Included in C02
C05 Bathroom including disassembly and redo waterproofingHK$13,000 per roomRemove tiles, repair the substrate, apply two waterproof coats and flood-testRetiling is excluded. Overlapping work is not charged again under C01, C02, C04 or A10.
A10 Bathroom strip-out and clearanceHK$9,950 per roomRemove and transport wall tiles, floor tiles, sanitaryware and the bathroom vanity—
D09 Form a shower base with a raised kerbHK$2,050 per setBuild, tile and waterproof the shower enclosure—

Includes labour and base materials. Facing tiles and sanitaryware are separate. Customers choose their own sanitaryware and HK Create Design charges for installation. The written quotation after site measurement confirms the price. [8]

Bathroom waterproofing prices: key figures illustrated | HK Create Design
Bathroom waterproofing prices: key figures at a glance | HK Create Design Select an image to enlarge

03

Waterproofing products: Sika, Nitocote and OPTIMIX

HK Create Design uses Sika 107 for C02 bathroom waterproofing. Sika lists SikaTop-107 Seal HK for bathrooms, toilets and balconies. Allow about 1.0 kg/m² per coat or 2.0 kg/m² in critical areas. Apply at least two coats, with three recommended where seepage risk is high.[2]

The manufacturer specifies +8 to +35°C for application. Approximate intervals between coats are 12 hours at 10°C, 6 hours at 20°C and 3 hours at 30°C. Protect the coating from direct sun, wind and rain while it cures.[2] Allow time between coats and for the full cure. These stages set the pace of waterproofing work.

Fosroc Nitocote CM110 is a two-component, polymer-modified cementitious waterproofing slurry. The manufacturer lists sunken bathroom slabs, roofs and balconies among its uses. It accommodates minor cracking and movement at tile joints and can be applied by brush, trowel or spray.[3]

The manufacturer lists OPTIMIX WP515 waterproofing slurry for bathrooms, kitchens and balconies. Apply at least two coats of about 1 mm each. Consumption is approximately 1.60 kg/mm/m². Allow about 1–2 days before applying the finish.[4]

All three products are cementitious waterproofing slurries. The appropriate system depends on site conditions and design requirements. HK Create Design’s C02 price is based on Sika 107. Any change of system is subject to written quotation.

  • At least two coats
  • Consider three coats in high-risk areas
  • Check the application temperature
  • Allow time between coats
  • Protect from sun, wind and rain during curing
Our rates for bathroom waterproofing and related work(Unit:HK$ per item)
C04 flood test
HK$1,400
D09 Form a shower base with a raised kerb
HK$2,050
C02 Bathroom waterproofing
HK$4,850
C05 Strip out and renew waterproofing
HK$13,000

HK Create Design’s published prices for 2026.

Site photo: the bathroom floor is levelled to falls. Tiling follows waterproofing and the ponding test.
Site photo: the bathroom floor is levelled to falls. Tiling follows waterproofing and the ponding test. Select an image to enlarge

04

How high should waterproofing extend?

HK Create Design’s C02 covers the full floor, 6 ft up the walls and the full height of the shower walls. Water drains to the floor, shower spray reaches the walls and their junction with the floor is vulnerable to seepage. The shower walls receive direct spray and need full-height coverage.

Without a shower enclosure or glass screen, water splashes farther and the waterproofed area needs to extend accordingly. With a bath, pay particular attention to its perimeter and the area beneath it.

Waste pipes, floor drains, wall penetrations and internal corners need reinforcement because they are particularly prone to leakage. C01 and C02 both include this detailing.

The quotation should state the waterproofing height. A line reading only “waterproofing” gives no coverage detail. The Consumer Council also lists height among the items to specify in a quotation.[1]

  • Entire floor
  • Specify the wall upstand height
  • Full-height coverage in the shower
  • Reinforce pipe penetrations and internal corners
Site photo of a completed bathroom renovation | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge

05

How a ponding test works and what to look for

A ponding test takes place after the waterproofing is complete and before tiling. Seal the floor drain and flood the floor to a depth of 2–3 cm. Over 24–48 hours, watch for a marked fall in the water level or stains on the ceiling below. HK Create Design photographs the observations for the handover record.

Testing before tiling matters. A leak found afterwards means removing tiles and repeating work, adding considerable time and cost. A ponding test isWaterproofingthe most important verification step in the process.

Coordinate the ponding test with the owner of the flat below and ask them to watch the ceiling. If a stain appears, drain the water promptly, inspect and repair the waterproofing, then retest.

C02 includes a 24-hour ponding test. A standalone C04 test costs HK$1,400 per visit and lasts 24–48 hours.

  • Test before tiling
  • Flood to a depth of 2–3 cm
  • 24–48 hours
  • Inspect the ceiling below
  • Keep a photographic record
Worked example 1

Example one: a 35 sq ft bathroom with the old tiles removed

Assumptions

  • Assume the old tiles have been removed and the substrate is sound.
  • Bathroom of approximately 35 sq ft.

How to calculate quantities

  1. C02 Bathroom waterproofing: 1 room × HK$4,850 = HK$4,850.
  2. A 24-hour ponding test is included. Do not add C04 separately.

HK$4,850。

Repair large cracks and loose areas in the substrate first. [8]

Use your square footage instead and see a reference budget

06

Why do bathroom waterproofing quotations differ?

1. Check the height. Treating only the floor can cover a fraction of the area of treating the floor, 6 ft up the walls and the full height of the shower.

2. Check the number of coats and the material. Sika recommends at least two coats of Sika 107.[2] Two coats take twice the material and time of one. Ask for the brand and model in writing.

3. Substrate preparation. Clean and dampen the substrate first, repairing cracks and loose areas. Waterproofing slurry cannot bond properly to an unprepared surface.

4. Reinforcing pipe penetrations and internal corners. These are common leak points and need extra detailing time.

5. Ponding tests. Check whether a test is included, its duration and how the result is recorded. Tiling without testing carries the greatest risk.

6. Strip-out scope. Removing bathroom tiles down to the substrate changes the work significantly. A full strip-out and renewal involves more than waterproofing an already exposed base.

  • Check waterproofing coverage
  • Check the material and number of coats
  • Check substrate preparation
  • Check reinforcement at pipe penetrations
  • Check ponding testing
  • Check the strip-out scope
Four details to specify in a bathroom waterproofing quotation

You can swipe left or right on your phone to view the complete table.

ItemSpecify in writingHow HK Create Design describes C02
Areas to be waterproofedFloor, walls, shower area and pipe penetrationsEntire floor, full height in the shower and reinforcement at internal corners and pipe penetrations
MaterialBrand and modelSika 107
Height of the waterproofingHow high does the waterproofing extend up the walls?6 ft wall upstands and full-height coverage in the shower
Leak testingPonding test duration, water depth and observations24-hour ponding test. For the standalone test, flood the area to a depth of 2–3 cm, inspect the ceiling below and take photographs.

These four points draw on the Consumer Council’s guidance on quotations. [1] [1]

07

Professional and official guidance

The following information is drawn from public documents issued by the Consumer Council, government departments and product manufacturers.

Consumer Council: a waterproofing quotation should specify the location, material, height and leak test.[1]

Sika’s product data: apply at least two coats of SikaTop-107 Seal HK, or three in high-risk areas. Application temperature: +8 to +35°C.[2]

1823 advises that owners should first investigate and repair seepage in residential flats. Unresolved cases can be reported to the Joint Office of the Food and Environmental Hygiene Department and the Buildings Department. According to 1823, revised procedures from 16 July 2026 include issuing an advisory repair notice and allowing time for repairs.[5]

FEHD: its seepage and dripping FAQ explains the scope and procedure of Joint Office investigations.[6]

Buildings Department: repair or replacement of sanitary fittings is exempt from prior approval but must comply with the Buildings Ordinance.[7]

In HK Create Design’s experience, common leak points are at drain edges, waste pipes and wall-to-floor junctions. We reinforce these details and verify the completed work with a ponding test.

  • Specify all four items in the quotation
  • Follow the manufacturer’s coat count and temperature limits
  • Owners’ responsibility for seepage
  • Exempt from prior approval but still subject to requirements

08

Seepage into the flat below: owners’ responsibilities and official procedures

If your bathroom is causing seepage on the ceiling below, 1823 advises that the relevant owners are generally responsible for investigating and repairing residential seepage.[5] Even if you have never renovated, you are responsible for dealing with seepage into the flat below caused by deteriorated waterproofing in your bathroom.

If you suspect seepage from the flat above or next door, 1823 advises raising it with the owners promptly. They should engage a building professional or licensed plumber to identify and repair the source.[5]

If the owners cannot resolve the issue, they can report it to the Joint Office of the Food and Environmental Hygiene Department and the Buildings Department. According to 1823, revised procedures for seepage in private buildings took effect on 16 July 2026. If there is reason to suspect the flat above, the Joint Office issues an advisory repair notice to its owner in about 14 working days of the report, asking for inspection and repair within 28 calendar days.[5]

According to 1823, the Joint Office contacts the complainant within 6 working days of receiving a report and uses non-destructive tests to identify the source. With the cooperation of the owners and occupants concerned, it can usually complete an investigation within 90 working days.[5] For the bathroom owner, a notice leaves limited time. Arrange an inspection and any necessary repairs promptly.

FEHD’s page on seepage and dripping also explains which cases the Joint Office handles.[6]

If the flat below reports a leak, a ponding test helps establish whether the bathroom is the source. If leakage is confirmed, assess whether a local repair is sufficient or a full strip-out and waterproofing renewal is needed.

  • Owners’ responsibility for seepage
  • Confirm with a ponding test first
  • Check the Joint Office’s current procedures
  • Assess local repair versus renewal
Waiting time between coats of SikaTop-107 Seal HK(Unit:hours)
10°C
about 12 hours
20°C
about 6 hours
30°C
about 3 hours

Manufacturer’s figures. Actual times vary with humidity and ventilation. [2]

Site photo of a masonry partition under construction | HK Create Design
Site photo of masonry work | HK Create Design Select an image to enlarge

09

Options A and B: local repair or complete strip-out and renewal

A local repair suits a clearly identified, small leak, such as one at a drain edge or individual tile joint. Tiles can be removed locally, the waterproofing renewed and the repair tested. It is quicker and cheaper, but the junction between old and new waterproofing is vulnerable. A misidentified leak source will remain.

A full strip-out suits bathrooms with several leaks, an ageing membrane or a planned renovation. It exposes the substrate for repair, fresh waterproofing and testing. C05 costs HK$13,000 and includes strip-out, base repairs, two waterproofing coats and a ponding test. Retiling is extra.

Start with a ponding test and note where seepage appears below, then ask a tradesperson to assess it. In a bathroom around ten to twenty years old with blackened joints and many hollow-sounding tiles, a full strip-out is usually advised.

If you are renovating the bathroom anyway, a full strip-out is usually the most economical choice. Demolition, waterproofing and tiling can then be completed in one project.

  • Consider a local repair if the leak is clearly located
  • Multiple leaks or ageing waterproofing may warrant a full strip-out
  • Test first, then decide
  • Complete the work together during renovation
Worked example 2

Example two: a larger 48 sq ft bathroom

Assumptions

  • Assume a bathroom of about 48 sq ft.

How to calculate quantities

  1. C02: HK$4,850 for the first 40 sq ft.
  2. Excess area: 8 sq ft × HK$39 = HK$312.
  3. Total: HK$5,162.

Approximately HK$5,162. The written quotation confirms the rate for excess area.

A large shower or a bath changes the area that needs treatment. [8]

Use your square footage instead and see a reference budget

10

Common bathroom waterproofing mistakes

1. Tiling before a ponding test. This is a common, high-risk mistake. A leak discovered after tiling can mean stripping it all out and starting again.

2. Treating only the floor. Without treatment at wall-to-floor junctions and in the shower, water can track down the walls.

3. Pipe penetrations without reinforcement. Drain outlets and floor drains are particularly vulnerable to leaks if detailing is omitted.

4. Rushing the work. Allow the specified interval between coats and cure the coating before tiling. Sika’s technical data gives the recoating intervals and curing requirements.[2]

5. Drilling through the waterproof layer. Fixings for rails and accessories can penetrate it after tiling. Keep holes away from the shower area where possible, or seal the penetration with waterproof silicone. HK Create Design uses DOWSIL mould-resistant silicone for wet-area joints.

  • Test before tiling
  • Include walls and the shower area
  • Reinforce pipe penetrations
  • Allow the work sufficient time
  • Drill with care

11

Handover checklist

After waterproofing, check for missed areas, blisters and cracks. Confirm reinforcement at internal corners and pipe penetrations, and compare the wall coverage with the quotation.

Ponding test: check the photographs, any change in the water level and the condition of the ceiling below.

After tiling, pour water to check the fall towards the drain and confirm there is no ponding. Inspect silicone joints for continuity.

Documents: keep the waterproofing product data, installation photographs and ponding test records. The workmanship warranty lasts one year, subject to the written quotation.

  • Check for missed areas and blistering
  • Check the height
  • Check test records
  • Check floor falls
  • Keep photographs and documents
Manufacturers’ data for common waterproofing products (summary)

You can swipe left or right on your phone to view the complete table.

MaterialTypeUse specified by the manufacturerCoats and material consumption
Sika SikaTop-107 Seal HKPolymer-modified cementitious waterproofing slurryBathrooms, toilets and balconiesAbout 1.0 kg/m² per coat, with at least two coats [2]
Fosroc Nitocote CM110Two-component polymer-modified cementitious waterproofing slurrySunken bathroom slabs, roofs and balconiesApply by brush, trowel or spray. The product accommodates minor cracking and movement at tile joints [3].
OPTIMIX WP515waterproofing slurryBathrooms, kitchens and balconiesAt least two coats, about 1 mm per coat, at approximately 1.60 kg/mm/m² [4]

C02 pricing is based on Sika 107. A change of system requires a written quotation. [2][3][4]

Project photo of plumbing work at Yat Man House, Ho Man Tin Estate | HK Create Design
Project photograph: plumbing at Yat Man House, Ho Man Tin Estate, May 2026, HK Create Design Select an image to enlarge

12

How to schedule bathroom renovation

Typical sequence: strip-out → plumbing and wiring → rendering and levelling to falls → first waterproofing coat → waiting period → second coat → curing → ponding test → tiling → grout finishing → install sanitaryware.

Complete plumbing before waterproofing. HK Create Design specifies copper pipes and works with licensed plumbers. We can handle Water Supplies Department applications. Complete the wiring and water heater supply at this stage as well.

Allow time between the two coats. Sika 107 requires about 6 hours at 20°C.[2] Allow for curing and a 24-hour ponding test afterwards. The waterproofing alone needs at least two to three days.

Customers choose the sanitaryware and taps. HK Create Design fits them for an installation fee.

  • Complete plumbing before waterproofing
  • Allow two to three days for waterproofing and testing
  • Fit sanitaryware last
Worked example 3

Example three: two ways to price a full strip-out and renewal

Assumptions

  • Assume all the old bathroom tiles, sanitaryware and vanity are to be removed and the waterproofing renewed.
  • 30 sq ft of floor and 180 sq ft of walls, followed by straight-laid 300 × 600 mm tiles.

How to calculate quantities

  1. Option A: A10 bathroom strip-out and clearance HK$9,950 + C02 bathroom waterproofing HK$4,850 = HK$14,800.
  2. Option B: C05 bathroom strip-out and renewed waterproofing costs HK$13,000, including strip-out, substrate repairs, two waterproofing coats and a ponding test.
  3. Tiling: D01 floor, 30 × HK$78 = HK$2,340, so the HK$3,250 minimum applies. D02 walls, 180 × HK$78 = HK$14,040.
  4. Option B including tiling: HK$13,000 + HK$3,250 + HK$14,040 = HK$30,290.

Demolition, waterproofing and tiling total about HK$30,290, excluding finish tiles, sanitaryware installation, plumbing and debris disposal.

C05 is not charged alongside A10, C02 or C04 for overlapping work in the same bathroom. The scope on site determines which item applies. [8]

Use your square footage instead and see a reference budget

13

Bathroom waterproofing in public rental flats, Home Ownership Scheme flats and older buildings

Public rental flat renovation: alterations to public rental flat bathrooms must meet Housing Department requirements. Check with the estate office first.

Home Ownership Scheme flat renovation: check management requirements for renovation hours and debris disposal, and coordinate the ponding test with the flat below.

Older flat renovation: waterproofing in older bathrooms is often worn out, and floors may have several layers of tiles. We recommend stripping back to the substrate before renewal. If the old water pipes are still lead or iron,Pipe replacementshould be done alongside the waterproofing.

  • Check first in public rental housing
  • For Home Ownership Scheme flats, coordinate with the flat below
  • Full strip-out and renewal in an older flat

14

How much of a bathroom renovation budget goes on waterproofing?

In example three, a full strip-out, new waterproofing and tiling cost about HK$30,290, excluding finish tiles, sanitaryware installation, plumbing and debris disposal. The C05 waterproofing package, including strip-out, is HK$13,000.

If the old tiles have been removed and only waterproofing is needed, C02 at HK$4,850 includes the waterproofing and a 24-hour ponding test.

For a bathroom budget, list demolition, plumbing, waterproofing, tiling, sanitaryware installation, the suspended ceiling and lights, and debris disposal separately. This makes quotations easier to compare.

  • Separate demolition, waterproofing and tiling
  • Include testing in the waterproofing scope
  • Compare item by item
How many seepage complaints does Hong Kong receive?

You can swipe left or right on your phone to view the complete table.

YearSeepage complaints received by the Joint OfficeReferred to the Buildings DepartmentReferred to the Water Supplies Department
202239,555 cases1,243 cases702 cases
202345,033 cases1,436 cases861 cases
202447,299 cases2,200 cases1,236 cases

Development Bureau reply to the Legislative Council [10]. Complaints rose by nearly 20% over the three years. [10]

Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge

15

Bath, shower enclosure or screen: how does the choice affect waterproofing?

Treat the floor beneath a bath and the adjoining walls before installation. This concealed area is hard to inspect. If the perimeter silicone deteriorates, water can track under the bath and into the flat below. Use mould-resistant silicone at the edge and inspect and renew it regularly.

A shower kerb keeps water inside the enclosure and directs it towards the shower drain. HK Create Design item D09 costs HK$2,050 per enclosure with kerb, including construction, tiling and waterproofing. The enclosure itself needs waterproofing, with reinforcement where it meets the walls.

A shower screen or level-access design: a step-free shower puts greater demands on floor falls and waterproofing because water can travel outside the shower area. Extend the waterproofing, form accurate falls and plan the drain position in advance.

Consider your family’s needs as well as appearance. For households withOlder residents, a level-access shower can be safer, but needs carefully formed falls and waterproofing. A bath may be more convenient for families with young children. Discuss the choice during design so the waterproofing matches the layout.

  • Waterproof beneath and around the bath
  • Reinforce shower junctions
  • Extend the waterproofing for a shower without a kerb
  • Choose for your household’s needs
Worked example 4

Example four: estimating Sika 107 quantities

Assumptions

  • Assume a 5 × 7 ft bathroom, giving a floor area of 35 sq ft.
  • 6 ft wall upstands around a 24 ft perimeter.

How to calculate quantities

  1. Wall area: 24 × 6 = 144 sq ft.
  2. Total area: 35 + 144 = 179 sq ft ≈ 16.6 m².
  3. Material for two coats: 16.6 × 1.0 kg × 2 ≈ 33 kg. [2]

About 33 kg, excluding additional coverage for full-height shower walls and reinforced areas.

Critical areas need more material. The manufacturer recommends about 2.0 kg/m². [2]

Use your square footage instead and see a reference budget

16

After waterproofing: routine maintenance

The membrane is concealed beneath the tiles. Check silicone around the bath, basin and shower screen regularly and renew it if it blackens or detaches. Look for damaged grout that allows water under the tiles, and keep the floor drain clear to reduce standing water and the risk of seepage.

If water stains appear on the ceiling below, arrange a ponding test promptly. Early action can reduce the repair area. Contact HK Create Design about problems arising during the one-year workmanship warranty.

  • Inspect the silicone sealant
  • Inspect tile joints
  • Keep the floor drain clear
  • Arrange a ponding test promptly if water stains appear

17

Site measurement, quotations and appointments

For a bathroom quotation we measure the area and inspect the shower, floor drain and old tiles. If seepage is already visible below, a ponding test can help confirm the source.

Before booking, prepare photographs of the bathroom, any seepage in the flat below, and the sanitaryware and tiles you prefer.

Send us any Joint Office notice or complaint from the flat below. We will try to schedule inspection and ponding testing within the time available. Our quotation states the repair scope, materials, number of coats and testing arrangements.

For a free quotation from a construction team, contact HK Create Design on WhatsApp 5243 7747. The Wong Tai Sin showroom opens Monday to Saturday, 10:00–18:00. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.

  • Measure the area
  • Inspect the floor drain and shower area
  • Prepare photographs of the seepage
  • Provide a copy of the Joint Office notice
Bathroom waterproofing heights at a glance

You can swipe left or right on your phone to view the complete table.

locationBuildings Department guidanceHK Create Design’s approach
Floor surfaceFull coverage [9]Comprehensive
General wall areasExtend 300 mm up the wall [9]Turn up the walls by 6 ft
Around the bath or showerAt least 1,800 mm [9]Full wall height
Internal corners, floor drains and pipes—Reinforce

The Buildings Department guidance is for new buildings. It is cited as a reference for renovation [9]. [9]

18

Water seepage in Hong Kong: what the dispute figures show

The Development Bureau reported 47,299 building seepage complaints to the Joint Office in 2024, nearly 20% more than the 39,555 recorded in 2022.[10]. In 2025, only 69.5% of cases were investigated within 90 working days.[11].

Public housing is affected too. In 2025 there were 9,203 seepage and leakage cases. More than 60% were in estates over 30 years old, and bathroom floors or walls were common sources.[12]. Getting the waterproofing right the first time costs less than investigating a leak and removing the tiles afterwards.

  • 47,299 complaints in 2024
  • 69.5% of investigations concluded within 90 working days
  • Bathrooms are a major source
Worked example 5

Example one: renewing only the waterproofing in a 35 sq ft bathroom

Assumptions

  • Illustrative example.
  • Tiles already removed down to the substrate.

How to calculate quantities

  1. C02 Bathroom waterproofing: HK$4,850, including ponding testing [8]

About HK$4,850

Major substrate damage requires a separate repair quotation [8]. [8]

Use your square footage instead and see a reference budget
Project photo of completed bespoke kitchen cabinets | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

19

How long before testing and tiling?

Apply at least 2 coats of SikaTop-107 Seal HK. For bathrooms, typical consumption is about 1.0 kg/m² per coat. At 30°C allow about 3 hours between coats.[2]. For SikaTop-300 Seal, the manufacturer requires at least 3 days of curing before a ponding test.[13].

HK Create Design applies two coats in crossing directions, allows them to cure and then carries out a 24–48-hour ponding test. Tiling starts after the test confirms there is no leak.[8]. Tiling over the waterproofing on the day of application to save time is a common cause of leaks.

  • At least 2 coats
  • Follow the manufacturer’s interval between coats
  • Let the waterproofing cure before testing

20

Why choose HK Create Design for bathroom waterproofing?

HK Create Design publishes its bathroom waterproofing prices in the online calculator. Each item states what is included or excluded and the minimum charge, so you can review additional costs before work starts.[8] HK Create Design’s quotations list materials, work stages and acceptance checks so you can compare other quotations line by line.

HK Create Design offers a one-year warranty after completion under the terms of the written quotation. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.

For a project estimate, send photos and the approximate area to HK Create Design on WhatsApp 5243 7747. You can also see samples and discuss options at our Wong Tai Sin shop, Monday to Saturday, 10:00–18:00.

  • Published, itemised prices
  • List inclusions and exclusions in the written quotation
  • One-year workmanship warranty
  • Send photos to WhatsApp 5243 7747 for a quotation

FAQ

16 practical questions answered

01How much does bathroom waterproofing cost?

HK Create Design charges HK$4,850 per bathroom of about 30–40 sq ft. This covers the whole floor, 6 ft wall upstands, full-height shower walls, two coats of Sika 107 and a 24-hour ponding test.

02How is an area above 40 sq ft priced?

Excess area is charged under C01 at HK$39 per sq ft, subject to the written quotation.

03Is there a separate charge for the ponding test?

C02 includes a 24-hour ponding test. A standalone test under C04 costs HK$1,400 per visit and lasts 24–48 hours.

04What does a full strip-out and renewal cost?

C05 bathroom strip-out and renewed waterproofing costs HK$13,000 per room, including strip-out, substrate repairs, two coats and a ponding test. Retiling is extra.

05How many waterproofing coats are needed?

Sika recommends at least two coats of SikaTop-107 Seal HK and three in areas at higher risk of seepage.[2] HK Create Design charges an extra HK$10 per sq ft for a third coat on area-based waterproofing quotations.

06How high should the waterproofing go?

HK Create Design’s C02 covers the whole floor, 6 ft up the walls and the full height of the shower walls.

07What should the quotation specify?

The Consumer Council recommends stating the areas, material, waterproofing height and leak test.[1]

08Am I responsible for seepage into the flat below?

According to 1823, owners are generally responsible for investigating and repairing seepage in residential flats.[5]

09How does the Joint Office handle seepage?

You can report the issue to the Joint Office. According to 1823, the procedures effective from 16 July 2026 include issuing an advisory repair notice.[5] Refer to the latest official announcement for full details.

10Can waterproofing be applied over existing tiles?

We do not recommend it. Waterproofing slurry is designed for a clean, damp substrate. Its adhesion and long-term performance on old tile faces cannot be assured.

11Can waterproofing be applied during winter?

Sika gives an application temperature of +8 to +35°C. Allow longer between coats at lower temperatures, about 12 hours at 10°C.[2]

12Sika or Nitocote?

Both are cementitious waterproofing slurries that their manufacturers list for bathroom use.[2][3] C02 is priced for Sika 107. Other systems are subject to written quotation.

13What should I do if I receive a notice recommending repairs?

According to 1823, the Joint Office asks the owner of the upper flat to inspect it and complete repairs within 28 calendar days.[5] Arrange a ponding test promptly to locate the leak, then decide between a local repair and renewing the waterproofing.

14How should an open shower without an enclosure be waterproofed?

A shower without a kerb needs more precise falls and wider waterproofing coverage. Water travels beyond the shower more readily, so extend the protected area and form the fall accurately.

15Is there a warranty?

The work carries a one-year warranty after completion, subject to the terms of the written quotation.

16How can I make an appointment?

WhatsApp 5243 7747. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Consumer Council, CHOICE issue 529: how to read a renovation quotation across 12 categories Accessed: 2026-11-03
  2. [2]Sika Hong Kong: SikaTop-107 Seal HK product information Accessed: 2026-11-03
  3. [3]Fosroc Nitocote CM110 product information Accessed: 2026-11-03
  4. [4]OPTIMIX WP515 waterproofing slurry technical data Accessed: 2026-11-03
  5. [5]1823: How to deal with water seepage in residential flats Accessed: 2026-11-03
  6. [6]Food and Environmental Hygiene Department: frequently asked questions about water seepage and dripping Accessed: 2026-11-03
  7. [7]Buildings Department: Frequently Asked Questions on Alteration and Addition Works to Domestic Premises Accessed: 2026-11-03
  8. [8]HK Create Design’s published 2026 prices: masonry, waterproofing, demolition and miscellaneous work Accessed: 2026-11-03
  9. [9]Buildings Department: Guidelines on Preventing Water Seepage in New Buildings (2005) Accessed: 2026-11-03
  10. [10]Development Bureau: Legislative Council Question 14, Joint Office for Investigation of Water Seepage Complaints (2 July 2025) Accessed: 2026-11-03
  11. [11]Joint Office for Investigation of Water Seepage Complaints: performance in investigating reports of building seepage Accessed: 2026-11-03
  12. [12]Housing Bureau: Legislative Council Question 8, Water seepage in public housing (28 January 2026) Accessed: 2026-11-03
  13. [13]Sika Hong Kong: SikaTop®-300 Seal technical data Accessed: 2026-11-03