Set the goal first: What you inspect and accept is a waterproof system, not a surface

Once the tile, caulking and silicone were completed, the waterproofing was mostly covered up. Therefore, the really critical acceptance point is before tiling or boarding. What the homeowner wants is not a sentence of "waterproofing has been done", but a record that can answer five things: where is the waterproofing range, how to treat the base layer, what are the materials and process basis, how to test the water, and how to repair and retest after failure.

First divide the project goals into two levels. The first layer is to protect daily wet areas when new or redone; the second layer is to find out the actual source of water seepage if watermarks have appeared. The two cannot be confused. A wet ceiling downstairs does not necessarily mean that the waterproofing of the floor has failed; common causes listed by the Buildings Department also include water supply pipes, drainage pipes, bathtub edges, and rainwater entering from rooftops, exterior walls or windows.[3]

If it is a renovation, first ask the contractor what kind of base is under the existing bricks, whether there are cracks, hollows, old waterproofing or caissons, and any items that can only be confirmed after removal. These are site risks and should not be pretended to have answers before work begins. The quotation can list the triggering condition of "to be jointly verified after excavation", but it must also be agreed on who will take the photos, who will propose the plan, when the price will be reviewed in writing, and when the coverage will continue.

  • Write "new waterproofing" and "existing water seepage diagnosis" separately in the scope of work
  • It is required to set up a common confirmation node before removing bricks, base layer, waterproofing, testing and tiling.
  • Record hidden situations that cannot be confirmed before starting construction and their written change process
Design renderings: Bathroom wet area floor, drainage and wall corners. The actual plan must be confirmed on site.
Design renderings: Bathroom wet area floor, drainage and wall corners. The actual plan must be confirmed on site. Select an image to enlarge

02

How to determine the waterproof range: match 300mm and 1,800mm

The Buildings Department's guidelines recommend that bathroom waterproofing membranes or waterproofing materials cover the entire floor and extend up to 300 mm on each wall; the walls around bathtubs and shower stalls should be extended up to at least 1,800 mm.[1] The most useful understanding for homeowners is: Generally, the wall base area and the shower wet area wall are two different measurement items. You cannot just write "toilet floor waterproofing" in the quotation, nor can you vaguely include the wall next to the bathtub, tub or shower screen.

The same guideline also states that this is a recommended approach to prevent water seepage in new buildings for general reference by designers and contractors. Therefore, 300mm and 1,800mm should not be said to be the legal universal sizes suitable for every renovation project. The shower location, sanitary ware chassis, wall finish, threshold, product technical information and building requirements still need to be checked on site; in the end, the scope drawing and quotation confirmed by both parties shall prevail.

Scope diagrams don’t have to be complicated. On the floor plan and photos of the four walls of the bathroom, you can use different colors to circle the floor, general wall bases, shower/bathtub walls, doorways, drainers, pipe openings and possible drilling locations in the future. Take photos with the same number before and after construction so that you can trace which detail was done after the tiles are laid.

  • Measure the floor, general wall base and shower/bathtub walls separately
  • Add numbers and recent photos to doorways, water purifiers, pipe openings and dark corners of walls and floors.
  • Don’t write the Buildings Department’s guidelines as a “statutory guarantee” without on-site verification
Write the bathroom waterproofing range into an acceptable range table

You can swipe left or right on your phone to view the complete table.

locationThe range that should be measured or markedCheck when acceptingCommon omissions or risksInformation should be retained
Full floor areaUse the net floor area available for the work, measured on site.Whether the waterproof layer continues to the wall base, door and around the water level; whether the subsequent protective layer is compatibleIt only reported "toilet waterproofing" without mentioning the area, water level removal or protection process.Before and after construction photos, material name/batch, scope sketch
General wall baseMeasure the turn-up height and length from the finished floor piece by pieceThe Buildings Department's guidelines use 300mm of each wall over the entire floor as a general reference; the official height should be included in the scope of workOnly do the floor, or interrupt the coating at the inner corner of the wallMeasurement photos, wall height markings, acceptance records before covering
Wall surrounding bathtub or showerCircle the wet area wall and measure the width and height from the groundThe Buildings Department's guidelines use at least 1,800 mm as a general reference; also check the sanitary ware, chassis and edge sealing practicesMistaking the general 300mm wall base range for the full range of the shower wallWall positioning photos, product technical information, and pre-completion test records
Floor drains, pipe openings, doorways and hidden cornersNumber the plans or photos one by one. It is not appropriate to describe only in square feet.Whether the closing is continuous; whether the product data requires the application of reinforcing layers, tapes or strips; whether it is subsequently drilled throughDestroying the waterproof layer after laying tiles, installing sanitary ware or drilling holes; there is no written explanation at the door or pipe openingRecent photos, construction sequence, repair locations and retest records

300mm and 1,800mm are derived from the Buildings Department's guidelines for new buildings. They are general references for design/construction and should not replace on-site design, product technical information or written quotations. SikaTop-300 Seal It is recommended to apply additional strips on cracks, wall-to-floor junctions, etc. to show that the details cannot be treated with the total area alone. [1][5]

Design renderings: Bathroom threshold, water level and brick joints.
Design renderings: Bathroom threshold, water level and brick joints. Select an image to enlarge
Site photo of bathroom cabinet and sanitaryware installation | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge
Bathroom waterproofing: illustrated facts and figures | HK Create Design
Bathroom waterproofing: key figures at a glance | HK Create Design Select an image to enlarge

03

Materials and processes: Ask for technical information, not just the brand name

Products with the same name as "waterproof materials" can have different base layer requirements, mixing methods, dosage of each layer, number of layers, waiting time between layers and maintenance time. The Buildings Department has also made it clear that waterproofing materials should be constructed in accordance with the manufacturer's specifications. Suitable waterproof caulking materials should be used around bathtubs and wash basins in accordance with the manufacturer's specifications. A compatible protective layer should be used above the waterproofing system.[1] Therefore, homeowners should ask for the actual brand, complete model and technical information used at that time, rather than accepting the words "name brand waterproofing".

A specific example is Sika Hong Kong's SikaTop-300 Seal: its technical page lists it as a two-component polymer-modified elastic cement-based waterproof slurry, and its scope of application includes wet areas such as bathrooms and shower rooms. The page lists at least two layers and a reference consumption of about 1 kilogram per square meter per layer. It also indicates that strip coatings are recommended for wall-to-floor junctions, cracks, and other locations.[5] This only shows "how specific the product information can be." It does not mean that it is more suitable for your organization than all products, nor is it the only recommendation.

Taking this product as an example, the technical page states that it must be cured for at least 3 days before the water storage test, and then it can be laid or plastered.[5] This also just explains why the fixed water closing hours circulated on the Internet cannot be applied to all materials. If the contractor recommends another product, the decision should be based on the latest technical data of that product, the temperature and humidity of the day, the condition of the grassroots and the construction plan, rather than copying the numbers of other products.

  • Collect material brand, model, batch, technical information and applicable basic information
  • Confirm the minimum number of layers, detail enhancement method, maintenance and testable conditions supported by which document
  • Confirm that tiling, plastering, caulking or installing sanitary ware will not damage the completed waterproofing layer

04

Flood testing: review the records and findings as well as duration

A flood test checks floors and junctions while the waterproofing can still be repaired. Buildings Department guidance calls for site supervision and verification such as ponding tests to check workmanship. It does not set a universal statutory 24- or 48-hour bathroom test.[1] Therefore, the safest approach is to write the test arrangements into the construction plan and make them consistent with the product information used.

A usable test record must at least include: test range and blocking location, start and end date and time, start and end water levels or measurement methods, whether there is other water on site, observation results downstairs and adjacent locations, photos, and who confirmed it. If the water level drops, first check whether the sealing is tight and whether there is evaporation, accidental drainage or other interference; if moisture marks are seen, it is also necessary to distinguish whether they are new leaks, old moisture marks or other water sources.

When a test fails, the worst thing you can do is immediately cover the problem with tiles, mortar, or silicone. The location should be marked first, photos should be kept, and the contractor should explain the proposed repair scope and method. After repair, the same scope of testing should be repeated. If the problem involves pipes or sanitary ware connections, waterproofing testing and drainage/water supply testing should be arranged separately to avoid attribution of errors.

  • Confirm product maintenance conditions and sealing methods before testing
  • Note the start and end times, water levels, observation points and site restrictions
  • After failure, a written repair plan and retest within the same scope are required, and the case will not be closed with a verbal "fixed the glue"
Worked example 1

Example one: breaking a sample bathroom into measured waterproofing quantities rather than pricing “one bathroom”

Assumptions

  • This is a hypothetical example illustrating calculation methods and is not a completed case, quote or construction proposal by the Company.
  • Assume that the buildable floor is 35 square feet and the perimeter of the wall base is 24 feet.
  • Generally, the wall base is turned up by 300 mm; 300 ÷ 304.8 = 0.9843 feet.
  • The shower wall is above the general 300 mm wall base, and there is another 18 square feet that needs to be covered; this 18 square feet has been defined as an additional area, so it is not counted twice with the wall base.

How to calculate quantities

  1. Ordinary wall upstands: 24 ft × 0.9842519685 ft = 23.62 sq ft.
  2. Combined area: 35.00 sq ft of floor + 23.62 sq ft of ordinary wall upstands + 18.00 sq ft of additional shower wall = 76.62 sq ft.
  3. Divide 76.62 square feet back into three items and write them into the range table, and also list drains, pipe openings, doorways and internal corners; these details should not disappear because the total area has been calculated.

This assumes a measurable waterproofing coverage of 76.62 square feet, with additional details to be described point by point. It reveals more 41.62 square feet of wall coverage and closing responsibilities than just "35 feet of floor waterproofing."

300 mm and 1,800 mm are general references in the Buildings Department's guidelines. They are not fixed rules that directly apply the area in this example to any unit. The actual measurement must be based on the shape of the bathroom, the location of the bathtub/tub, the base layer, product information and official drawings; the total area of ​​the shower wall must also be carefully avoided to avoid double counting with the general wall base. [1][5]

Use your square footage instead and see a reference budget
Masonry work in progress | HK Create Design
Site photo of masonry work | HK Create Design Select an image to enlarge

05

How to troubleshoot visible watermarks: first narrow down the possibilities based on water usage

The watermark location is just a clue. Common reasons listed by the Buildings Department include leaking drainage pipes, leaking water pipes in units above or adjacent to the building, leaking water pipes, inadequate floor waterproofing or bathtub edge sealing, and rainwater seeping in from rooftops, platforms, balconies, exterior walls or windows.[3] Therefore, "the ceiling downstairs is wet under the bathroom" does not directly prove that the entire bathroom must be redone to waterproofing.

What homeowners can safely do is compile the evidence: the date the watermark first appeared, whether it was aggravated by using the shower/toilet/hand basin, whether it was different when it rained, where and when the photo was taken, and past maintenance receipts. This information can help professionals determine whether drainage, water supply, sanitary ware edge sealing or floor waterproofing should be considered first. Do not cut open floor slabs, remove ceilings, modify underground pipes, or handle electrical installations in humid environments.

If it involves the construction, installation, maintenance, alteration, repair or dismantling of a water supply system, the Water Supplies Department explains that the Waterworks Facilities Ordinance has requirements for designated plumbing works, which should usually be handled by licensed plumbers, registered plumbers or persons under their instruction and supervision. If you have any questions about whether it is a minor project, you should check with the Water Authority.[4] Treat concealed plumbing as a specialist issue and have the applicable requirements checked before treating it as routine joint filling.

  • Establish a timeline of "when to use water and when to get wet" and take more than just one watermark photo
  • Separately record the conditions of sunny days, rainy days, showers, toilet flushing and use of the wash basin.
  • Stop handling hidden pipes, persistent water seepage or wet electrical locations by yourself, and arrange for appropriate professional assessment.
Project photo of plumbing work at Yat Man House, Ho Man Tin Estate | HK Create Design
Project photograph: plumbing at Yat Man House, Ho Man Tin Estate, May 2026, HK Create Design Select an image to enlarge

06

Five acceptance nodes before masking: evidence is retained at every step

The first node is the base layer after demolition. Check whether the floor and walls are loose, cracked, obviously hollow, damp or old, and confirm the location of water removal and space for future repairs. It’s not about the homeowner judging the structure, but asking questions while it’s still visible to avoid finding out later that the waterproofing has been applied and the substrate has not been treated.

The second node is before waterproofing construction. Check the base conditions, internal corners, wall-to-floor junctions, pipe openings and drain removers required by the product information. The third node is when the waterproofing is completed but not covered: confirm the scope from the distant view, confirm the details from the recent photos, and record the materials and dates. These two sets of photos should be saved along with the floor plan.

4. Flood-test to the agreed plan. After a pass, apply compatible protection, render or tiles. 5. Check drainage and product-specific seals at baths and basins. Collect test sheets, material data, defects and repair records and the warranty. The Buildings Department also advises protecting existing waterproofing during fitting-out works.[1]

It is better to include a recognizable location in the photo, such as the number of a corner, doorway or water purifier, rather than just a gray coating with no sense of direction. If the project is disputed later, "when, where, and whether it was seen before covering" will be more useful than a photo of the finished bathroom.

  • Take a set of photos with location marks after demolition, before construction, after waterproofing, after testing, and after tiling.
  • Check together before waterproofing is obscured by protective layers or tiles
  • Collect test records, material data, repair and retest records, and maintenance scope
Compare waterproofing-related quotations: first unify the quantity and unincluded items, then look at the total amount

You can swipe left or right on your phone to view the complete table.

Compare itemsQuantity or pricing basisThe quotation must stateCommon unincluded items/risksHomeowner decision-making problem
Removing old bricks and chippingState floor and wall areas separately, with the depth of removal to the cement bed or concreteRemoval depth, protection, handling, rubble and how additional deep hacking is priced“Remove bathroom” leaves the substrate, waste and unexpected findings unspecifiedIf the damp base or underground pipes are revealed only after disassembly, who will confirm the scope and how to get a quote first?
Basement and slope waterThe actual floor area and the locations that need to be repaired are not covered in "one form"Leveling, crack or hollow treatment, water removal and protective layer processesThe base layer is not treated before waterproofing; use ceramic tiles to cover drainage or closing problems in the future.Which node will I ask for joint acceptance before waterproofing?
waterproof layerFloors, general wall bases, shower walls and details should be listed separately in area or rangeBrand/model, number of floors or technical data basis, wall height, pipe openings and doorway details, testingOnly labor is listed or only "waterproof" is listed; materials, turning up, water testing and protection processes are omittedWhat materials are involved in this project, where is it done, when is it tested, and how can it be redone after failure?
Tiles and fabricsTiled area, tile size, laying pattern, special finishing and treatment of wastageWho supplies the labor, base material, and ceramic tile fabrics, and whether cutting, transportation, loading, and sweeping are included?Think of the unit price of tiles as an all-inclusive price including tiles, cleaning and transportation, sanitary ware disassembly and installation, and waterproofing.If the brick size, layout or crabapple angle is changed, what will be re-priced?
Testing, delivery and maintenanceUse clear project nodes instead of fuzzy "completion" calculationsTest range, start and end time, water level/observation point, photos, repair and retest arrangements; maintenance scope and exclusionsSaying "the water has been tested" verbally, but there is no test record; mistaking continuous pipe leakage for waterproofing maintenanceWhat documents can I receive before acceptance? What situations are not covered by this maintenance?

The Consumer Council recommends detailing the waterproofing locations, materials, upstand height and leak testing and stating actual construction areas for masonry. Our quick estimate also excludes full kitchen and bathroom reconstruction, waterproofing and replacement services, furniture and tile finishes. A single item or preliminary estimate does not cover a whole-flat renovation. [2][6][7]

Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge
Project photo of kitchen cabinet installation | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

07

Quotation comparison: Total amounts can only be compared within the same range.

The Consumer Council notes thatMasonry and tilingThe quotation should state the actual work area. For waterproofing, specify locations, material details, membrane height and whether a watertightness test is included.[2] The most effective way to compare is not to collect several total prices, but to hand over the same scope list to each contractor: which floor to demolish, how many floors and walls, height of the wet area, detail closing, protective layer, testing, tiling, fabrics, cleaning, sanitary ware disassembly and installation, and arrangements by the management office, and backfill them item by item.

Ask whether “labour and materials” includes waterproofing materials, mortar and the tiles themselves. The Consumer Council distinguishes masonry base materials from finishes. If the quote covers only labour and base materials, the owner may need to buy the tiles separately.[2] A tiling unit rate alone does not automatically include removal, substrate repair, waterproofing, sanitaryware, waste collection or special finishing. Mark unknown items for confirmation rather than assigning HK$0 or calling them all-inclusive.

Arrangements for changes to the contract or quotation should be written in an actionable manner: what findings trigger additions or subtractions, who will measure, when a written quotation will be provided, how the homeowner will confirm, and whether the coverage process will be suspended before confirmation. The Consumer Council recommends that the details of the post-processing work, the charging method and the completion date be included in the quotation in black and white to avoid relying solely on verbal promises.[2] This is general consumption information, not a legal conclusion for an individual contract. If there is a dispute or a large amount, professional advice may be obtained.

  • Use the same scope sheet to request quotes and compare item by item rather than just the total.
  • List waterproofing materials, extent, height, details, test and retest arrangements as separate rows
  • Put the verification, price review and approval procedures for unknown bases or underground pipes into written documents

08

Use our estimating tool: Know what it counts and what it doesn’t

HK Create Design's 2026 online calculator lists 117 work and service options in 8 categories. Of these, 116 have indicative prices and 1 rooftop package is priced on enquiry.[6] These figures describe the catalog status of our company's public calculator and are not the average of the Hong Kong market, nor do they have a fixed unit price for every bathroom. The calculator is suitable for breaking down ideas into quantities and processes. The formal project still needs to be confirmed by on-site conditions and written quotation.

The quick version covers basic whole-flat renovation, repainting and floor tiling. It starts from saleable area and approximates paint area as saleable area × 3. Full kitchens and bathrooms, waterproofing, replumbing, rewiring, furniture, finish tiles, sanitaryware, insurance, management deposits and renovation fees are excluded.[6]

The calculator cap can include up to a 20% planning reservation, which is not an automatic surcharge. Its function is to allow homeowners to see possible buffers before fabrics are unmeasured, unpacked, or undecided, rather than packaging an unspecified total into a promised price.[6] The budget demonstration in this article is also just a calculation demonstration, and it is not stated as a bathroom pricing for the company or the market.

Online estimates and enquiries are free. A site visit can be arranged if needed. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. Send the location, dimensions, site photos, occupancy and intended scope to WhatsApp 52437747 so we can advise whether to arrange a visit.[7]

  • Think of a quick estimate as a starting point for sorting out your requirements, not a formal all-inclusive quote
  • Bathroom waterproofing should be filled in separately on the floor, walls and details, and should not be replaced by paint multipliers.
  • Prepare bathroom photos, dimensions, leakage timeline and management office requirements before making an appointment.
Worked example 2

Example two: distinguishing a 20% planning allowance from a surcharge

Assumptions

  • This is a budget planning example, not a completed company case, a formal quotation, or the Hong Kong market average price.
  • Assume that the written project subtotal of HK$48,000 has been compiled to the same range; it does not represent the actual cost of any bathroom.
  • Select the 20% reservation only for planning purposes; the company's public calculator explains that the 20% of the upper limit is a planning reservation and is not a surcharge automatically charged by the company.

How to calculate quantities

  1. Allowance: HK$48,000 × 0.20 = HK$9,600.
  2. Upper budget: HK$48,000 + HK$9,600 = HK$57,600.
  3. The HK$48,000 is still regarded as a subtotal of the current scope; only after on-site discovery, specification changes or new construction are confirmed in writing, it will be treated as a formal quotation instead of automatically treating HK$9,600 as a mandatory payment.

The planning range for this hypothetical example is HK$48,000 to HK$57,600, of which HK$9,600 is reserved space, not the promised project price or inevitable price increase.

Scope, stripped base, piping, management requirements, materials, removal and fixture arrangements can all change the true cost. The specified plan for the quick estimate also does not include complete kitchen and toilet reconstruction, waterproofing, plumbing and electrical resurfacing, etc., so this example cannot be used as an all-inclusive price for the whole house or bathroom. [6][7]

Use your square footage instead and see a reference budget
Bathroom waterproofing: illustrated checklist | HK Create Design
Bathroom waterproofing: checklist | HK Create Design Select an image to enlarge

09

When to upgrade to professional investigation or management office coordination?

If water seepage occurs repeatedly, affects downstairs or adjacent units, appears only after certain types of water use, or if underground pipes or common parts are suspected, "find the source" should be put before "re-surface". The Buildings Department recommends that owners hire construction technicians or licensed plumbers to determine the cause and make repairs; if the management office still cannot negotiate with neighbors after investigation, they can call the Joint Office at 1823 for help.[3]

The Buildings Department FAQ says the Joint Office began piloting a new procedure on 16 July 2026. Stage one adds infrared thermography and electronic moisture meters. Where there is reason to believe the source is upstairs, the owner there may receive a repair advisory notice asking them to investigate and complete repairs within 28 calendar days.[3] This describes the government's procedure for investigating seepage as a sanitary nuisance in private buildings. It is not a typical bathroomWaterproofingwork programme, nor a guarantee that every case qualifies or can be completed within the same time.

Work involving electrical installations,Aluminium windows, structural walls, slabs, external walls or major strip-out may require different qualifications, building management arrangements and safety measures. Ask who will assess, carry out and coordinate the work. Do not remove dangerous window components, break into a slab or touch electrics in a wet area yourself. Mould removal, formaldehyde treatment and repainting cannot rule out continuing leaks or guarantee healthy occupancy.

  • If neighbors are affected, keep timelines, photos and contact records, and notify the management office as soon as possible.
  • Check the licensed arrangements for underground pipes or water supply projects and do not dismantle or modify them on your own
  • Separate understanding of government procedures, engineering remediation and private contract responsibilities

10

How to look after delivery: daily use does not mean giving up records

Upon delivery, first check the drainage direction, water removal speed, sanitary ware connection, bathtub or washbasin edge sealing, and wall and floor openings under normal usage conditions. If any abnormalities are found, immediately record the date, location and usage with photos or videos, and send a written notification to the contractor. Do not make large repairs or gouges by yourself first, otherwise the original evidence and source may be changed.

Read the warranty scope as well as its term. Ask whether it covers only waterproofing or also drains, sanitaryware seals, pipes, tile joints, later drilling, third-party changes or external rainwater. Our detailed calculator lists a one-year workmanship warranty for waterproofing, masonry and tiling. The final signed quotation and terms determine eligibility and exclusions.[7]

There are only a few types of delivery documents worth keeping: scope drawings, material information, pre-masking photos, test records, approved changes, receipts and warranty terms. They may not be able to solve every case of water seepage immediately, but they can make subsequent diagnosis and communication not dependent on memory alone.

  • Upon delivery, inspection will be based on normal water usage conditions, and any abnormalities will be recorded with the date and location.
  • Read clearly the boundaries and exclusions of the works covered by the maintenance, and do not take it as a guarantee for all water seepage
  • Centrally store scope drawings, product information, photos, test sheets, changes and official quotes

FAQ

7 practical questions answered

01Must a bathroom flood test last 24 or 48 hours?

A fixed 24 or 48 hours should not be said to be the general statutory rule for bathrooms in Hong Kong. The Buildings Department's guidelines mention water immersion testing as an example to verify construction quality, but do not specify a uniform number of hours for bathrooms.[1] The decision should be based on the actual product technical data, maintenance conditions, construction plan, test scope and building conditions, and the start and end time, water level, observation points and results should be recorded. For example, the technical page of SikaTop-300 Seal states that it must be cured for at least 3 days before filling. This is only information about this product and cannot be transferred to other products.[5]

02Is it enough to just waterproof the bathroom floor?

You cannot judge by just "making a platform". The Buildings Department's guidelines recommend the use of a waterproofing system for the entire bathroom floor and walls, with a wall base of 300 mm and a perimeter of 1,800 mm around the bathtub and shower cubicle as a general reference.[1] When renovating, the floor, general wall base, shower wall, doorway, water purifier and pipe opening should be clearly written separately, and confirmed based on the site and product data, rather than assuming that the same range is suitable for all bathrooms.

03There is a water mark on the ceiling downstairs. Does that mean the entire bathroom must be redone and waterproofed?

uncertain. Drainage pipes, water supply pipes, floor waterproofing layers, bathtub edge sealing and rainwater infiltration may all cause water seepage.[3] First record its relationship with water used in showers, toilet flushing, wash basins or rain, and then have the building technician or licensed plumber investigate as needed. Do not remove ceilings, cut floor slabs, or modify pipes by yourself when there are hidden pipes, wet electricity, or neighbors.

04The quotation only says "toilet waterproofing with work and materials included", is that acceptable?

Usually not enough for a fair comparison. The Consumer Council recommends that waterproofing quotations state the location, material information, height of the waterproofing layer and whether leakage testing is provided.[2] In addition, whether the base repair, pipe opening/door closing, protective layer, repair and retest after failing the test, removal, tiling and fabric are included, you will know whether the two quotes are doing the same thing. Unknown items should be listed for on-site verification and should not be treated as zero cost or all-inclusive.

05Can water seepage be solved by just patching up silicone glue or re-caulking?

Silicone and caulk are part of the fixture or finish sealing, but are not the common solution for all leaks. If the source is water supply/drainage pipes, floor waterproofing, or external rainwater, only repairing the surface may temporarily cover the problem, which may delay diagnosis.[3] Possible sources should be identified first based on usage conditions and on-site testing; the caulking materials around bathtubs and wash basins should also be processed according to the manufacturer's specifications.[1]

06Can our company's online estimate be used as a full-inclusive price for the bathroom?

No. The calculator is a preliminary budgeting tool. Of its 117 options, 116 have reference unit prices and 1 rooftop package awaits a quotation. Individual bathroom items still need confirmation.[6] The quick version excludes complete kitchen and bathroom reconstruction, waterproofing, replumbing and rewiring, furniture, finish tiles, sanitaryware, works insurance and management fees.[6] Initial online estimates and enquiries are free. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. Confirm eligibility for the offer on WhatsApp 52437747.[7]

07If the replacement of concealed pipes is involved, can it be handled by general plasterers at the same time?

Concealed plumbing should be scoped separately. The Water Supplies Department describes statutory controls on constructing, installing, maintaining, altering, repairing and removing specified plumbing works. These normally involve a licensed plumber, registered plumbing worker or a person acting under appropriate instruction and supervision. Ask the Water Authority if the work's minor status is uncertain.[4] In terms of project arrangements, it is required to clearly outline the scope of plumbing work, testing, who is responsible, and handover with the waterproofing process.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Buildings Department: Guidelines to prevent water seepage in new buildings Accessed: 2026-10-21
  2. [2]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-10-21
  3. [3]Buildings Department: Frequently Asked Questions on Water Seepage Problems Accessed: 2026-10-21
  4. [4]Water Supplies Department: Licensed Plumber Accessed: 2026-10-21
  5. [5]Sika Hong Kong: SikaTop-300 Seal products and technical information Accessed: 2026-10-21
  6. [6]HK Create Design: 2026 Quick Renovation Budget Calculator Accessed: 2026-10-21
  7. [7]HK Create Design: 2026 detailed project budget and pricing instructions Accessed: 2026-10-21