Step 1. Set priorities and a budget
Before renovating, ask why you are doing it, how long you will stay and how much you can spend. A full renovation may suit a second-hand flat you intend to occupy for ten years or more. A local refurbishment may suffice for a three-to-five-year stay.
Use HK Create Design’s online estimator to get an initial budget[1]. For a 450 sq ft flat, the light renovation example costs about HK$107,110, the intermediate option HK$236,890 and the full option HK$270,980[1]. The three scopes differ considerably. Deciding which you need makes the design discussion easier.
Set aside an owner-held reserve of about 20% of the works allowance. Opening up can expose ageing pipes or hollow plaster, and a reserve helps you deal with them.
Finally, list essentials and items you would like. Essentials might includeDistribution board replacement, Bathroom waterproofing. Decorative paint and lighting troughs are examples of optional items. Prioritise the essentials and add other items later if needed.
- Consider how long you plan to live there when setting the scope
- 450 sq ft: light HK$107,110, intermediate HK$236,890, full HK$270,980
- Allow a contingency of 20% of the works budget
- List the essentials and the extras you would like

02
Step 2. Site survey and condition inspection
A survey establishes both dimensions and condition. Inspect the age of the distribution board, scorch marks at sockets, galvanised pipes, kitchen and bathroom seepage, hollow or mouldy plaster and water ingress at windows.
Free site measurement for two or more work items is available until 31 December 2026. The L04 site visit costs HK$500 after the offer and is credited in full when the order is confirmed[1].
Prepare the floor plan, management renovation rules, style references and a description of your household and daily routines, such as whether anyone hasOlder residents, children, pets and working from home. The more details you share, the better the design can fit your routine.
In an older building, consider an H01 electrical inspection at HK$770 and a G01 opening-up inspection of supply and waste pipes at HK$930, with photos recording the condition[1]. These checks help you decide how much to reserve for concealed work.
- Inspect the distribution board, pipes, signs of seepage and walls
- Limited offer: free measurement for two or more work items
- Prepare the floor plan and management renovation rules
- Arrange electrical and plumbing checks in older flats
You can swipe left or right on your phone to view the complete table.
| steps | Application stage | time | Owner's responsibilities |
|---|---|---|---|
| 1 | Set priorities and a budget | — | List the essentials and the extras you would like |
| 2 | Measure and inspect the flat | 1 visit | Prepare the plan and renovation rules |
| 3 | Design and prepare drawings | 1–3 weeks | Check sockets, switches and cabinet doors |
| 4 | Review the quote and sign the contract | — | Check each item against the drawings and confirm the warranty |
| 5 | Building management | Before starting work | Apply for permission and pay the deposit |
| 6 | Site protection and strip-out | About 1 weeks | Inspect after strip-out |
| 7 | Plumbing and electrical work | 1–2 weeks | Check services drawings and obtain photos of concealed pipes and wiring |
| 8 | Wet trades and waterproofing | About 2 weeks | Review water-test records |
| 9 | Joinery and ceilings | About 1 weeks | Confirm lighting points and access panels |
| 10 | Painting | 1–2 weeks | Inspect under light from the side |
| 11 | Flooring and furniture | About 1 weeks | Test cabinet doors and drawers |
| 12 | Cleaning and handover | About half a week | Inspect each item and draw up a defects list |
Illustrated for a full 450 sq ft renovation. Exact timing depends on the works programme. [1]

03
Step 3. Design and drawings
After the survey, the designer prepares a proposal for your needs. HK Create DesignBespoke furnitureIncludes design, floor plans, building-services layouts, furniture designs, VR visuals and production drawings.
Floor plans show the layout and furniture. Services plans locate sockets, lights, air conditioning, water and waste points. Furniture drawings show cabinet dimensions and fittings. VR visuals show the proposed finished appearance, and production drawings give the factory its working dimensions.
Design usually takes one to three weeks, depending on revisions. Changes on paper cost less than removing and rebuilding finished work. Take time to settle the layout.
When reviewing drawings, check socket numbers, switch positions, air-conditioner pipe routes, cabinet door clearance and passage widths. These details affect daily use.
- Whole-flat drawings: plans, building services, furniture, VR and production drawings
- Allow one to three weeks for design
- Drawing changes cost least during design
- Check sockets, switches, cabinet doors and passages
- BudgetSet priorities
- Site measurementInspect the flat’s condition
- DesignPrepare whole-flat drawings
- quoteSign a contract
- Building managementApplication
- RemovalProtect the site first
- Plumbing and electrical workConcealed work
- Wet trades and waterproofingflood test
- Joinery and ceilingsaccess panel
- PaintingVentilation
- Flooring and furnitureInstallation
- AcceptanceWarranty
「I tell customers that it is easy to revise a drawing several times. A single change after construction starts can be expensive. Approving the details first can save money.」

04
Step 4. Quotation and contract
The Consumer Council recommends checking the detailed scope, material brands and models, quantities, payment terms and warranty[2]. The quote should allow every item to be checked against the design drawings, with the scope and price clearly stated.
HK Create Design publishes its prices online[1]. Each item has a reference code, quantity, unit price and subtotal. For example, E02 wall preparation and painting is HK$21 per sq ft and J01 SPC flooring is HK$60 per sq ft.
Payments are usually made in instalments against completed work stages stated in the quotation. Avoid paying most of the sum at the outset. Obtain written approval for extra work before it proceeds.
Before signing, agree the start and completion dates, warranty period and scope, how variations are priced and how delays will be handled. HK Create Design provides a one-year warranty. The minimum charge is HK$2,000.
- Check each quoted item against the drawings
- Check itemised figures against the published prices
- Pay in stages and approve variations in writing
- Confirm dates, warranty and delay arrangements
05
Step 5. Notify management and prepare for work
Before starting, apply to building management. Many buildings require a form, deposit, contractor information and insurance copy. Management may specify hours such as 9 am to 6 pm on weekdays and restrict noisy work on Sundays and public holidays.
The Environmental Protection Department publishes domestic renovation noise guidance and asks owners to consider their neighbours[6]. HK Create Design schedules noisy work such as breaking out within the permitted hours and posts a renovation notice in the lift lobby.
Work affecting the structure, partitions, window bays or façade may require Buildings Department approval or procedures under the Minor Works Control System[4][5]. Check these requirements before starting work so that the necessary applications can be made in time.
L02 third-party liability and employees’ compensation insurance for whole-flat works is HK$6,700[1]. Many building managers require a copy of the insurance policy before allowing work to start.
- Apply for renovation permission and pay the management deposit
- Observe the permitted working hours
- Check Buildings Department requirements for structural changes
- L02 insurance, HK$6,700

06
Step 6. Site protection and strip-out
On day one, protect the lift, corridor and entrance with boards and sheeting. Cover items to be retained inside the flat, such as windows and door frames. Good protection reduces damage and disputes.
Strip-out can include old kitchen cabinets, kitchen and bathroom tiles, timber flooring and wardrobes. HK Create Design’s rates include A09 kitchen strip-out and removal HK$9,950, A10 bathroom strip-out and removal HK$9,950, A08 timber flooring removal HK$22 per sq ft and A07 built-in wardrobe removal HK$61 per sq ft[1].
Strip-out produces construction waste. The Environmental Protection Department’s Construction Waste Disposal Charging Scheme charges by weight[7]. A11 debris removal is HK$4,200 per truckload including carrying it downstairs, haulage and lawful disposal[1].
Strip-out often exposes hollow plaster, corroded pipes or cracked floor finishes. Inspect the flat afterwards and agree the next steps with the contractor. Typical strip-out for a 450 sq ft flat takes about one week.
- Put protection in place first
- Kitchen or bathroom strip-out, HK$9,950 each
- Debris removal, HK$4,200 per truckload
- Inspect for hidden defects after strip-out
Example: estimated duration of a full 450 sq ft renovation
Assumptions
- Two-bedroom flat
- Full kitchen and bathroom renovation
- Bespoke furniture
How to calculate quantities
- Strip-out, about 1 week
- Plumbing and electrical work, about 1.5 weeks
- Wet trades and waterproofing, about 2 weeks
- Joinery and ceilings, about 1 week
- Painting, about 1.5 weeks
- Flooring and furniture, about 1 week
- Cleaning and handover, about 0.5 week
- Total about 8.5 weeks
Construction takes about 8.5 weeks, plus one to three weeks for design.
Building time restrictions, hidden defects in an older flat and design changes can extend the programme. [1]
- CorrectPlumbing and wiring, then wet trades, painting and furniture
- IncorrectWiring after painting can mean reopening and repairing chases

07
Step 7. First-fix plumbing and electrical work
Install first-fix plumbing and wiring after strip-out and before plastering and tiling. Electrical work can include a distribution board, wiring, sockets and dedicated circuits. Plumbing can include replacing hot- and cold-water pipes and rerouting waste.
The Electrical and Mechanical Services Department requires fixed electrical installation work to be carried out by registered electrical workers through a registered electrical contractor[8]. The Water Supplies Department website provides details of licensed plumbers[9]. HK Create Design’s prices include H09 distribution board replacement HK$6,800, H06 dedicated circuits HK$3,350 each and G05 kitchen and bathroom supply and waste pipe replacement HK$22,300[1].
After first fix, pressure-test the supply pipes for leaks and photograph concealed service routes. The records can help identify areas to avoid when drilling for pictures or cabinets later.
At this stage, check every socket and light switch against the building-services drawings. Moving them after the walls are closed means opening chases again. Allow around one to two weeks for plumbing and wiring in a 450 sq ft flat.
- Install pipes and wiring before plastering and tiling
- Registered electrical contractor and licensed plumber
- Pressure-test pipes and photograph service routes
- Check against the building-services drawings

08
Step 8. Wet trades and waterproofing
After first fix, carry out plastering, masonry, screeding, waterproofing and tiling. Faulty kitchen or bathroom waterproofing can leak into the flat below and mean removing the new tiles.
C02 bathroom waterproofing costs HK$4,850. It includes the whole floor, walls up to 6 ft, full-height shower walls, two coats of Sika 107 and a 24-hour pond test. C03 kitchen waterproofing costs HK$4,300[1].
For a pond test, close the floor outlet, add 2 to 3 cm of water and monitor the water level and ceiling below for 24 to 48 hours. Wait for a satisfactory test before tiling. Ask the contractor for photos of the test.
D01 floor tiling and D02 wall tiling are HK$78 per sq ft. D04 large-format tiling is HK$120 per sq ft[1]. Check the tiling for level surfaces, straight joints and hollow spots. A hollow sound when gently tapped can indicate a void. Wet trades and waterproofing in a 450 sq ft flat take about two weeks.
- Prioritise kitchen and bathroom waterproofing
- Bathroom waterproofing HK$4,850 including the pond test
- Tile after the waterproofing has passed the water test
- Tap tiles to check for hollow areas
You can swipe left or right on your phone to view the complete table.
| stage | No. | Item | Unit price |
|---|---|---|---|
| Removal | A09/A10 | Strip out and clear the kitchen or bathroom | HK$9,950 per room |
| Plumbing and electrical work | H09 | Replace the distribution board | HK$6,800 |
| Plumbing and electrical work | G05 | Whole-flat kitchen and bathroom supply and waste pipes | HK$22,300 |
| Waterproofing | C02 | Bathroom waterproofing includes a water test | HK$4,850 |
| ceiling | F01 | Gypsum board suspended ceilings | HK$51 per sq ft |
| Painting | E02 | Patch the surface, damp-proof, sand and paint | HK$21 per sq ft |
| floor | J01 | SPC stone plastic floor | HK$60 per sq ft |
| clean | L01 | Cleaning and formaldehyde treatment | HK$16 per sq ft |
HK Create Design’s published prices for 2026. [1]

09
Step 9. Joinery and false ceilings
After the wet trades and once the floor has dried, install false ceilings, lighting troughs and curtain pelmets. A false ceiling can hide air-conditioner pipes and cables and accommodate concealed lighting.
HK Create Design’s F01 metal-framed plasterboard ceiling is HK$51 per sq ft with a 100 sq ft minimum. F03 lighting troughs cost HK$460 per linear foot with a 10 ft minimum. F04 curtain pelmets cost HK$460 per linear foot with an 8 ft minimum. F05 aluminium kitchen or bathroom ceilings cost HK$3,650 per room[1].
Confirm lights, air conditioners and access panels before closing the ceiling. Provide access to the air conditioner and its condensate drain for future servicing.
The factory can produce custom furniture from the approved production drawings at this stage. HK Create Design specifies ENF-grade board as standard. Joinery and ceilings for a 450 sq ft flat take about one week.
- Use a false ceiling to conceal air-conditioner pipes and wiring
- Plasterboard ceiling, HK$51 per sq ft
- Allow service access to air conditioning
- Furniture production runs in parallel at the factory
10
Step 10. Painting
Paint after the false ceilings and before flooring and furniture installation. Choose the preparation to suit the surface. E01 stripping, filling, moisture-resistant preparation, sanding and painting is HK$39 per sq ft for peeling or formerly mould-affected surfaces after the cause is addressed. E02 preparation and painting is HK$21 for largely sound walls. E03 direct repainting is HK$12 for sound finishes[1].
Painting stagesincludes primer, filling, sanding and finishing coats. Filler must dry before sanding, followed by two or three finishing coats. Rushing can cause unevenness, brush marks or blistering.
The Environmental Protection Department notes that paint can release volatile organic compounds. Maintain ventilation during and after painting[10]. Choose low-VOC paint and ventilate the flat for one to two weeks before moving in where possible.
Check painted walls with a torch held at an angle to spot unevenness, brush marks or pinholes. Accept the finish before fitting flooring and furniture. Allow around one to two weeks for painting in a 450 sq ft flat.
- Choose E01, E02 or E03 to suit the wall condition
- Let filler dry thoroughly before sanding
- Low-VOC finishes and good ventilation
- Inspect paintwork under a torch held at a shallow angle
11
Step 11. Flooring and furniture installation
Lay flooring and fit furniture after painting. J01 SPC flooring is HK$60 per sq ft with a 200 sq ft minimum. J02 laminate is HK$82 per sq ft. J04 skirting is HK$10 per linear foot[1].
Furniture generally takes one to three days to fit. HK Create Design manufactures it from production drawings and assembles and finishes it on site. Check door movement and alignment, drawer operation and shelf stability.
Finish by fitting lights, sanitary ware and hardware. H05 pendant or ceiling light installation is HK$670 per light supplied by the owner. K06 full bathroom fitting installation is HK$5,650[1].
Protect new floors during installation and avoid dragging furniture or tools over them. Flooring and furniture in a 450 sq ft flat take about one week.
- SPC HK$60 per sq ft, laminate HK$82 per sq ft
- On-site furniture assembly takes one to three days
- Check cabinet doors, drawers and shelves
- Protect the new flooring
- Sockets and light switchestest each one.
- Tapoperate the taps and check the drains.
- Cabinet doors and drawersopen each one.
- Paintinginspect with a torch.
- floorlisten for unusual sounds.
- Tile surfacecheck for a hollow sound.

12
Step 12. Cleaning, acceptance and warranty
Clean after all work is finished. HK Create Design’s L01 RenoClean Post-renovation cleaningand formaldehyde treatment at HK$16 per sq ft[1]. Carry out formal acceptance after cleaning because dust can hide defects.
At handover, test sockets and light switches, operate each tap and check drains. Open cabinet doors and drawers, inspect paintwork under side lighting, walk over the floor for unusual sounds and tap tiles for hollow spots. List defects and agree a date for the contractor to rectify them.
HK Create Design provides a one-year warranty. During that period, send photos and a description on WhatsApp for follow-up. Keep the quote, design drawings and photos of concealed plumbing and wiring for future repairs.
Open windows for ventilation for one to two weeks before moving in where conditions permit[10], allowing odours from new furniture and paint to dissipate. Households with older people, children or pregnant occupants may wish to allow longer ventilation.
- Cleaning and formaldehyde treatment, HK$16 per sq ft
- Inspect each item and draw up a defects list
- One-year warranty
- Ventilate for one to two weeks before moving in
Example: setting a budget at three levels
Assumptions
- 450 sq ft flat
- Start with an example scope
How to calculate quantities
- Light renovation, about HK$107,110
- Intermediate, about HK$236,890
- Full renovation, about HK$270,980
- Full example × 1.2, including a contingency, = HK$325,176
For the full renovation example, a total budget of about HK$325,176 includes a 20% reserve on the works allowance.
The owner holds the contingency separately. Final prices depend on measurement and the written quotation. [1]
- 8–10 weeksConstruction periodExcluding design
- $270,980Example totalFull renovation
- 1 yearWarrantyAll works
Examples based on HK Create Design's published 2026 rates.

13
Programme for renovating a 450 sq ft flat
For a full renovation of a 450 sq ft flat, allow about one to three weeks for design and 8 to 10 weeks from demolition to cleaning. As a guide: one week for demolition, one to two for plumbing and electrical work, two for masonry and waterproofing, one for carpentry and ceilings, one to two for painting, one for flooring and furniture, and about half a week for cleaning and handover.
Building working hours, hidden defects, material delays, weather and owner-requested changes can all affect the programme. Waterproofing and painting need suitable conditions. A design change can delay subsequent work.
The Labour Department reminds owners and contractors to attend to site safety during repair and alteration works[11]. Rushing can compromise safety and workmanship. Allow a realistic programme. If a tenancy or move-in deadline is fixed, consider starting design two to three months in advance.
- Design takes one to three weeks
- Allow around 8–10 weeks for construction
- Design changes can cause delays
- Allow a realistic construction period
14
Contact HK Create Design for whole-flat renovation
HK Create Design has served Hong Kong homes since 2019. Our team includes designers and tradespeople with over 15 years’ experience, coordinating design, quotation, construction and warranty follow-up. Prices are published online[1], with an itemised quotation showing the charges.
Free site measurement is available for two or more work items until 31 December 2026. Custom furniture includes design and whole-flat drawings. Work carries a one-year warranty and the minimum charge is HK$2,000.
Shop 16, G/F, Fu Yau Building, 61 Po Kong Village Road, Wong Tai Sin, Kowloon. WhatsApp 5243 7747 with a floor plan and photos of the flat for initial advice and a budget range.
- One team coordinates the work
- Prices published online
- Free site measurement for a limited time
- WhatsApp 5243 7747
Advice from our tradespeople
「I tell customers that it is easy to revise a drawing several times. A single change after construction starts can be expensive. Approving the details first can save money.」
「We hand owners photos of concealed pipes and wiring so they can check the routes before drilling or fixing anything later.」
FAQ
9 practical questions answered
01How long does it take to renovate a whole house?
Full renovation of 450 sq ft takes about 8–10 weeks of construction plus one to three weeks of design. An older flat or design changes can extend the programme.
02What is the first step in a whole-home renovation?
Set priorities and a budget, then book a site survey. The 450 sq ft light, intermediate and full examples cost about HK$107,110, HK$236,890 and HK$270,980 respectively[1].
03Why do plumbing and electrical work come first?
Concealed pipes and wiring go into the walls and floor before rendering or tiling. Reversing the sequence requires reopening channels.
04Is water testing needed after waterproofing?
Yes. In this example the contractor closes the floor outlet, adds 2–3 cm of water and monitors the area below for 24–48 hours. C02 bathroom waterproofing includes a 24-hour pond test[1].
05Should painting or furniture installation come first?
Paint first, then install the flooring and furniture to keep paint off the new finishes.
06Does the renovation require an application?
Routine interior renovations generally require a building management application. Work affecting the structure, partitions, window bays or façade may need Buildings Department approval or the Minor Works Control System[4][5].
07What should I check in a quotation?
Scope, material brands and models, quantities, payment terms and warranty[2]. Check each item against the design drawings.
08Can the design change during renovation?
Yes. Changes after work starts can require removal, repairs or rework and increase cost or time. Resolve them during design where possible.
09How long should I ventilate before moving in?
Allow around one to two weeks of ventilation where possible, and consider longer for a home with older people or children. Choose low-VOC paint and ENF-grade board[10].
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]HK Create Design published 2026 rates and work item descriptions Accessed: 2026-11-03
- [2]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-03
- [3]Consumer Council: 4 proposed measures to strengthen regulation of the home renovation industry (21 February 2024) Accessed: 2026-11-03
- [4]Buildings Department — frequently asked questions on alterations and additions in domestic premises Accessed: 2026-11-03
- [5]Buildings Department: Minor Works Control System Accessed: 2026-11-03
- [6]Environmental Protection Department: FAQs on noise from renovation in residential premises Accessed: 2026-11-03
- [7]Environmental Protection Department: Construction Waste Disposal Charging Scheme Accessed: 2026-11-03
- [8]Electrical and Mechanical Services Department: Household Electrical Safety Handbook, new installations, additions and alterations Accessed: 2026-11-03
- [9]Water Supplies Department: Licensed Plumber Accessed: 2026-11-03
- [10]Environmental Protection Department: Indoor Air Quality Information Centre FAQs Accessed: 2026-11-03
- [11]Labour Department: repair, maintenance, alteration and addition works — guidance for owners and tenants Accessed: 2026-11-03