Why preparation before construction matters

The trades depend on earlier decisions. Electricians need socket positions, tilers need tile selections and furniture makers need approved drawings. A late decision can hold up every stage that follows.

The Consumer Council study found that 61% of reported renovation disputes involved delays[2]. A delay is not always the tradesperson’s fault. Often, the two parties did not agree the scope or confirm the materials before the work started, or forgot to allow time for approvals.

Changes are easiest to agree before signing the contract and approving the drawings. Changes on site may mean demolition, repairs and rework. Spending two or three weeks preparing can save construction time and money.

These 30 pre-start checks are grouped under 8 headings. Tick off completed items and follow up the rest with the designer or contractor.

  • Work stages depend on one another
  • Delays accounted for 61% of reported disputes
  • Changes cost least before construction
  • 30 checks in 8 groups
Whole-home renovation on site | HK Create Design
Renovation project photo | HK Create Design Select an image to enlarge

02

Group 1. Quotation, items 1–6

1. List reference codes, quantities, units and unit prices for the scope. 2. Specify what will be removed and what will stay. The Consumer Council recommends identifying items and areas to remove, retain or leave untouched and recording the extent, such as whether to remove the screed beneath floor tiles.[1].

3. Specify exposed or concealed pipes, the pipe material and the valve from which the quoted run begins[1]. Item 4. Specify the rate for each electrical point, including single or double sockets, network points and air-conditioner switches, and whether the existing distribution board will be retained[1].

5. For wet trades and waterproofing, specify measured areas, base and finish materials, waterproofed locations, membrane and height, and testing. Fewer than half the contractors in the Consumer Council survey specified each of the membrane material, its height and whether a water test was included[1]. HK Create Design’s C02 Bathroom waterproofingSpecify the entire floor, wall upstands to 6 ft and full-height shower walls, two coats of Sika 107 and a 24-hour pond test[3].

6. For painting, specify primer and finishing coat counts and whether the existing walls will be stripped[1]. HK Create Design quotes its E01, E02 and E03 paint systems separately and describes the work included[3].

  • Itemised scope and prices
  • List what is to be removed and retained
  • How plumbing and electrical work are priced
  • Waterproofing area, material, height and testing
  • Paint coats and removal of old finishes
Pre-work checklist: summary of 30 items

You can swipe left or right on your phone to view the complete table.

CategoryProject numberKey pointsComplete
quote1–6Itemisation, removal, plumbing, electrical, waterproofing and paint□
Contract7–10Dates, variations, warranty and disputes□
payment11–13Number of instalments, measurable milestones and final payment after acceptance□
Statutory and building management requirements14–17Structure, permissions, working hours and insurance□
Record of existing conditions18–20Flat, common areas and water and electricity meters□
Design and materials21–25Whole-flat drawings, electrical points, tiles, paint and board□
Appliances and sanitary fittings26–27Model, dimensions and who supplies it□
Household arrangements28–30Temporary accommodation, notifying neighbours and ventilation□

Adapted from the Consumer Council’s 12 renovation quotation categories. [1]

Before renovation starts: key figures illustrated | HK Create Design
Before renovation starts: key figures at a glance | HK Create Design Select an image to enlarge

03

Group 2. Contract terms, items 7–10

7. Record the start and completion dates and possible programme risks such as weather, factory delays or transport[1]. The Consumer Council found that only a few contractors in its survey stated the estimated duration in their quotation[1], so ask for clarification and confirm whether the programme includesBespoke furniture.

8. Add variation scope, price, payment terms and completion date to the written quote and obtain approval before starting the extra work[1]. Item 9. State warranty terms and a deadline for rectifying defects[1]. HK Create Design’s work carries a one-year warranty.

10. Agree how delays and disputes will be handled and what happens if either party terminates the contract[1]. If a problem arises, both parties can refer back to these terms.

The Consumer Council recommended a standard quotation template and consideration of a cooling-off period of at least 7 days and alternative dispute resolution[2]. These recommendations can be discussed with your contractor when agreeing the contract terms.

  • Start and completion dates
  • Record variations in writing
  • Warranty and defects rectification deadlines
  • Delays and dispute resolution
HK Create Design・Illustrated overviewEight categories to review before work starts
  1. quoteList each item separately.
  2. Contractin writing.
  3. paymentin 4 instalments.
  4. Building managementpermissions and insurance.
  5. Existing conditionKeep a photographic record.
  6. Designwhole-flat drawings.
HK Create Design・Figures at a glanceConsumer Council payment recommendations
  1. 40%First instalmentNo more than
  2. 4 instalmentsNumber of instalmentsRecommendation
  3. 10%Final instalmentAfter handover and acceptance

Consumer Council information.

「Before site work, we go through the strip-out and retention list with the owner, down to individual hinges, so everyone knows which items must stay.」

Project supervisor, HK Create Design

04

Group 3. Payment, items 11–13

11. Agree the number of instalments and corresponding work stages. The Consumer Council recommends an initial deposit of no more than 40% of the contract value to limit early-stage losses if “Unfinished works” can lead to substantial losses. It cites the Hong Kong Institute of Building Inspectors’ recommendation to pay in 4 instalments[1].

12. Use measurable payment triggers. For example, specify completed wiring and plumbing with the agreed pressure test. A vague milestone such as “30% of works complete” is hard to verify[1]. Inspect the completed stage on site before releasing its payment.

13. Arrange the final payment after inspection and acceptance of the completed works[1]. Draw up a defects list at handover and arrange the final payment after the agreed defects have been rectified.

Custom furniture is made to approved production drawings and usually requires a deposit once the design is confirmed. HK Create Design’s quotation sets out the amount and milestone for each payment so you can compare terms.

  • Keep the first instalment at or below 40%
  • Pay in 4 instalments
  • Link payment to measurable milestones
  • Pay the final balance after acceptance
Consumer Council: common types of renovation disputes(Unit:%)
Project delay
61%
Poor workmanship
39%
Refusal to fix defects
30%

Consumer Council study on home renovation (2024). [2]

Made-to-measure kitchen cabinets and wall units | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge

05

Group 4. Statutory and management requirements, items 14–17

14. Identify any changes affecting the structure, partitions, window bays or façade. The Buildings Department says structural alterations generally require an authorised person and prior approval. Designated work can follow the Minor Works Control System[4][5].

15. Apply to management for permission and check its documents, deposit and insurance requirements. 16. Check the building’s working hours and noise restrictions. The Environmental Protection Department publishes guidance on domestic renovation noise[6]. Building management usually also specifies construction hours.

17. Confirm insurance. The Consumer Council recommends agreeing before work starts who will arrange third-party liability or home renovation insurance[1]. HK Create Design L02 third-party liability and employees' compensation insurance for whole-flat projects: HK$6,700[3].

The Labour Department reminds owners and contractors to consider work safety during repair and alteration projects[10]. Selecting an insured contractor who manages site safety also protects the owner.

  • Check Buildings Department requirements before structural alterations
  • Management application and deposit
  • Working hours and noise
  • Third-party liability insurance

06

Group 5. Existing conditions, items 18–20

18. Photograph or film the flat before work starts, including walls, floors, windows, doors and ceilings. Record existing cracks, stains and damage. A slow video walkthrough with spoken locations can help document a later dispute.

19. Record lift, corridor and lobby conditions. The Consumer Council advises contractors to protect communal areas in advance to limit damage when moving debris[1]. Photograph common areas with management before starting, then compare the condition at completion to avoid deposit disputes. Date the photos and give each party a copy.

20. Record water and electricity meter readings and photograph the distribution board and water stop valve. If temporary power is needed, the Consumer Council recommends applying promptly to avoid delay[1].

  • Photograph and film the flat’s existing condition
  • Photograph the common areas with management
  • Record water and electricity meter readings
  • Apply early for temporary electricity
Worked example 1

Example: working back from a fixed move-in deadline

Assumptions

  • Existing tenancy ends on 30 April
  • Full renovation of a 450 sq ft flat
  • Allow about 9 weeks for construction

How to calculate quantities

  1. Finish on 23 April to allow one week of ventilation before move-in
  2. 9 weeks of construction, starting 19 February
  3. Allow 3 weeks for the contract and management application, signing on 29 January
  4. Allow 4 weeks for design and quotation, starting measurement on 1 January

Start measuring in early January to move in by the end of April in this example.

Allow another two or three weeks for Lunar New Year closures or building management approval where relevant. [3]

Use your square footage instead and see a reference budget
HK Create Design・Illustrated comparisonMaking changes before or after work starts
  1. Before starting workChanging an unapproved drawing usually costs little
  2. After work startsRemoval, making good and rework
Site photo of a completed custom bathroom cabinet | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge
Recording existing conditions before work starts (design rendering) | HK Create Design
Design illustration: Recording site conditions before work starts. The final design follows the site measurements and design drawings. HK Create Design. Select an image to enlarge

07

Group 6. Design and materials, items 21–25

21. Approve the whole-flat drawings. HK Create Design’s custom furniture service includes plans, building-services layouts, furniture designs, VR visuals and production drawings. The Consumer Council also recommends supplying drawings, detailed dimensions, material samples and colours for written approval after the quote is settled[1].

22. Mark each socket, switch, air conditioner and network point on the services drawings. 23. Select tile sizes and styles. Large-format, diagonal or herringbone layouts may cost extra[1]. HK Create Design charges HK$120 per sq ft for D04 large-format tiling and HK$78 per sq ft for D01 straight-laid tiling[3].

24. Choose thePaint coloursand flooring style. Going from dark to light can require another coat. E03 adds HK$4 per sq ft[3]. Item 25. Select furniture board colours, door styles, hardware and handles. The Consumer Council recommends specifying the cost of fittings such as runners and hinges and who supplies them[1].

ENF-grade board is standard at HK Create Design, with formaldehyde emissions ≤0.025 mg/m³. Check samples in daylight and under lamps. If possible, compare a physical sample with your walls and floor in the flat itself.

  • Sign off the whole-flat drawings
  • Check each socket and light switch
  • Tile, paint and flooring colours
  • Board, furniture fittings and handles
Example payment instalments using Consumer Council guidance

You can swipe left or right on your phone to view the complete table.

Number of instalmentsExample 1Example 2Illustrative payment milestones
Instalment 110% booking deposit and 30% further deposit10% booking deposit and 20% further depositSign the contract and start work
Instalment 230%30%Middle stages of the work
Instalment 320%30%Later stages of the work
Final instalment10%10%After handover and acceptance

Recommendation of the Hong Kong Institute of Building Inspectors, cited by the Consumer Council. The parties’ written agreement determines the actual terms. [1]

Project photo of bespoke wardrobes and storage cabinets | HK Create Design
Project photo of bespoke wardrobes | HK Create Design Select an image to enlarge
Selecting materials before work starts (design rendering) | HK Create Design
Design illustration: Choosing materials before work starts. The final design follows the site measurements and design drawings. HK Create Design. Select an image to enlarge

08

Group 7. Appliances and sanitary fittings, items 26–27

26. Select built-in and large appliance models, including the refrigerator, washing machine, oven, dishwasher, cooker hood, water heater and air conditioners. Use model dimensions, ventilation clearances and electrical requirements to plan cabinetry and services.

For example, an electric water heater, induction hob or oven may need a dedicated circuit. HK Create Design’s H06 rate is HK$3,350 per circuit[3]. The Electrical and Mechanical Services Department requires electrical work to be handled by a registered electrical contractor[7]. The cooker hood dimensions determine the width of the wall cabinet. K04 cooker hood installation costs HK$860 per unit[3].

27. Record who supplies the toilet, basin, shower fittings, shower screen and vanity[1]. Arrange for customer-supplied sanitaryware to arrive in advance so that the installer has everything on site. Open the boxes on delivery and check for damage. HK Create Design K06 installation of a complete set of bathroom sanitaryware and fittings: HK$5,650[3]. Have qualified people carry out plumbing work. The Water Supplies Department website provides details of licensed plumbers[8].

  • Appliance models determine cabinet dimensions
  • Check dedicated circuits for high-load appliances
  • Who supplies the sanitary fittings?
  • Arrange early delivery of owner-supplied sanitary fittings

09

Group 8. Household arrangements, items 28–30

28. Arrange the move and temporary accommodation. A 450 sq ft full renovation typically takes eight to ten weeks and the flat is generally uninhabitable. Move out or store existing furniture and keep valuables in your possession.

29. Notify neighbours. Put a notice in the lift lobby with dates and a contact number and speak to adjacent residents about noise and dust. If the flat below hasOlder residentsor babies, ask whether any periods particularly need to be quiet and try to schedule noisy work around them.

30. Arrange cleaning and ventilation before move-in. The Environmental Protection Department notes that new paint and furniture can release volatile organic compounds. Maintain ventilation after completion[9]. HK Create Design’s L01 RenoClean Post-renovation cleaningand formaldehyde treatment at HK$16 per sq ft[3]. Allow one to two weeks of ventilation before moving in where possible.

  • Arrange temporary accommodation and the move
  • Post a notice and speak with neighbours
  • Allow time for ventilation
  • Cleaning and formaldehyde treatment
Consumer Council: main concerns of people who commissioned renovations(Unit:%)
Unfinished or abandoned works
73%
Poor workmanship
61%
Contractor becomes unreachable after taking payment
59%

Consumer Council study on home renovation (2024). [2]

HK Create Design・Work sequenceCountdown to the start of work
  1. 6–8 weeksMeasure and design
  2. 4–6 weeksFinalise drawings and compare quotations
  3. 2–4 weeksSign the contract and submit applications
  4. 1–2 weeksMove the furniture and take photos
Preparing the home before renovation (design rendering) | HK Create Design
Design illustration: Preparing the home before renovation begins. The final design follows the site measurements and design drawings. HK Create Design. Select an image to enlarge

10

What to do and when before work starts

6–8 weeks before work. Set the budget, book a survey and begin design. 4–6 weeks before work. Approve drawings, compare quotes and select appliances. 2–4 weeks before work. Sign the contract, make the first payment, apply to management and select tiles and paint colours.

1–2 weeks before work. Move out furniture, photograph existing conditions, record meters, display notices and confirm insurance. On the first day, protect common areas and walk through the flat with the contractor to confirm what stays and what goes. Colour-code items to retain so each trade can identify them.

If you have a move-in deadline, such as the end of an existing tenancy, consider starting preparations three to four months beforehand.Whole-flat renovationoften takes longer than expected. Time contingency is as important as a cost contingency. Allow for factory and trade closures around Lunar New Year, Christmas and other long holidays.

  • Begin design 6–8 weeks before work
  • 2–4 weeks for signing and applications
  • 1–2 weeks for moving furniture and taking photos
  • Work back three to four months from a fixed deadline

11

5 things commonly overlooked before starting

1. Air conditioning. Choosing a unit after the pipe and power routes are fixed may mean drilling into newly painted walls. Agree models, indoor unit positions and pipe routes before site work.

2. Network and TV points. Plan router placement and the data outlets required in each room before construction. H03 additional twin socket, TV or network point is HK$1,200 per point[3].

3. Curtains. Coordinate pelmets and tracks with false ceilings and painting. F04 curtain pelmets cost HK$460 per linear foot, minimum 8 ft[3]. If you decide after moving in, a surface-mounted track may be the only option. Curtain style also affects pelmet depth. Allow more room for double tracks carrying sheers and blackout curtains.

4. Robot vacuum and vacuum cleaner storage. Allow clearance under cabinets, a charging point and suitable plinth height. 5. Lighting. Pendant and ceiling fixtures need suitable wiring and support. Recessed spotlights need cut-outs. Confirm dimensions early for owner-supplied lights.

  • Air-conditioner pipe routes and power supply
  • Network and TV points
  • Curtain pelmet and track
  • Robot vacuum and lighting
Worked example 2

Example: calculating payments using Consumer Council guidance

Assumptions

  • Total works price HK$270,980
  • Example 2 uses 4 instalments

How to calculate quantities

  1. Instalment 1, 30%: HK$81,294
  2. Instalment 2, 30%: HK$81,294
  3. Instalment 3, 30%: HK$81,294
  4. Final 10%: HK$27,098
  5. Total: HK$270,980

Initial payment up to 40%, with the balance after acceptance.

Illustration only. The actual instalments and amounts depend on the written quotation and agreement. [1][3]

Use your square footage instead and see a reference budget
Before renovation starts: checklist illustrated | HK Create Design
Before renovation starts: checklist | HK Create Design Select an image to enlarge

12

10 questions to ask the renovation contractor before signing

1. Who will oversee the works, and who should you contact about a problem? 2. Which trades are directly employed and which are subcontracted? How will quality be checked? 3. Does the programme include custom furniture production? The Consumer Council found that some contractors excluded the time for custom joinery[1].

4. How will progress be reported? Will you receive photos? 5. If hidden corrosion or hollow plaster is found, how will the contractor notify you, price the change and obtain approval before proceeding?

6. Does the price include both labour and materials? Are there extra installation charges for tiles or fittings that you supply? The Consumer Council says many quotations exclude finishing materials and recommends clarifying this[1]. 7. Does cleaning cover the whole flat or only part of it? Is formaldehyde treatment included? The Consumer Council found that few contractors specified the scope of cleaning[1].

8. How long is the warranty, what does it cover and how are faults reported? 9. How will debris be removed and are government construction waste disposal charges included?[1] 10. Can you see previous project photos or customer reviews?

Record the answers to these 10 questions in the quote or contract so both parties can refer to them later. HK Create Design’s quote sets out the scope, materials, cleaning, waste removal, insurance and warranty.

  • Who is responsible for follow-up?
  • Does the programme include furniture production?
  • How will hidden defects be managed?
  • Labour and materials included or supplied by the owner
  • Warranty and debris disposal
  • Record the answers in the quotation

13

Ask HK Create Design to help prepare for the work

HK Create Design has served Hong Kong households since 2019. Our team includes designers and tradespeople with over 15 years’ experience. Each quotation lists reference codes, quantities and unit prices, and our prices are published online[3], helping you check each item against Consumer Council recommendations.

A limited offer provides free site measurement for two or more work items until 31 December 2026. Custom furniture includes design, whole-flat drawings and VR visuals. Work carries a one-year warranty and the minimum charge is HK$2,000.

Shop 16, G/F, Fu Yau Building, 61 Po Kong Village Road, Wong Tai Sin, Kowloon. WhatsApp 5243 7747 with your move-in date and flat details. We can work back to a pre-start programme and provide a checklist.

  • Itemise the quotation
  • Prices published online
  • Whole-flat drawings and VR visuals
  • WhatsApp 5243 7747

Advice from our tradespeople

「Before site work, we go through the strip-out and retention list with the owner, down to individual hinges, so everyone knows which items must stay.」

Project supervisor, HK Create DesignHK Create Design project team

「Appliance models often arrive late. A refrigerator just two centimetres wider can affect the whole tall unit, so we ask for the model before designing.」

Head of Design, HK Create DesignHK Create Design team

FAQ

10 practical questions answered

01How much should I pay as an initial renovation deposit?

The Consumer Council recommends an initial payment of no more than 40% of the contract sum and cites the Hong Kong Institute of Building Inspectors’ suggestion of 4 instalments[1].

02When should I pay the final balance?

Pay after acceptance and completion of agreed defect repairs[1].

03What waterproofing details should the quote specify?

Waterproofed locations, material, membrane height and testing[1]. For example, C02 specifies the whole floor, a 6 ft wall upstand and a 24-hour pond test[3].

04How are later additions to the work handled?

Record the price, terms and completion date of a variation in the written quotation before it starts[1].

05How soon before starting should I begin preparation?

Start the design 6–8 weeks before construction. With a fixed move-in deadline, work backwards three to four months.

06Do I need insurance for the renovation?

The Consumer Council recommends confirming before work starts who will provide third-party liability insurance[1]. HK Create Design’s L02 whole-flat works insurance costs HK$6,700[3].

07Why take photographs of the existing condition?

Photos of the flat and common areas establish the original condition and help avoid disputes over damage and deposits.

08Does the quote include the finish materials?

Ask explicitly. The Consumer Council found that most quotations surveyed excluded finishing materials. HK Create Design identifies supply arrangements, for example J01 SPC includes materials and installation, while K05 shower screen installation is labour only[1][3].

09What if hidden problems emerge during renovation?

Pause work, tell the owner and photograph the issue. Obtain a written quotation for the addition before proceeding. A 20% planning contingency can reduce the need for last-minute borrowing.

10When should I finalise the appliances?

Select built-in and large appliances before approving the design, so that furniture dimensions and electrical circuits can suit the models.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-03
  2. [2]Consumer Council: 4 proposed measures to strengthen regulation of the home renovation industry (21 February 2024) Accessed: 2026-11-03
  3. [3]HK Create Design published 2026 rates and work item descriptions Accessed: 2026-11-03
  4. [4]Buildings Department — frequently asked questions on alterations and additions in domestic premises Accessed: 2026-11-03
  5. [5]Buildings Department: Minor Works Control System Accessed: 2026-11-03
  6. [6]Environmental Protection Department: FAQs on noise from renovation in residential premises Accessed: 2026-11-03
  7. [7]Electrical and Mechanical Services Department: Household Electrical Safety Handbook, new installations, additions and alterations Accessed: 2026-11-03
  8. [8]Water Supplies Department: Licensed Plumber Accessed: 2026-11-03
  9. [9]Environmental Protection Department: Indoor Air Quality Information Centre FAQs Accessed: 2026-11-03
  10. [10]Labour Department: repair, maintenance, alteration and addition works — guidance for owners and tenants Accessed: 2026-11-03