01

Why older flats may need repiping

Unlined galvanised steel was once common in Hong Kong. As it corrodes, water left standing can turn yellow. Serious corrosion may require replacement. WSD stopped allowing new use of these pipes on 23 December 1995.[2]

WSD notes that corrosion can restrict the pipe bore and reduce water pressure.[4] Discoloured water, low flow and repeated leaks in an older home may indicate ageing pipework beyond a single fitting.

Our standard specification uses copper for new drinking-water pipes throughout the flat.Older flat renovationKitchen and bathroom strip-out is a convenient point to renew the pipes.

  • Yellow discolouration in water
  • Weak water pressure
  • Frequent leaks
  • Replace during renovation
Room strip-out and ceiling plastering at a flat in Tai Kok Tsui
Site photo: a stripped-out room in an older building being prepared for revised plumbing and cable routes. Select an image to enlarge

02

Steps 1–2: assessment and application

1. Check the pipe materials and routes, meter and valve position, valve condition and number of outlets. Where investigation is necessary, G01 supply/waste opening-up costs HK$930 per item including a photo report and local repair.[9]

2. Determine whether consent is needed. Alterations to an inside service generally require the Water Authority's written permission. Work of a minor nature must satisfy all five conditions, including the restriction on soft-soldered copper joints.[5][6] Where an application is required, the licensed plumber submits WWO 46 Parts I and II. Wait until Part III is issued before starting those works.[1]

Our partner licensed plumber handles the application. While approval is pending, work independent of the water installation, such as measuring or agreed strip-out, can proceed.

  • Identify the pipe materials
  • Check that the stop valve closes fully
  • Determine whether an application is needed
  • Wait for Part III before starting
Pipe replacement sequence in an older building

You can swipe left or right on your phone to view the complete table.

Application stageWhat is it for?Pay attention toIndicative time
1. Inspect and measureCheck pipe material, meter and outletsG01 opening-up inspection includes a photographic report [9]According to site arrangements
2. Apply for approvalThe licensed plumber submits WWO 46 Parts I and II where requiredFor work requiring approval, start after Part III is issued [1]Case by case
3. Pretreat fittingsCopper-alloy fitting pretreatmentChange the water daily and keep the container covered [1]5 days [1]
4. Strip outStrip out kitchen, bathroom and tilesProtect common areasDepends on scope
5. Cut service chasesMark routes and cut chasesDo not embed pipe runs lengthwise in structural members [3]Depends on scope
6. Lay copper pipesNew hot and cold water pipesParallel new and existing runs are preferred where practicable [1]Depends on scope
7. Pressure-testPressure testing before wall closurePressure-test and record the result as directed by the licensed plumberBefore closing the wall
8. Disinfect and flushFlush after free-chlorine disinfectionAt least 30 ppm for at least 30 minutes [1]Minimum 30 minutes
9. Make goodRender, waterproof and tileC02 bathroom waterproofing includes a 24-hour flood test [9]Depends on scope
10. Final inspectionFinal inspection and water sampling, where approval appliesNotification within seven working days of Part IV [1]See the published figures

Only the published WSD times are fixed reference points here. Confirm the remaining on-site stages in the written programme. [1][3][9]

Pipe replacement stages: key figures illustrated | HK Create Design
Pipe replacement stages: key figures at a glance | HK Create Design Select an image to enlarge

03

Step 3: fitting pretreatment

WSD specifies a five-day soak for new fittings with copper-alloy internal surfaces that contact drinking water. Keep the containers covered and replace the water daily.[1] The purpose is to reduce metal release from fittings into drinking water.

Start the five days of pretreatment alongside demolition where possible. Waiting until the chases are complete can leave the installers waiting for fittings.

WSD requires pipes and fittings for the water installation to have prior approval from the Water Authority. Approved products can be supported by a General Acceptance letter.[7]

  • Order fittings in advance
  • Pretreat fittings during demolition
  • Change the water daily and keep covered
  • Use approved fittings

「Whole-flat repiping may take a few days to two weeks, depending on chasing and approvals. Coordinate the mason and electrician so routes can be opened and reinstated in one sequence.」

Plumbing Supervisor, HK Create Design
New floor screed and wall render after bathroom tiles were removed
Site photo: levelling a bathroom floor. Pressure-test the pipes before waterproofing and tiling. Select an image to enlarge

04

Steps 4–6: strip-out, chasing and copper pipework

Protect shared corridors and lifts during strip-out and clear debris daily. Mark routes and confirm that the proposed chases avoid structural members. The English guide prohibits embedding pipes lengthwise in structural elements. Pipes may run in plaster or screed, with sleeves at approved penetrations through floors, beams or walls.[3]

WSD recommends laying new pipes alongside the old where practicable and removing the old after the new supply is ready. Where this cannot be done, consider replacement in the same position.[1] In a vacant flat, pipes can be replaced in the same positions. In an occupied home, run new and old systems alongside one another where practicable to limit outages.

The guidance generally specifies 20 mm as the minimum pipe diameter. A branch serving a single outlet and no more than 3 m long may be 15 mm.[3] Copper pipe and fitting brands we use include Wednesbury, Kembla (KemPress), Lawton, OTTO and OPAL.

  • Protect common areas
  • Keep longitudinal pipe runs out of structural members
  • Sleeve approved wall penetrations
  • Size the pipes to the applicable requirements
Official time periods in the pipe replacement process(Unit:day)
Copper-alloy fitting pretreatment
5 days
Notification after Part IV
Within 7 working days
Final inspection target for at least 70% of cases
Within 14 working days

Source: WSD Guide to Application for Water Supply, October 2026. Distinguish working days from calendar days when planning. [1]

05

Steps 7–8: pressure testing, disinfection and flushing

Pressure-test before concealment. Our G-series plumbing items include pressure testing. The licensed plumber sets the appropriate test and records the readings and times, with photographs.[9]

After a satisfactory pressure test, the licensed plumber disinfects and flushes the system. The repair procedure cited specifies at least 30 ppm free residual chlorine with at least 30 minutes of contact, followed by thorough flushing.[1] Soft-soldered joints may also require WSD-witnessed non-destructive lead-content testing under the applicable procedure.[1]

Connect taps and sanitaryware after flushing. Clients choose the fixtures and we charge for installation, e.g. K02 basin and tap installation at HK$1,150.[9]

  • Pressure testing before wall closure
  • Record the readings
  • Disinfect and flush
  • Then fit taps and sanitaryware
New white storage-type electric water heater mounted above the shower in a small bathroom, with neatly arranged pipes
Illustration: a new white electric storage water heater above the shower in a compact bathroom, with neatly arranged pipework. HK Create Design. Select an image to enlarge

06

Step 9: making good, waterproofing and tiling

Complete the pipes before rendering and waterproofing. Our bathroom waterproofing item C02 Bathroom waterproofing is HK$4,850 including a 24-hour flood test. Kitchen waterproofing (C03) is HK$4,300.[9]

Tiling before the services are complete can lead to breaking out new work. Our teams complete and test services and waterproofing before laying tiles.

G02 includes local render repairs to its chases. Extensive additional reinstatement can be priced using B06 mason daywork at HK$2,700 per day.[9]

  • Complete the pipework before waterproofing
  • Tile after the flood test
  • Reinstate the pipe chases
Worked example 1

Example 1: pipe replacement schedule in a full renovation of an older two-bedroom flat (hypothetical)

Assumptions

  • Assumption: vacant flat, with the kitchen and bathroom fully stripped out.
  • Assumption: the work requires an application and Part III has already been issued.
  • Assumption: the fittings go into pretreatment on the first demolition day.

How to calculate quantities

  1. Example days 1–3: strip out the kitchen and bathroom (A09 and A10).
  2. Days 1–5: soak the applicable copper-alloy fittings during the first five days. [1]
  3. Example days 4–7: cut chases and install copper pipework. Pretreated fittings become available from day 6.
  4. Example day 8: pressure-test and record readings, disinfect for the specified contact time (at least 30 minutes in this example), then flush. [1]
  5. Example day 9 onwards: render, waterproof, complete the 24-hour flood test and tile.
  6. WSD issues the notification within seven working days of receipt of Part IV under the applicable procedure. [1]

In this example, repiping falls within roughly the first two weeks of renovation. Final inspection needs additional time.

Days are illustrative and show sequence only. Timing depends on scope, approval and coordination with other trades. [1]

Use your square footage instead and see a reference budget
Site photo of floor channels for pipework at Yat Man House, Ho Man Tin Estate | HK Create Design
Project photograph: plumbing at Yat Man House, Ho Man Tin Estate, May 2026, HK Create Design Select an image to enlarge

07

Step 10: final inspection and handover

For applicable works the licensed plumber submits Part IV after completion. WSD notifies and arranges the appointment within seven working days. With satisfactory checklists submitted on time, it aims to conduct at least 70% of inspections within 14 working days from the appointment being made.[1]

In occupied buildings, the sampling procedure includes at least 30 minutes of stagnation. Acceptance criteria include lead at or below 10 µg/L and turbidity at or below 3.0 NTU. Part V(b) follows satisfactory results under the applicable procedure.[1]

At handover, obtain pipe-route photographs, pressure-test and flood-test records, and Water Supplies Department application documents where applicable.

  • Submit Part IV
  • Final inspection
  • Water sample passes
  • Handover documents

08

Reducing disruption while living in the flat

Water outages are the main disruption in an occupied flat. The WSD guide covers temporary drinking-water arrangements, including a metered temporary supply, an appropriate filtration arrangement or bottled water.[1] For occupied flats, consider a phased kitchen-then-bathroom sequence, with supply restored at the end of each working day where practicable.

Before an outage, check that the stop valve closes properly. WSD advises closing the stop valve beside the meter promptly if a leak develops.[8] Deal with a corroded main stop valve before starting.

Phasing can extend the job and multiply making-good visits. Allow for additional mason daywork.

  • Work in phases
  • Restore water daily where practicable
  • Prepare bottled water
  • Check the stop valve first
Replacing pipes in a vacant or occupied flat

You can swipe left or right on your phone to view the complete table.

compareVacant flat, complete renovationOccupied flat, local or phased works
Application stageStrip out, replace and reinstate in one sequenceWork in stages and restore supply after each section
Water supply interruptionLess disruptionAgree outage times in advance
Temporary drinking waterUsually unnecessaryTemporary drinking water may be required [1]
Handling old and new pipesLike-for-like replacement in the same position is possiblePrefer a parallel new run, removing the old one after commissioning [1]
CostOpening routes during the kitchen and bathroom strip-out reduces extra chasingRepeated work and making good

Typical comparison. Confirm the arrangements after site assessment. [1]

09

The cost of sequencing mistakes

1. Tiling first means removing new tiles for pipework. 2. Forgetting the fitting pretreatment can delay installation. 3. Beginning work needing WSD permission before Part III is issued.[1] 4. Closing walls before pressure testing. 5. Replacing only kitchen and bathroom branches while a corroded incoming pipe continues to discolour the water.

6. Treating a common pipe fault as a problem inside one flat. WSD identifies management or the registered agent as responsible for common pipes, pumps and tanks.[4] 7. Failing to photograph concealed routes can lead to a pipe being drilled through later.

Planning the sequence early costs less than remedial work.

  • Install pipework before tiling
  • Allow time for pretreatment
  • Start after permission is granted
  • Pressure testing before wall closure
  • Photograph the pipe routes
Site photo of bathroom cabinet and sanitaryware installation | HK Create Design
Site photo of a bathroom renovation | HK Create Design Select an image to enlarge

10

What WSD requires during pipe replacement

WSD guidance covers parallel new and old pipe runs where practicable, temporary drinking water, fitting pretreatment, testing for lead in soft-soldered joints, disinfection and water sampling.[1]

WSD identifies corroded plumbing and poorly maintained roof tanks as common causes of yellow or cloudy water. Persistent or severe discolouration should be assessed by a licensed plumber, who can replace corroded pipes where necessary.[4]

The requirements vary by project. Use them to discuss the proposed scope with the contractor.

  • Run old and new pipes alongside one another
  • Temporary drinking water
  • Pretreating fittings
  • Disinfection and water sampling
Worked example 2

Example 2: kitchen and bathroom demolition with whole-flat repiping and waterproofing

Assumptions

  • One kitchen and one bathroom, both stripped out completely.
  • Replace kitchen and bathroom supply and waste pipes and renew waterproofing in both rooms.
  • Tiling, tiles and kitchen cabinets are extra.

How to calculate quantities

  1. A09 kitchen strip-out HK$9,950 + A10 bathroom strip-out HK$9,950 = HK$19,900. [9]
  2. G05 whole-flat supply and waste pipe replacement, kitchen and bathroom: HK$22,300.
  3. C02 bathroom waterproofing HK$4,850 + C03 kitchen waterproofing HK$4,300 = HK$9,150.
  4. Total: HK$19,900 + HK$22,300 + HK$9,150 = HK$51,350.

Indicative combined subtotal for strip-out, repiping and waterproofing: HK$51,350.

Tiling, cabinetry, sanitaryware, painting and reconstruction of concealed runs are extra. Confirm the written quote after measurement. [9]

Use your square footage instead and see a reference budget

11

Coordinating repiping and rewiring

Older flat renovationPipe replacementandRewiringRepiping and rewiring often run together. Mark routes and organise chasing in one visit where possible. Keep the water pipes and electrical conduits separate and avoid locating sockets directly above water pipes.

Typical sequence: strip out, mark water and electrical routes, form chases, install pipes and conduits, pressure-test and test circuits, make good, waterproof, tile, then fit sanitaryware and switches. Electrical work needs inspection and testing. Our H01 inspection item is HK$770.[9]

In combined jobs, our teams use one coordinated services drawing and photograph the pipes and conduits before concealment. See our rewiring guide for electrical details.

  • Mark out and cut chases at the same stage
  • Keep water pipes and electrical conduits on separate routes
  • Use the same coordinated services drawing
  • Photograph the routes before closing walls

12

Estimating the duration for different scopes

For one or two points, G01 investigation plus G02 relocation can be a relatively short local job.[9] Work of a minor nature can proceed without this application. Where permission is needed, wait for Part III.[2][1]

One room: G03 or G04 can run alongside a kitchen or bathroom renovation. Coordinate repiping with strip-out and waterproofing. C02 bathroom waterproofing includes a 24-hour flood test, so allow at least a day for that test.[9]

Whole flat: G05 covers kitchen and bathroom supply and waste pipe replacement. Add strip-out, waterproofing and tiling. Use the written programme and allow for WSD inspection where applicable. The notification target is seven working days. Where satisfactory checklists are submitted on time, WSD aims to inspect at least 70% of cases within 14 working days of making the appointment.[1]

  • Local work: shorter programme
  • Kitchen or bathroom: coordinate with the room renovation
  • Whole flat: allow for final inspection
Records to obtain after each stage

You can swipe left or right on your phone to view the complete table.

Application stageevidenceWhy does it need
InspectionPhotographs of opened areas and pipe materialsDecide between local and whole-flat replacement
ApplicationCopy of WWO 46 Part III [1]Check approval before starting
Install the pipesPhotographs of pipe markings and routesAvoid concealed pipes during future work
pressure testPressure-test photographs and recordsCheck for leaks before concealment
WaterproofingFlood-test recordsC02 includes a 24-hour flood test [9]
AcceptanceCopies of Part V(a) and V(b) [1]Confirm satisfactory completion

Work of a minor nature has no WWO 46 paperwork. Still retain the other photographs and test records. [1][9]

13

What the owner needs to do during the work

Notify management, register the renovation under building rules, protect shared areas and check the main stop valve. WSD advises closing the stop valve beside the meter promptly if a leak occurs.[8]

During the work, request photos after each stage, particularly the routes before concealment and the pressure-test records. If remaining in the flat, confirm outage dates and prepare drinking water.

At completion, run every outlet, check the first draw in the morning and observe pressure with two taps open. Where approval is required, allow for WSD inspection and sampling. Keep photos and records. During our one-year workmanship warranty, send photos of any issues for follow-up.

  • Notify building management before starting
  • Request photographs at each stage
  • Test each outlet at completion
  • Keep the documentation
Renovated small Hong Kong bathroom with large light grey tiles, a glass shower enclosure, wood-grain vanity and LED-lit mirror
Illustration: renovated compact Hong Kong bathroom with large light-grey tiles, a glass shower enclosure, wood-effect vanity and LED mirror. HK Create Design. Select an image to enlarge

14

Design decisions before repiping

Decide the position and height of the sink, washing machine, water heater, filter, WC, basin and shower before closing the walls. G02 lists HK$1,700 per hot/cold water point relocation,Toilet relocation G07 from HK$9,300.[9]

Confirm cabinet and vanity dimensions so outlets clear the cabinet panels. Set the shower height for the users and allow space for dual heads. Coordinate the heater with its electricity or gas supply. See the water-heater replacement guide.

At measurement we go through the fixture positions with the owner, include them in the quotation and confirm them again before work.

  • Confirm each outlet location
  • Confirm kitchen and vanity dimensions first
  • Shower height
  • Water-heater position
Worked example 3

Example 3: day-work budget for making good chased channels

Assumptions

  • The living room and corridor need extra chases outside the making good included in G02.
  • Assumption: two days of mason's work.

How to calculate quantities

  1. B06 mason on daywork: HK$2,700/day. [9]
  2. 2 days × HK$2,700 = HK$5,400.

Indicative additional making good: HK$5,400.

Days are illustrative. Extra making good depends on the walls and chase extent. G02 already includes local render repairs. [9]

Use your square footage instead and see a reference budget
Project photo of kitchen cabinet installation | HK Create Design
Project photo of bespoke kitchen cabinets | HK Create Design Select an image to enlarge
Pipe replacement stages: checklist illustrated | HK Create Design
Pipe replacement stages: checklist | HK Create Design Select an image to enlarge

15

What to monitor in the first months

Small bubbles may briefly make newly drawn water look cloudy. WSD says milky water that clears as bubbles disperse is generally caused by air. Persistently discoloured water needs investigation.[4]

Monitor new damp patches, dripping joints and meter movement when all outlets are off. For a leak, shut the stop valve and contact us. Our one-year workmanship warranty excludes deliberate damage.

Check the concealed route photos before installing shelves, mounting a television or drilling later.

  • Check the water colour in the morning
  • Look for damp patches on walls
  • Check the meter periodically
  • Check the route photos before drilling

16

Arranging repiping with HK Create Design

HK Create Design opened in 2019. Our team brings 15 years of project experience and can coordinate repiping, waterproofing,Masonry and tilingWe coordinate repiping with the older flat's renovation. Our partner licensed plumber handles WSD applications. The one-year workmanship warranty excludes deliberate damage.

For a free quotation from a construction team, contact HK Create Design on WhatsApp 5243 7747. The Wong Tai Sin showroom opens Monday to Saturday, 10:00–18:00. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.

  • WhatsApp 5243 7747
  • Book a site measurement

Advice from our tradespeople

「Whole-flat repiping may take a few days to two weeks, depending on chasing and approvals. Coordinate the mason and electrician so routes can be opened and reinstated in one sequence.」

Plumbing Supervisor, HK Create DesignHK Create Design project team

「Complete the pressure test and confirm there are no leaks before concealment. Reopening a finished wall adds substantial cost.」

Partner Licensed Plumber, HK Create DesignHK Create Design's partner plumbing contractor

「We notify clients and neighbouring occupiers of planned outages and aim to restore supply within the working day.」

Project Manager, HK Create DesignHK Create Design project team

FAQ

11 practical questions answered

01How long does repiping an older flat take?

It depends on scope and submissions. Official timings include five days for fitting conditioning and notice within seven working days after Part 4. Confirm other dates in the written programme.[1]

02What are the stages of pipe replacement?

Inspection, application, fitting conditioning, removal, chasing, copper pipe installation, pressure testing, disinfection and flushing, reinstatement and acceptance.

03Will the water need to be turned off for pipe replacement?

Yes. A vacant flat can be done in one operation. In an occupied flat, phase the work and arrange a temporary drinking water supply.[1]

04Which comes first, repiping or waterproofing?

Replace the pipes first. Once pressure testing passes, waterproof and flood-test, then lay the tiles.

05Why do fittings need five days of soaking?

Water Supplies Department guidance calls for soaking copper-alloy fittings for five days before installation, changing the water daily and covering the container.[1]

06Do pipes need disinfection after replacement?

Yes. The guidance requires at least 30 ppm free chlorine for a minimum of 30 minutes, followed by flushing.[1]

07How much does whole-flat pipe replacement cost?

HK Create Design G05 whole-flat replacement of kitchen and bathroom supply and drainage pipes is HK$22,300 including pressure testing. Concealed pipe reconstruction is quoted separately.[9]

08Can pipes be concealed in the walls?

Pipes can run in render or screed, but not lengthwise within structural members. Sleeves are required where pipes pass through walls or slabs.[3]

09Can pipes be replaced while I live in the flat?

Yes. Work is usually phased with the water supply restored before the team leaves each day. Allow extra time.

10How soon after repiping does the acceptance inspection take place?

For works requiring application, the Water Supplies Department aims to carry out final inspection within 14 working days for at least 70% of cases, provided the checklist is submitted on time.[1]

11Which pipes does HK Create Design use?

We use copper for all drinking water pipes, with Pegler and Tectite/ENDEX fittings, rather than galvanised iron.

CHECK THE BASIS

Data and technical basis, sources can be verified

  1. [1]Water Supplies Department: Guide to Application for Water Supply (October 2026 edition) Accessed: 2026-11-03
  2. [2]Water Supplies Department: Water Facts Accessed: 2026-11-03
  3. [3]Water Supplies Department: Guide to Application for Water Supply (January 2025) Accessed: 2026-11-03
  4. [4]Water Supplies Department: water supply problems in private estates and buildings and maintenance of inside service systems Accessed: 2026-11-03
  5. [5]Water Supplies Department: Employing a Licensed Plumber Accessed: 2026-11-03
  6. [6]Water Supplies Department: Minor works Accessed: 2026-11-03
  7. [7]Water Supplies Department: Make Smart Choices of Pipes and Fittings (General Acceptance, GA) Accessed: 2026-11-03
  8. [8]Water Supplies Department: Advice on unusually high water consumption Accessed: 2026-11-03
  9. [9]HK Create Design 2026 detailed project budget and public price list Accessed: 2026-11-03