01
What sections 14 and 15 cover
Section 14 of the Waterworks Ordinance generally requires prior written permission from the Water Authority to construct, install, alter or remove an inside service. A licensed plumber can apply on the owner's behalf. Carrying out work without required permission is an offence.[1]
Section 15 reserves specified plumbing works to designated persons, including licensed plumbers, registered or provisionally registered plumbing workers, persons working under the required instruction and supervision, and authorised public officers. Provisions for works of a minor nature also apply.[1]
Section 14 addresses permission. Section 15 sets out who may undertake the work.Pipe replacementwork must meet both sets of requirements.
- Section 14: written permission
- Section 15: designated persons
- A breach is an offence

02
Five concurrent conditions for work of a minor nature
WSD's minor-nature guidance gives five conditions for these works: unchanged use, no conversion from indirect to direct supply, no meter removal, no soft-soldering of copper joints and no need for a backflow prevention device.[2]
WSD examples include replacing pipes or fittings inside a flat, repairing leaks, adding valves and extending pipework to serve a new draw-off point.[2] Many in-flat replacements using push-fit or press-fit fittings may qualify where all the other conditions are met.
Exemption from an application does not remove product or workmanship requirements. The pipes and fittings must meet WSD requirements and the system should be pressure-tested.
- All five conditions must be met
- Soft soldering fails the criterion
- Removing a meter falls outside the criteria
- Materials must still comply
You can swipe left or right on your phone to view the complete table.
| Condition | Example meeting the criteria | Example outside the criteria |
|---|---|---|
| No change of use. [2] | Replace a kitchen cold-water pipe in its existing position | Change a domestic supply to commercial use |
| No conversion from indirect to direct supply [2] | Retain the existing supply arrangement | Change to direct supply from the street main |
| No removal of the water meter [2] | Replace only pipes downstream of the meter serving the flat | Move or remove the water meter |
| No soft-soldered copper pipe joints [2] | Use push-fit or press-fit fittings | Make a tin-based soft-solder joint in copper pipe |
| No backflow prevention device required [2] | Typical kitchen and bathroom outlets | Connection requiring a backflow prevention device |
For the in-flat examples described by WSD, all five conditions must be met. Examples include replacing pipes or fittings, repairing leaks, adding valves and extending a pipe to a new outlet. Ask the licensed plumber to assess the work against the Water Authority's criteria. [2]

03
WWO 46 from application to issue of Part V
Where an application is needed, the licensed plumber submits WWO 46 Parts I and II with WWO 1149. Start only after the Water Authority grants permission and issues Part III.[3]
On completion the licensed plumber submits Part IV. Under the stated procedure, WSD issues a notification and books final inspection within seven working days. Selected soft-solder joints undergo non-destructive lead testing. Part V(a) follows satisfactory inspection.[3]
Submit the laboratory water report to WSD. Part V(b) follows once the acceptance criteria have been met.[3] Where permission is required, wait for Part III before starting and complete the inspection stages before accepting the job as finished.
- Wait for Part III before starting
- Part IV: completion notice
- Part V(a): satisfactory final inspection
- Part V(b): water quality accepted
「Check whether the proposed pipework qualifies as minor in nature. A licensed plumber may need to apply to WSD before pipes are replaced or moved.」

04
Documents and information for the owner to prepare
The licensed plumber completes and submits the form. Owners normally provide property details, proof of ownership or authorisation and the necessary signatures. Confirm exact requirements with the plumber and WSD.
At the survey, we inspect pipe and meter positions and identify permission requirements in the quote. After you place the order, our licensed plumbing partner prepares the application and we handle the arrangements with WSD.
Verify the responsible plumber in WSD's online Register of Licensed Plumbers.[1]
- Provide the required flat details
- Sign the required documents
- Verify the licensed plumber online
- Keep a copy of the application
05
Soft soldering, lead tests and water samples
WSD strengthened control of inside services in August 2015, including checks on soft-soldered joints and lead in drinking water.[4] Under the guide, selected soft-soldered joints undergo non-destructive lead testing witnessed by WSD. For a completed section, a tested new joint and photo record can support a request for temporary resumption of supply. An exception applies to the specified integral solder-ring fittings.[3]
After installation, the plumber disinfects and flushes the system under the applicable procedure. The cited chlorine method uses at least 30 ppm free residual chlorine and at least 30 minutes' contact.[3] Before water sampling, allow at least 30 minutes of stagnation in an occupied building and six hours in an unoccupied building. Collect metal samples first.[3]
Soft soldering can affect permission, testing and timing. Specify the jointing method before accepting the quote.
- Lead testing for selected soft-soldered joints
- Disinfect and flush the system
- Stagnation period before sampling
- Specify the jointing method in the quote

06
Application and inspection timings
WSD's published timing distinguishes notification from inspection. It issues the notification within seven working days of receiving Part IV under the applicable procedure. With a satisfactory checklist within seven working days of notification, its target is to inspect at least 70% of cases within 14 working days of making the appointment.[3]
The time to obtain Part III depends on the case. Apply early and coordinate the plumbing programme with strip-out, masonry and waterproofing.
In an occupied flat, ask about temporary water. The guidance favours installing new pipes alongside ageing ones before removing the old where practical, with temporary drinking-water arrangements.[3]
- Allow time for permission
- Allow roughly a month after site completion for inspection planning
- Arrange temporary water
Example 1: which of three jobs requires an application?
Assumptions
- Case A: replace one kitchen cold-water copper pipe in place with push-fit fittings.
- Case B: replace all bathroom pipework using soft-soldered copper joints.
- Case C: move the water meter.
How to calculate quantities
- Case A: use and supply arrangement unchanged, meter retained, no soft solder, no backflow device required. All five conditions are met and the work may qualify. [2]
- Case B: soft solder fails the fourth condition. The work is outside this minor-nature category and requires permission. [2]
- Case C: meter removal fails the third condition, so permission is required. [2]
Permission for a pipe replacement depends on scope and jointing method.
The licensed plumber assesses the actual work against WSD requirements. Even exempt minor-nature work must meet the relevant product and installation standards. [2]

07
Common misunderstandings about WSD applications
1. Replacing pipes inside a flat can still require permission. Soft-soldered copper joints fall outside the minor-nature criteria.[2] 2. Experience alone is insufficient for specified plumbing work. Engage the appropriate designated person.[1] 3. The licensed plumber submits the application. The owner provides the required information and signatures.
4. Permission is only the start. Completion requires Parts IV and V and the applicable water quality checks.[3] 5. Communal pipes, pumps and tanks are managed by the building management or registered agent. Arrange work through them.[5]
6. Upstream pipework and the meter are not automatically the individual owner's to alter. WSD maintains the meter and the consumer must protect it. Meter removal is outside the minor-nature category.[5][2]
- Soft soldering requires permission
- Work undertaken by a designated person
- Application submitted by a licensed plumber
- Inspection follows the physical works
- Refer communal pipework to the responsible party
08
How can I confirm the application and inspection are complete?
For work subject to the full procedure, Part V(b) confirms the relevant final inspection and water sample results have been accepted.[3] Owners can ask the licensed plumber for copies of the relevant documents.
Pressure-test before enclosure, photograph the routes and run every outlet. Our G items all include pressure testing.[7]
Minor-nature work has no Part V certificate under this process. Keep pressure-test records, photographs and receipts.
- Copy of Part V(b)
- Pressure test records
- Wiring route photos
- Receipt
You can swipe left or right on your phone to view the complete table.
| stage | Who carries out the work? | content |
|---|---|---|
| Parts I and II with WWO 1149 | licensed plumber | Submit the application and work details. [3] |
| Part III | Water Authority | Wait for permission before starting. [3] |
| Part IV | licensed plumber | Notify on completion. WSD issues its notification within seven working days under the stated procedure. [3] |
| Final inspection | Water Supplies Department | Includes non-destructive lead testing of selected soft-soldered joints. [3] |
| Part V(a) | Water Authority | Issued after a satisfactory final inspection. [3] |
| Laboratory report | Arranged by the licensed plumber | Submit the laboratory water report to WSD. [3] |
| Part V(b) | Water Authority | Issued once all requirements are met. [3] |
Based on WSD's Guide to Application for Water Supply, October 2026 edition. Follow WSD's requirements for the specific project. [3]
09
WSD guidance on work to an inside service
For work subject to the statutory procedures, obtain permission, use the required designated persons and specify compliant materials.[1] Enhanced controls cover General Acceptance of pipes and fittings, lead testing of selected soft-soldered joints and testing of drinking-water samples.[4]
WSD provides a register where owners can check a licensed plumber's details.[1][6] This gives the owner a straightforward check.
Our licensed plumbing partner handles required applications. HK Create Design coordinates the overall works and submissions.
- Permission granted
- Designated person
- Compliant materials
- Check against the register

10
How to budget for the submission and the work
Our published rates: G05 kitchen and bathroom supply and drainage replacement HK$22,300, G04 complete bathroom HK$13,300, G02 hot or cold point relocation HK$1,700 per point, G07 Toilet relocation From HK$9,300.[7]
For work requiring permission, we specify the application arrangements in the written quote after site measurement. For detailed cost examples, seePipe replacement pricesguide. For the scope of our service, see the pipe replacement page.
- Put the submission arrangements in the quotation
- Read the pipe replacement cost guide
Example 2: time from completion to final inspection under an assumed schedule
Assumptions
- Assume the work requires permission, Part III has been issued and site work is finished.
- Assume the licensed plumber submits Part IV on the completion date and the inspection checklist by the required deadline.
How to calculate quantities
- Under the stated procedure, WSD issues the notification and books the final inspection within seven working days of receiving Part IV. [3]
- WSD aims to carry out final inspections in at least 70% of qualifying cases within 14 working days of making the appointment. [3]
- Illustrative programme: 7 + 14 = 21 working days, or a little over four weeks before allowing for public holidays. The actual inspection date may differ.
- The water sample results must also be submitted. Part V(b) follows once the acceptance criteria have been met. [3]
For replacement work requiring permission, allow roughly a month in the programme from site completion to final inspection, subject to WSD's arrangements.
The target covers at least 70% of cases. WSD arranges actual dates and this example is for planning only. [3]
11
Examples: permission or work of a minor nature?
Replacing kitchen hot and cold pipes in place using push-fit fittings may qualify where the use and supply arrangement are unchanged, the meter stays, no soft solder is used and no backflow device is required.[2] Even where a kitchen relocation requires extending the pipes, it may qualify if the conditions are met. WSD includes extending pipework to add a draw-off point among its examples.[2]
Full bathroom replacement using traditional tin-based soft solder involves soft-soldered copper joints and falls outside the minor-nature category. Apply for permission.[2] Allow time for lead testing and inspection too.[3]
Moving a meter or converting an indirect supply to a direct connection from the street main falls outside the minor-nature category.[2] The work may also involve communal areas. Discuss it with management first.
For a water filter or heater, the jointing arrangement and need for a backflow prevention device affect classification. At the survey, we check with the licensed plumber and record the arrangement in the quote.
- In-place replacement with push-fit fittings may qualify as minor in nature
- Soft soldering: permission required
- Moving the meter requires an application
- Assess filters and water heaters individually
12
Licensed plumbers and registered plumbing workers: the difference
WSD says specified plumbing work may be carried out by a licensed plumber, a registered plumbing worker, a provisionally registered plumbing worker or someone working under their instruction and supervision as applicable.[1] A licensed plumber submits the request for written permission on the owner's behalf.[1]
The licensed plumber is responsible for the submission and the work. Registered plumbing workers can carry out site work within their permitted role. Check the licensed plumber in WSD's register.[6]
Our licensed plumbing partner handles applications and inspections. We coordinate site work with the other trades so owners have a single contact for plumbing, masonry and waterproofing.
- A licensed plumber handles the application
- A registered plumbing worker may undertake site work
- Check the online register
- One point of contact coordinates the work
You can swipe left or right on your phone to view the complete table.
| parameters | Acceptance criteria | parameters | Acceptance criteria |
|---|---|---|---|
| Turbidity | ≤3.0 NTU | Lead | ≤10µg/L |
| Colour | ≤5 Hazen | Chromium | ≤50µg/L |
| pH | 6.5–9.5 | Nickel | ≤70µg/L |
| Free residual chlorine | ≤1.5mg/L | Cadmium | ≤3µg/L |
| Conductivity | ≤500µS/cm | Copper | ≤2000µg/L |
| Heterotrophic plate count | ≤20 cfu/mL | Antimony | ≤20µg/L |
| Escherichia coli (E. coli) | 0 cfu/100mL | — | — |
Before sampling, allow at least 30 minutes' stagnation in an occupied building and at least 6 hours in an unoccupied building. Collect metal samples first. [3] [3]
13
What the owner needs to do during the application
1. Sign the documents and provide flat details. 2. Arrange access for WSD's final inspection and water sampling. For a sample in an occupied building, avoid water use for at least the required 30-minute stagnation period.[3]
3. For soft-soldered joints, a tested new joint and photo record for each completed section may support an application for temporary resumption of supply.[3] Occupants may need a temporary supply before all testing is complete. Agree arrangements in advance.
4. Keep copies of all documents, including Part III permission and Parts V(a) and V(b). They may be needed on a future sale,Flat inspectionor a later renovation.
- Sign the documents
- Arrange access for inspection
- Stagnation period before sampling
- Keep copies

14
Applications for public rental, Home Ownership Scheme and private flats
Pipe replacement within a private flat is subject to the Waterworks Ordinance. Where required, a licensed plumber applies to WSD.[1] Also observe the deed of mutual covenant and management rules on registration and working hours.
Public rental and some Home Ownership Scheme flats have Housing Authority or estate rules in addition to WSD requirements. Certain work needs estate office consent first. We check the position at the site visit.
An individual owner cannot independently alter communal or upstream pipework. Contact building management or the owners' corporation to establish responsibility and arrange the work.[5]
- Private flats: WSD requirements and the deed of mutual covenant
- Public rental and Home Ownership Scheme flats: check estate rules first
- Arrange work on communal pipes through management
Example 3: budget for bathroom repiping and toilet relocation
Assumptions
- Replace the complete set of hot and cold pipes in the bathroom.
- Relocate the WC and reroute its drain.
- Our licensed plumbing partner handles submissions. Tile removal, waterproofing and tiling are extra.
How to calculate quantities
- G04 Complete bathroom hot and cold water installation: HK$13,300. [7]
- G07 Move the WC and reroute the drain: from HK$9,300.
- Total: HK$13,300 + HK$9,300 = HK$22,600 and up.
Indicative plumbing cost from HK$22,600.
Assess WC relocation on site. The waste pipe is a drainage item separate from the supply pipework, but both need coordination. Refer to the written quote. [7]


15
If WSD requests more information
The licensed plumber follows up any request for clearer drawings or additional material data. Provide the required owner information and signatures promptly.
If the installation fails inspection or the joint lead or water sample results exceed the limits, carry out the required rectification and retest.[3] Use compliant materials and carry out the required flushing and disinfection to reduce the risk of rework.
We report application progress alongside the site programme so owners know which stage has been reached.
- Provide additional information promptly
- Rectify and retest if a requirement is not met
- Compliant materials reduce rework
- Track progress
16
Arrange WSD application support through HK Create Design
HK Create Design opened in 2019 and the team has 15 years' project experience. We use copper for drinking-water pipework and coordinate WSD submissions through our licensed plumbing partners. A one-year workmanship warranty excludes deliberate damage.
For a free quotation from a construction team, contact HK Create Design on WhatsApp 5243 7747. The Wong Tai Sin showroom opens Monday to Saturday, 10:00–18:00. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.
- WhatsApp 5243 7747
- Book a site measurement
Advice from our tradespeople
「Check whether the proposed pipework qualifies as minor in nature. A licensed plumber may need to apply to WSD before pipes are replaced or moved.」
「We allow for approval and inspection when scheduling the plumbing and coordinate the other trades around those dates.」
「Keep the records to document compliance if the property is sold or a neighbour reports seepage later.」
FAQ
11 practical questions answered
01Does pipe replacement always require an application to the Water Supplies Department?
Not always. Alteration of an inside service generally requires written permission. The five conditions govern the minor-nature exemption for the in-flat work described.[1][2]
02Which jobs count as works of a minor nature?
Examples include replacing pipes or fittings in the flat, repairing leaks, adding valves or extending to a new outlet, subject to all five conditions.[2]
03Do soft-soldered copper joints require permission?
Yes. Soft-soldered copper joints fall outside the in-flat minor-nature exemption described.[2]
04Can the owner submit the application personally?
A licensed plumber generally submits the application on the owner's behalf.[1] Our licensed plumbing partner handles the submission, coordinated by HK Create Design.
05What is WWO 46?
WWO 46 is the inside service application and completion form. Parts I–V cover the application, permission, completion, inspection and acceptance of water quality.[3]
06How long after completion does inspection take place?
Under the stated procedure, WSD issues a notification within seven working days of receiving Part IV. A satisfactory checklist submitted on time qualifies for the target of final inspection in at least 70% of cases within 14 working days of making the appointment.[3]
07Will water samples be tested at handover?
Yes. For occupied buildings, examples of acceptance criteria include lead ≤10 µg/L and E. coli at 0 CFU/100 mL.[3]
08What happens if pipes are replaced without applying?
Breach of section 14 is an offence.[1] It may also affect subsequent inspection and insurance.
10Do I need to submit the application for the building's communal pipe?
Building management or the registered agent handles communal water pipes, pumps and tanks.[5]
11How are application costs priced?
We set out the application arrangements in the written quote after site measurement.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]Water Supplies Department: Employing a Licensed Plumber Accessed: 2026-11-03
- [2]Water Supplies Department: Minor works Accessed: 2026-11-03
- [3]Water Supplies Department: Guide to Application for Water Supply (October 2026 edition) Accessed: 2026-11-03
- [4]Water Supplies Department: enhanced control of inside services Accessed: 2026-11-03
- [5]Water Supplies Department: water supply problems in private estates and buildings and maintenance of inside service systems Accessed: 2026-11-03
- [6]Water Supplies Department: Licensed Plumber Accessed: 2026-11-03
- [7]HK Create Design 2026 detailed project budget and public price list Accessed: 2026-11-03