1. Identify the job: replace a fitting, repair a leak, add an outlet or alter the system?
The most inaccurate first step is to call all work "water pipe modification". Just changing the toilet, faucet or wash basin does not necessarily require moving the original water supply and drainage; when adding a washing machine, dishwasher or bathtub, you need to check the location of new water intake points, water outlet connections, valves, cabinets and appliances; when moving the toilet or relocating the kitchen and toilet, you will also have to deal with branch pipes, risers, floors, waterproofing, plans and management rules. Start by writing down every piece of equipment you want to keep, remove, and add so your quote starts from the same list.
The Buildings Department explained that general repairs or replacements of sanitary equipment are exempt from approval, but must still meet relevant standards including drainage. If any changes are made to the drainage pipes related to toilets, bathrooms or kitchens, the Buildings Department must be notified before the start of the project and/or after completion in accordance with the minor works control system, and a prescribed registered contractor must be appointed to perform the construction and properly lay the waterproof layer.[1] Therefore, "replacing sanitary ware" and "borrowing sanitary ware to change drainage" cannot be treated with the same assumption.
The requirements can be divided into four columns: water supply, water removal, waterproofing, and surface restoration. Each column asks three more questions: where to start, where to end, and how to prove completion. In this way, even if you finally decide to only do partial repairs, you will know which column has been excluded, instead of just receiving a "fixed" sentence.
- List all sanitary ware and appliances that have been retained, removed, relocated and added, with model number or size.
- Use floor plans or photos to mark the water meter, main switch, branch switch, floor drain, existing water outlet and visible standpipe.
- Divide "Treat the source of water leakage" and "Repair damaged finishes" into two quotatable items.
02
2. What to gather before measurement so the quotation can use actual details
The photo should have both a close-up lens and an ambient lens. The close-up lens can take pictures of the corner valve at the bottom of the cabinet, the water drain of the wash basin, the bottom of the toilet, the floor drain, the air extraction position and any water marks; the ambient mirror can take pictures of the entire kitchen or toilet, allowing people to see how far apart the cleaning utensils are and the position of the door and cabinet. If there is a persistent odor or water seepage, record the date of occurrence, whether it only occurs after showering, the affected location downstairs, and any repairs that have been made. The information can help with segmented inspections better than a photo of a damp wall.
Simultaneously find out the approved unit plans, management office renovation regulations, deeds of mutual covenant and old maintenance orders. The Buildings Department recommends that owners check the approved plans and minor works records at the early stage of design to understand the structural layout, kitchen fire-resistant construction, room separation and drainage facilities; they should also check whether there are any additional restrictions in the deed of mutual covenant and the management company.[1] This step is not a formality: the wall or door enclosing the kitchen may have structural or fire-resistant functions, and changes in the location and area of the kitchen should not be judged solely by general renovation quotes.
The company offers the following arrangement. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. Online estimates and enquiries are free.[5] Before measuring, please send the area, photos, project location, whether people live in it, and the items you want to keep. This will allow the on-site work to focus on feasibility and quantity verification, rather than interpreting the measurement as a confirmed project price.
- Prepare approved plans, management office rules, water leakage or odor records, and receipts for repairs done.
- Measure or mark the basic dimensions of kitchen cabinets, bathroom cabinets, sanitary ware, window sills and doorways.
- Ask the management office in advance about the construction period, lifts, protection, common areas, water sealing and deposit arrangements.
You can swipe left or right on your phone to view the complete table.
| demand situation | Quantity/position to confirm before measuring | The company’s 2026 public pricing method | Known not included or other items to be negotiated | Homeowner Decision Risks |
|---|---|---|---|---|
| Drilling inspection at designated locations | Which wall, floor or cabinet location; can the finish be restored? | G01 by project, HK$930 | Actual pipe alterations are charged separately | Just doing an inspection does not mean that all leaks have been found; ask for photos and a summary of findings first. |
| Add or move a hot and cold water level | New location, original control position, exposed or concealed pipe, wall finish | G02 by bit, HK$1,700 | Special restoration conditions other than slotting and new wiring must be verified on site | It's the same "bit", but the distance, interfaces and repairs can be very different. Don't treat the unit price as the total price. |
| Install hot and cold water pipes throughout the bathroom | The respective positions of showers, toilets and wash basins and whether the original pipes are retained | G04 According to the project, the price is HK$13,300, and the test pressure is listed | Rebuilding concealed pipework and cutting new chases are by separate agreement | It is necessary to distinguish whether the water supply is connected to the sanitary ware, or whether it has been connected to water diversion, waterproofing, brickwork and sanitary ware materials. |
| The toilet was moved and the water was diverted | The central location of the old and new toilets, the conditions of the floor, the relationship between the branch pipes and the riser pipes that can be connected | G07 According to the project, starting from HK$9,300, quotation will be made after on-site assessment | Brick removal, waterproofing, sanitary ware or restrictions other than actual floor repairs cannot be assumed to be covered | Dewatering changes involve drainage systems and procedures, and you cannot just choose the lowest price based on the distance moved. |
| Bathroom waterproofing | Actual area of floor, ceiling, shower seat, pipes and wall tiles | C02 room is about 30 to 40 square feet, HK$4,850 | If it exceeds 40 square feet, it will be charged as C01; tiles and sanitary ware are not included in this item. | The 24-hour water shut-off included in the price list is within the scope of the company's projects and is not the statutory unified testing hours for all Hong Kong projects. |
The table uses only HK Create Design's October 2026 standard items to explain per-point, per-item and per-room pricing. It is neither a market average nor a formal quotation. The Consumer Council also advises identifying where plumbing prices start, whether pipes are exposed or concealed, whether pricing is by length or room, and the pipe and fitting specifications. [3][5]

03
3. Procedures and personnel: indoor work still needs checking
When it comes to structural walls, beams, columns, floor openings or other structural changes, the Buildings Department points out that the owner must appoint an authorized person and a registered structural engineer to assess, submit the drawings and obtain approval and consent before it can be carried out by a registered contractor.[1] This decision falls outside plumbing work alone. If the project also involves electricity, gas,Aluminium windows, external walls or demolition, state any specialist appointments and responsibilities in the quotation. A single plumbing total can obscure work by other trades.
Regarding water supply, the Water Supplies Department explained that the construction, installation, alteration or dismantling of internal water supply systems in principle involves the written permission of the Water Authority and a designated person; only if the alteration or repair is minor in nature, the permit may be exempted or non-designated persons may be allowed to carry out it. The department also listed conditions, such as not changing the purpose of water supply or direct/indirect water supply method, not dismantling or reinstalling water meters, not involving soldering copper pipes and not requiring backflow prevention devices.[2] This means that "adding one more space" does not necessarily automatically equal the same procedure. The actual concept should be left to a licensed plumber or the Water Supplies Department to clarify as necessary.
The contractor is required to list in writing who will verify the procedures, who will submit the required documents, who will be responsible for notifying the management office, and when the trenches will be sealed or paved. This is information on the division of labor, not a legal conclusion for individual units; if you have any questions, you should check directly with the relevant departments or qualified persons.
- If there are questions about the structure, floor slab, kitchen location or fire-resistant separation, the decision to demolish and modify the building shall be suspended first.
- Ask which water-supply works require a licensed plumber or an application, and whether the work qualifies as being of a minor nature.
- Include management approval, construction period, and document responsibilities in the pre-construction checklist.
04
4. Supply planning: check valves, routes and maintenance access before choosing taps
The water supply design should show the main and branch valves, hot and cold connections to each fixture, what each local valve isolates, and whether concealed joints will remain accessible. Ask for indexed photos of routes, valves and joints before enclosure. These records will help when tracing a cabinet leak or replacing a tap.
If the quotation states "a complete set of hot and cold water pipes", it must be listed one by one whether the shower head, toilet, wash basin, zinc basin, washing machine or water heater are included. According to the company's public price list, the standard item for a complete set of hot and cold water pipes in the toilet is HK$13,300, including showers, toilets, washbasin water supply and pressure test, but underground pipe reconstruction and wall cutting are separately negotiated.[5] This just shows that the same name does not mean the same boundary; it is the company's price list, not the Hong Kong market average.
When adding a new washing machine or dishwasher, also check water supply, drainage, electricity, appliance instructions and cabinet modifications. Although the Water Supplies Department's minor works page lists examples of extending an existing water supply pipe to supply an additional washing machine, dishwasher or water filter in the same dwelling, it is still subject to the conditions stated therein.[2] Do not use an online diagram to connect or modify pipes by yourself.
We use copper, not galvanised iron, for fresh water pipes. Common brands are Wednesbury (distributed by CYH, BS EN 1057), Kembla (Kempress), LAWTON, OTTO and OPAL. Fittings include Pegler (Pegler Yorkshire) and Tectite/ENDEX push-fit, compression and silver-brazed fittings. We select certified pipes and fittings meeting Water Supplies Department requirements. Our partner licensed plumber replaces fresh water pipes and we handle department applications. Clients usually choose sanitaryware and taps, and we charge separately for installation labour.
- Mark each new water point and its hot and cold water needs on the map.
- Request a quote stating whether each valve, angle valve, hose, connection and pressure test is included.
- Save the dated photos of the route before sealing and mark the locations for future inspections.
Example one: itemising a hypothetical bathroom renovation into a verifiable subtotal
Assumptions
- This is a calculation demonstration, not a completed case, construction commitment or official quotation by our company.
- Assuming a toilet of about 35 square feet, the total tiled area of the wall and floor is assumed to be 200 square feet.
- This example uses the company's published October 2026 items only: A10 strip-out at HK$9,950, G04 complete bathroom hot and cold pipework at HK$13,300, C02 waterproofing at HK$4,850, D01/D02 tiling labour and bedding materials at HK$78 per sq ft, and K06 sanitaryware and hardware installation at HK$5,650.
How to calculate quantities
- Tiling subtotal: 200 sq ft × HK$78 = HK$15,600.
- Total: HK$9,950 + HK$13,300 + HK$4,850 + HK$15,600 + HK$5,650 = HK$49,350.
- By listing the applicable scope and uninclusive items of each item separately, you cannot rewrite HK$49,350 as "toilet all-inclusive".
Based on the above pure assumptions and public standard price, the subtotal of the project is HK$49,350; this is only to show that plumbing, waterproofing, tiling and installation can be checked separately, and is not the average price in the Hong Kong market.
Excludes client-selected finishes such as tiles and sanitaryware, management deposits and fees, extra rubble removal, insurance, replacement concealed pipes, new wall chases, special substrates, associated procedures and defects found after strip-out. Confirm actual areas, routes and applicable items in a written quote after measurement. [5]
05
5. Drainage, traps and odours: trace the system before masking the smell
Slow water removal does not necessarily mean that the entire pipe needs to be replaced; nor does the odor just mean that the floor drain is aging. Water seals, drainage connections, branch pipes, anti-siphon arrangements and public parts of toilets, washbasins, bathtubs or floor drains may affect the results. The Buildings Department reminds that when modifying or removing unit drainage systems, including anti-siphon pipes, appropriate registered contractors should be appointed in accordance with the minor works control system; each sanitary equipment should have effective water seals, such as air traps with anti-siphon facilities.[1] Therefore, removing seemingly redundant pipe fittings or sealing connections may transfer the problem from the surface to the wall.
When dealing with odors, first note whether it is long-term, intermittent, or only occurs after a certain piece of sanitary ware is drained. If the floor drain has been without water for a long time, the water seal may have dried up. However, if there is a persistent odor, abnormalities in the drain outlet or back siphon pipe, water seepage or cracks in the drain pipe, the Buildings Department recommends arranging for inspection and repair by a qualified contractor as soon as possible.[1] These observations will help arrange inspections, rather than requiring homeowners to dismantle or connect drain pipes themselves.
Be especially careful when moving toilets. The company's public price list lists "restroom relocation with water diversion" as starting at HK$9,300, and requires on-site assessment and quotation.[5] The word "start" reflects that it is not a fixed answer: the new and old location, floor conditions, accessible branch pipes, drainage modification procedures, waterproofing and surface restoration will all change the scope.
- Record when the odor or backflow occurs and after using which sanitary ware.
- It is required to clarify the lines of responsibility for branch pipes, public risers and visible anti-siphon related parts within the unit.
- For toilet relocation, first ask for feasibility and procedural opinions, and then compare the subsequent sub-projects.

06
6. Waterproofing scope: specify the substrate, pipe penetrations, materials and testing
The waterproofing quotation depends on the location rather than just a name: is the whole platform or part of it? How to deal with the wall-to-floor interface? How to strengthen the shower position and pipe location? How to measure the height of the wall? To what base layer should the original bricks be removed before they are redone? The Consumer Council recommends that the quotation specify the waterproofing location, materials, height of the waterproofing layer and leakage test.[3] By writing these items close to the price, it is easier to avoid discovering after completion that both parties have different understandings of "waterproofing".
If the contractor recommends SikaTop®-107 Seal HK, it should be regarded as a verifiable specified product rather than the only option available. Sika Hong Kong describes this product as a two-component polymer-modified cement-based waterproof slurry. It lists the usage areas such as bathrooms, toilets, terraces, etc., and states that for general waterproofing purposes, at least two layers should be applied; the actual dosage will be affected by the roughness, thickness and construction scope of the base layer.[6] These product data do not replace an on-site grassroots assessment, nor do they automatically guarantee the absence of leaks. When using other products, the product information, construction scope and compatibility information of the current version should also be required.
In the company's 2026 price list,Bathroom waterproofingThe standard item covers one room of approximately 30 to 40 sq ft and specifies a 24-hour flood test. A separate flood test item allows 24 to 48 hours.[5] That is the company's project description, not the unified testing hours stipulated in Hong Kong laws. Before each test, the water sealing method, observation location, who will take the photos, when bricks can be laid, and how to deal with abnormalities should be confirmed before the project.
- The quotation lists the waterproofing location, area or height, full product name, base treatment and pipe closing.
- Before testing, confirm the water level or method, start and end time, shooting location, and processing procedures after problems are discovered.
- Do not cover the relevant locations with bricks or permanently seal them before confirming the test results and photos.
You can swipe left or right on your phone to view the complete table.
| What the owner wants to do | Quantity/current situation to be recorded | The calculation method that should be used for quotation | Don't assume it's included | Risks that should be addressed first |
|---|---|---|---|---|
| Only replace the toilet, faucet or wash basin | Model, water inlet and outlet connections, existing switches and cabinet space | By piece or set, list who supplies the sanitary ware and who installs it | Old valves, hidden leaks, wall and floor tile repairs or changes to the drainage system | Although the replacement of sanitary equipment is generally exempt from approval, it must still comply with drainage and other relevant standards. |
| Add a washing machine or dishwasher water point to an existing kitchen | Location of new appliances, existing water supply branch pipes, drain connections, and whether backflow prevention devices are required | Listed by new water intake points, valves, cold water and moisture removal items | Procedures for electricity, cabinet openings, appliance supply, and non-minor works | The Water Supplies Department sets out the conditions for minor works; if they are not met, the application must be processed by a licensed plumber. |
| Rebuild a toilet | Floor and wall area, list of sanitary ware, water routes, and shower area | Quantity of items including demolition, water supply, water removal, waterproofing, tiling, and installation of sanitary ware | Facing tiles, sanitary ware, management office fees, dump trucks, insurance or concealment issues | Modification of relevant drainage pipes must be handled in accordance with the minor works supervision system, and waterproofing arrangements must be made. |
| Move the toilet or reposition the kitchen and toilet | Approval of plans, locations of risers and branch pipes, platform height differences, and common part boundaries | Conduct a feasibility assessment first, and then list the feasible scope and subsequent processes in writing. | Structural, fire-resistant partitions, utility pipes, floor slabs or complete restoration works | The location and structural/fire resistance requirements of the kitchen cannot be inferred based on the renovation concept; check the plans, deed of mutual covenant and management rules first. |
| Persistent odor or water leakage downstairs | Time of occurrence, water usage, status of water meters and gates, photos and affected locations | Quote inspection, segment testing, patching and recovery separately | The permanent effect is guaranteed after only repairing the glue or replacing the floor drain. | First, separate the water supply, drainage, waterproofing and public parts. If there is odor or water seepage, it is recommended to arrange for inspection by a qualified contractor. |
This table is not a conclusion of procedure or law. Its function is to allow different contractors to respond based on the same set of data, reducing the need to mix "replacement", "additional seats" and "modification of the system" into one total price. [1][2][3][5]
07
7. Compare quotations by verifiable scope as well as total price
Each contractor is required to quote based on the same list of sanitary ware, floor plans and photos. For water pipes, it is especially important to ask whether the starting point is the first gate switch after entering the house, the stratified water meter switch position, or an existing interface; whether it is an open pipe or a concealed pipe; whether it is calculated per square foot, per location, per space, or as a whole; and the specifications and sources of fittings and pipes. This is exactly the information that the Consumer Council has listed as being clearly stated in the water pipe quotation.[3] If a quotation does not include quantities, unit prices or sub-items, a lower total price does not necessarily mean the same range.
Demolition, plastering, protection, repair, tiles, sanitary ware, management office deposits and handling fees, insurance, night or holiday arrangements should all be placed next to the corresponding processes. Do not fill in the unknown unit price with zero, and do not understand "work and material included" to mean the fabric is included. The company's public price list clearly states that many finishing materials, management office fees, etc. are not included by default; the actual project is still subject to the official quotation.[5]
Payment terms should also be linked to verifiable processes, rather than just vague percentages. The Consumer Council cited recommendations that the deposit should preferably not exceed 40% of the total project cost, and there should be clear payment criteria for each installment. It is better to pay the final amount after completion of inspection and acceptance.[3] This is consumption information rather than a legal fixed ratio for all contracts; the start, change, execution, completion and termination arrangements in the contract should be confirmed in writing by both parties.
- Each column lists quantity, unit of measure, unit price, subtotal, material, labor, test, and recovery.
- Other items are not included and their confirmation methods are not included, and "to be determined" is not used to replace all information.
- If any problems are discovered after relocation, additions or demolition, the scope, price and construction period must be clearly stated in writing before proceeding.
08
8. How to use the online estimate without mistaking it for a whole-flat package
Enter saleable area for three quick examples: basic whole-flat renovation, repainting and floor tiling. Of 117 work items and options in 8 categories, 116 have reference unit rates and 1 rooftop package needs a quotation.[5] This is to sort out demand first and does not mean that every unit will use all items, nor should it be described as the average renovation price in Hong Kong.
The quick basic whole-flat estimate explicitly excludes complete kitchen and bathroom rebuilds, replumbing and rewiring,Bespoke furnitureand tile finishes. Saleable area × 3 estimates paintable area without measuring the walls and ceiling on site. The optional 20% is a planning allowance, not an additional fee.[5] Water pipe projects cannot be directly deduced from the usable area, because the starting location, number of sanitary ware, exposed or concealed pipes, water diversion, and wall and floor restoration will all affect the scope.
Start with a free online estimate based on area and a scheme. Add or remove items in the detailed calculator, then take the results, drawings and photos to the site assessment for verification. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. WhatsApp enquiries: 52437747.[5] Before making a formal quotation, the project scope, materials, payment, management arrangements and uninclusive items should be clearly checked.
- Think of a quick estimate as a list of requirements and don’t forward it as a “quote” or “all-inclusive package.”
- After seeing the pre-filled quantity by area, change it item by item to the quantity of kitchen, toilet, sanitary ware and actual route.
- After downloading or saving the preliminary list, request a formal quote listing the changes after on-site verification.
Example two: measuring water supply routes before estimating cost when no per-metre rate is available
Assumptions
- This is a measurement demonstration of a fictitious floor plan. It is not a completed case by our company, nor does it represent the actual layout of any unit.
- Assume that the distance from the branch to the shower head is 3.2 meters for cold water and 3.2 meters for hot water; the distance to the wash basin is 2.1 meters for cold water and 2.1 meters for hot water; and the distance to the toilet for cold water is 3.0 meters.
- Reserve 10% of the length for cutting and splicing; this reservation is an assumption and not a company charging ratio or technical specification. The company's public prices are listed in "bits" or "items", and the price per meter of water pipe is not listed in this example.
How to calculate quantities
- Base route lengths: 3.2 + 3.2 + 2.1 + 2.1 + 3.0 = 13.6 m.
- Assumed allowance: 13.6 m × 10% = 1.36 m. Total: 13.6 + 1.36 = 14.96 m.
- This example rounds to 15 m for ordering discussions. Mark the endpoints, route, concealed or exposed sections, and connections on the sketch.
The preliminary water supply pipe size in this fictional sketch is 15 meters. You can use it to compare whether two quotes cover the same route, but you cannot use 15 meters to calculate the amount or confirm legal procedures.
The route and length may be changed on site due to beams, columns, existing pipelines, maintenance needs, finish restoration, and water procedures. Whether a water supply project is minor in nature must be judged based on the conditions and actual design of the Water Supplies Department; non-minor projects should be handled by a licensed plumber first. [2][5]
09
9. Strip-out and work by other trades: agree safety and reinstatement costs before starting
Pipes are often close to tiles, cement beds, vanities, suspended ceilings or wiring. Itemise exploratory opening, tile removal, chasing, protection, waste storage and removal, patch rendering, retiling and cleaning. Mark what can only be confirmed after opening up so the owner can distinguish the original scope from work on concealed old pipes, voids or seepage.
Use qualified personnel for external pipes, electrical work and working at height. The Labour Department's maintenance incident materials explain that external pipes must be secured and the area below cordoned off before removal. Electrical checks require proper isolation, lockout and warning notices by qualified workers.[4] This article does not provide DIY methods for removing pipes, modifying electricity, or cutting walls.
If you need to dismantle cabinets or remove household appliances during the project, first take photos and list the items to be retained, and stipulate removal, temporary storage, protection and damage treatment. The Consumer Council also pointed out that the demolition list, construction waste disposal and protection of common areas will affect the charges, and gas installations must be handled by qualified persons or companies.[3] By writing these conditions next to the demolition items, it is less likely that "not included" disputes will arise in the middle of the project.
- Before demolition, take photos of the current situation and list the retained items, locations to be protected, and the removable range.
- It is required to clearly list the clearing and transportation, loading and unloading, management arrangements, repairs and surface restoration.
- When work involving electricity, gas, exterior walls, aluminum windows, structures or heights, only appropriately qualified personnel will be assigned to handle it.
10
10. Closing up, handover and warranty: keep records that will help trace future leaks
Before sealing trenches, laying bricks or installing cabinets, complete inspections that are consistent with that stage and submit the results into saveable information: photos of water supply routes and switch locations, water connections and serviceable locations, photos of waterproofing construction scope and testing, sanitary ware models, product information, quotation changes and maintenance terms. When taking photos, add a description of the location, such as "hot and cold water angle valve behind the wash basin cabinet" instead of just a large number of photos of the project without a name.
At handover, run taps and the shower, flush the toilet and check the basin and floor drain. Confirm who tested supply and drainage, which joints remain accessible, and what dates and areas the records cover. Agree whom to contact and what evidence to provide if leakage, odour or blockage returns. Waterproofing, masonry or tile warranties do not automatically cover existing common pipework or other trades.
After completion, if moisture is found in the cabinet, the water meter is abnormal when no water is used, the wall is blistered, or watermarks or odors persist downstairs, reduce the relevant water use first, close identifiable switches under safe conditions, keep photos and time records, and then arrange for inspection. Do not cut walls, change gas or electricity by yourself, and do not use formaldehyde removal services as a guarantee of health or immediate occupancy; ventilation, product instructions, and professional evaluation when necessary cannot be omitted.
- Collect photos before sealing, test records, material receipts, as-built drawings or hand-drawn routes and maintenance terms.
- List unfinished items, responsible persons, completion deadlines and review methods in writing.
- If problems arise in the future, first retain evidence and isolate risks, and then arrange for inspection by appropriate professionals.
FAQ
7 practical questions answered
01If I just replace the toilet seat or wash basin, do I need to ignore the Buildings Department procedures?
Generally, the repair or replacement of sanitary equipment is an exempted project and does not require prior approval and consent from the Buildings Department; however, it must still comply with relevant structural, fire protection and drainage requirements.[1] The key is the actual scope: If the relevant drainage pipes in the kitchen, toilet or bathroom are modified at the same time, the Buildings Department points out that it must be handled according to the minor works control system, and a prescribed registered contractor must be appointed and a waterproof layer must be properly laid.[1] Therefore, first clearly indicate "replacement only" or "replacement with modification management" in the quotation, and then check it according to the unit, drawings and management office requirements.
02If I add a washing machine or dishwasher to the same unit, do I have to hire a licensed plumber?
You can't just generalize by "adding one bit". The Water Supplies Department lists some examples of expansion of existing water supply pipes and supply of new washing machines or dishwashers in the same residence, which can be classified as minor works, but must also meet the conditions of not changing the purpose or method of water supply, not dismantling and reinstalling water meters, not involving soldered copper pipes, and not requiring backflow prevention devices.[2] Non-minor works should first employ a licensed plumber and apply to the Water Authority, and have them carried out by a designated person.[2] It is safer to have the appliance information, existing water pipes and water outlet locations checked by a licensed plumber or the Water Supplies Department than to make your own judgment.
03Why is it that even if the quotation includes "full toilet plumbing", it may not include waterproofing or tile paving?
The connection of water supply and sanitary ware, water diversion, waterproofing, brick removal, backfilling, tiling and supply of sanitary ware are different processes. The company's public price list includes a complete set of hot and cold water pipes for the toilet, including shower, toilet, washbasin, water supply and pressure test. It is also stated that reconstruction of the hidden pipe and wall cutting are separately negotiated; toilet waterproofing, tile paving and sanitary ware installation are separate items.[5] When comparing prices, put the quantity, unit of account and uninclusive items in each column side by side, so that one water supply price will not be mistaken for the price of a complete bathroom renovation.
04Does Hong Kong require every flood test to last 24 or 48 hours?
The hours in one quotation are not a universal statutory requirement for Hong Kong residential projects. The company's 2026 standard bathroom waterproofing item specifies a 24-hour flood test, while a separate flood-test item allows 24–48 hours. Those durations describe the company's pricing scope.[5] The focus of the Consumer Council is that the quotation should specify the location, material, height and testing arrangements of waterproofing.[3] Homeowners should confirm the actual testing methods, observation locations, recording formats, and what to do if they fail before starting work, rather than just comparing the number of hours.
05If there is water seeping from the ceiling downstairs, does it have to be caused by a leak in my water supply pipe?
uncertain. Possible sources include water supply, drainage connections, floor waterproofing, pipe closings, sanitary ware edges, or problems related to common parts in the unit. The correct approach is to break the inspection into traceable steps, record when it occurs, what kind of water is related to it, and which location is affected, and then let the qualified contractor determine the scope of testing and repair. The Buildings Department advises households who suspect that there is an odor in the drain outlet or anti-siphon pipe, water seepage or cracks in the drain pipe to arrange for inspection and repair by a qualified contractor as soon as possible.[1] Jumping to conclusions or repeatedly applying glue before checking the source may delay the processing.
06Can an online estimate from saleable area serve as a formal plumbing quotation?
No. The quick calculator estimates three example schemes by saleable area. The basic renovation excludes full kitchen and bathroom reconstruction, replumbing, rewiring, fitted furniture and tile finishes. Multiplying saleable area by 3 gives only an approximate painted surface area.[5] Confirm each plumbing item separately, including fixture quantities, starting valve, exposed or concealed pipework, drainage, strip-out and reinstatement. Online estimates and enquiries are free. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order. Arrange this on WhatsApp 52437747.[5]
07As long as all the water is discharged and drained normally during the acceptance inspection, is it enough?
That is just a basic observation and is not a substitute for written scope and documentation. Also check the position of each switch, whether the route before sealing is visible in the photo, the test range of drainage and waterproofing, sanitary ware and material information, unfinished projects and maintenance boundaries. The Consumer Council recommends that waterproofing quotations list testing arrangements, and also reminds that subsequent installation work, leakage inspection deadlines and final arrangements should be written clearly in advance.[3] If there are intersecting processes involving electricity, gas, exterior walls or structures, the required documents should be completed and left by appropriately qualified personnel.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]Buildings Department: Alteration and addition works to domestic premises Accessed: 2026-10-21
- [2]Water Supplies Department: Minor works Accessed: 2026-10-21
- [3]Consumer Council: Don’t want to overspend again? Read the renovation quotation! Accessed: 2026-10-21
- [4]Labor Department: Brief analysis series on construction site accident cases—plumbing and electricity maintenance Accessed: 2026-10-21
- [5]HK Create Design: 2026 renovation project price list and public estimate instructions Accessed: 2026-10-21
- [6]Sika Hong Kong: SikaTop®-107 Seal HK Product Information Accessed: 2026-10-21