01
Why minor works requirements matter for window replacement
The Buildings Department's Minor Works Control System sorts work by nature, scale, complexity and safety risk. It lists 187 items: 58 in Class I, 68 in Class II and 61 in Class III.[1] Window repair, replacement and removal have separate minor works items.
The controls address the risk of an external sash or pane falling. The Audit Commission reported 445 window-fall incidents from January 2017 through December 2024. Six incidents caused one death and seven injuries.[7] The system requires the appropriate registered contractor to follow prescribed procedures and record the work, supporting quality and traceability.
For window work within the Minor Works Control System, the owner or agent appoints the appropriate registered contractor and, for Class I, a prescribed building professional. Window work outside the applicable simplified or exempted scope can require approved plans and Buildings Department consent to commence.[4][1] The required appointments and submissions should be in place for the actual scope.
Following the system provides a record of the work for prospective purchasers, solicitors and lenders. If the window later requiresMandatory window inspection, the qualified person will have records to review. Agreeing the class and documents early also makes it easier to schedule the start.
- Which minor works item covers my window replacement?
- Verify the contractor's minor works registration
- Retain copies of all submitted documents
- If told no submission is needed, ask which provision applies
You can swipe left or right on your phone to view the complete table.
| Item | Grade | Nature of the work | Main conditions |
|---|---|---|---|
| 1.60 | Level I | Window repair or replacement to the original design | Window repair or replacement outside the scope of items 2.8 and 3.6 [2] |
| 2.8 | Level II | Repair or replacement of windows | At over 3.5m and up to 100m, span at most 6m with work on the main frame or a sub-frame over 1.2m. Above 100m, span at most 6m, external opening at most 6m² and shorter side at most 1.8m [2] |
| 3.6 | Level III | Repair or replacement of windows | Highest point up to 3.5m and span up to 6m, or over 3.5m and up to 100m with work on a sub-frame no longer than 1.2m only [2] |
| 2.9 | Level II | Window removal | Window height up to 6m and outside item 3.7 [2] |
| 3.7 | Level III | Window removal | Highest point no more than 3.5m above ground [2] |
| 1.6/1.15/2.13/2.14/3.11 | Depends on the item | Remove or alter an existing protective barrier | Changing a low sill wall or balcony railing may involve [2][4] |
| 2.5 | Level II | Like-for-like repair or replacement of a protective barrier | Protective barriers other than reinforced concrete external walls or brick walls [2][4] |
The registered minor works contractor or prescribed building professional checks the actual height, span and frame elements against the full item criteria. This table summarises the Buildings Department guidance. [2][4]

02
How are window works classified?
For Class II item 2.8 at a height over 3.5m and up to 100m, the structural element span must be at most 6m and work must involve a main frame or a sub-frame longer than 1.2m. Above 100m, the span must be at most 6m, the opening at most 6m² and its shorter side at most 1.8m. Check the complete item conditions.[2]
Class III item 3.6 can cover a highest point up to 3.5m above ground and a span up to 6m. Where the highest point is over 3.5m and up to 100m, the work must involve only a sub-frame no longer than 1.2m. Check the full item conditions.[2] Class I item 1.60 covers like-for-like repair or replacement outside the scope of items 2.8 and 3.6, subject to its item conditions.[2]
Window removal has separate items 2.9 (Class II) and 3.7 (Class III). Item 3.7 covers qualifying windows with their highest point no more than 3.5m above ground.[2] Altering a window, low sill wall, balcony railing or exterior wall that acts as a safety barrier may involve items 1.6, 1.15, 2.13, 2.14 or 3.11. Like-for-like repair or replacement of a barrier may fall under Class II item 2.5.[2][4]
Complete replacement in an upper-floor flat often involves its main frame and may fall under Class II item 2.8. A low-level window or short sub-frame repair may fall under Class III. The contractor should take the actual measurements and record the classification in the quote.
- Measure the height of the window's highest point above ground
- Confirm the span and whether the work involves a main frame or only a sub-frame
- Does the work alter the sill wall or barrier?
- Record the minor works item number in the quotation


03
Who needs to be appointed?
Class I requires a prescribed building professional and a prescribed registered contractor. Classes II and III require a prescribed registered contractor.[1] Prescribed building professionals include authorized persons and registered structural engineers as applicable. Prescribed registered contractors can include registered general building contractors or registered minor works contractors within their scope.
Use the Buildings Department's register to check the contractor's number and the classes, types or items covered. Different minor works registrations allow different window works. Ask for the registration number with the quotation.
Under the Mandatory Window Inspection Scheme, qualified persons can include authorized persons, registered structural engineers, registered inspectors, registered general building contractors and registered minor works contractors registered for the relevant window work, subject to the applicable requirements.[8] The inspection role is separate from the replacement contract. The same firm may act only where it holds the relevant qualifications for both.
A renovation company may work with a registeredAluminium windows partners who make the submissions. At HK Create Design, the window specialist handles the window work, the relevant registered contractor handles statutory submissions and we coordinate associated works. The quote should name the party responsible.
- Identify the registered contractor responsible for filing
- Verify registration on the Buildings Department website
- Class I also requires a prescribed building professional
- Identify responsibilities in the quotation
「Window replacements generally need the relevant registered contractor and minor works submissions. Keep completion records for future sale and insurance enquiries.」
04
Submission deadlines — seven days and 14 days
For Classes I and II, the prescribed documents must be lodged at least seven days before work. Class III has no pre-commencement filing requirement.[1] All three classes require completion documents within 14 days.[1]
For Class II work, allow at least seven days between submitting the notice and starting on site. Missing the deadline can affect both the contractor and owner. Submit early so the notice period can overlap with frame and glass manufacture.
Ask for the completion submissions and keep them with the quotation, invoice and completion photos. Records can be useful for a future sale or mandatory inspection. The filing deadline is within 14 days after completion.
If an initial sash replacement becomes a frame replacement, the works class may change. Before proceeding, have the contractor reassess the scope and determine whether a revised submission is required.
- Allow at least seven days for Class I and II pre-start filing
- File within 14 days after completion
- Request copies of the submissions
- Reassess the class if the scope changes
Example 1: calculating submission dates before starting and after completion
Assumptions
- Illustrative Class II item 2.8 replacement scheduled to start on 14 December 2026.
- Assumed completion date: 16 December 2026.
- In the relevant Class I or II example, file at least seven days before work and within 14 days after completion. [1]
How to calculate quantities
- Pre-start example: 14 December minus seven days = 7 December, the latest submission date.
- Completion example: 16 December + 14 days = 30 December, the latest date for submission.
- Allow a buffer. In this example, prepare documents by 4 December before the weekend.
In the example, the pre-start documents are due by 7 December and completion documents by 30 December.
Use Buildings Department requirements to calculate the actual filing dates with the contractor. Recalculate if the start date changes. [1]

05
Design limits when changing windows
New windows must meet statutory requirements for natural lighting, ventilation and fire safety as well as the technical installation requirements.[2] Keep the required window area and ventilation when planning air conditioners or furniture. Changing all opening sections to fixed panes can leave the room without adequate ventilation.
The Buildings Department requires protective barriers generally at least 1.1m above finished floor level at openings in external walls above the ground floor.[2] Lowering the wall below a window to create floor-to-ceiling glazing alters a safety barrier. A different minor works item or prior approval may apply. Households withOlder residents or children should pay particular attention to this.
The Buildings Department states that a green balcony or utility platform exempted from gross floor area calculations must not be enclosed.[2] Glazing in a balcony to turn it into indoor space may contravene the approved design and require reinstatement.
The deed of mutual covenant and management rules may specify the frame colour, glass colour or opening style. Check before ordering replacements.
- Avoid narrowing or permanently closing a window without assessment
- Assess the low wall below a window before proposing removal
- Keep exempted green balconies open
- Ask management about external appearance requirements
You can swipe left or right on your phone to view the complete table.
| compare | Level I | Level II | Level III |
|---|---|---|---|
| Complexity and safety risk | High [1] | Moderate [1] | Low [1] |
| Number of projects | 58 items [1] | 68 items [1] | 61 items [1] |
| Who must be appointed? | Prescribed building professional and prescribed registered contractor [1] | Prescribed registered contractor [1] | Prescribed registered contractor [1] |
| Pre-commencement submission | At least seven days before commencement [1] | At least seven days before commencement [1] | No pre-start submission required [1] |
| Submit after completion | Within 14 days [1] | Within 14 days [1] | Within 14 days [1] |
| Typical window replacement scenarios | Window works beyond items 2.8 and 3.6 | Many complete window replacements in flats on upper floors | Low-level window or replacement of a short sub-frame only |
The common replacement scenarios are indicative. The appointed contractor must confirm the class for the actual window. [1]

06
What owners should ask about working at height
Window replacement is high-risk. Where there is a risk of a fall of 2m or more, the employer must ensure suitable fall prevention and a safe system of work. The Labour Department calls for task-specific risk assessment and suitable work platforms.[3]
The Labour Department's window installation safety alert specifies platforms at least 400mm wide, top rails 900–1,150mm high, intermediate rails 450–600mm and toe boards at least 200mm. A competent person should inspect the platform before first use and at intervals of no more than 14 days. Where a platform is not reasonably practicable and the hazard cannot be avoided, provide a suitable harness with continuous attachment to a secure anchor, independent lifeline or fall-arrest system. Workers should wear helmets with chin straps.[5]
The Labour Department's guidance to owners and tenants identifies window replacement as high-risk work. Workers should hold the required construction safety training card and be provided with suitable platforms for external work, such as a truss-out scaffold.[9] Ask the contractor which working platform will be used and how workers, glass and people below will be protected if another access arrangement is proposed.
Safe access and protection affect the price and programme. Check what they include before comparing quotes. We itemise third-party and employees' compensation insurance on whole-flat projects. For small jobs, the relevant labour rates include it.[11]
- Ask about the work platform or truss-out scaffold
- Workers need the required construction safety training card
- Confirm insurance
- Provide protection below the work area during removal
07
From measurement through handover
First, the specialist checks the frames for distortion, hinge fixings for corrosion and the perimeter for leaks, and measures openings and height above ground. The Buildings Department lists visible defects that should prompt further assessment.[4]
Second, obtain a written quote covering each window's dimensions, frame, glazing, hardware, expected class, filing responsibility, safety measures and perimeter repairs. Third, confirm the order and register the working hours with management. Fourth, complete the pre-start submission where required, at least seven days in advance for Classes I and II.[1]
Fifth, the contractor removes the old glazing and frame and installs, aligns and secures the replacement system. Sixth, the contractor completes the weather seals, interior junctions, rendering and painting around the opening.Window perimeter sealantSee our window perimeter sealing guide for more detail.
Step 7 is handover inspection. Step 8 is filing completion documents within 14 days.[1] Check that the quote is detailed, the applicable submissions are made and the completed work passes the agreed handover inspection.
- Inspection and measurement
- written quotation
- Register with building management
- Pre-commencement submission
- Remove old equipment and install the replacement.
- Seal joints and make good
- Acceptance
- Completion submission
Example 2: which class applies to each of three windows?
Assumptions
- Window A: 12th-floor living room, highest point about 36m above ground, 2.4m span, complete replacement including the main frame.
- Window B: rear window of a ground-floor shop, highest point 3.2m above ground and a 1.5m span.
- Window C: small 20th-floor bathroom window, replacing only one 1.0m sub-frame.
- Assessment based on the Buildings Department's published criteria. [2]
How to calculate quantities
- A: over 3.5m and up to 100m, span at most 6m and work includes the main frame — Class II item 2.8.
- B: highest point at most 3.5m and span at most 6m — Class III item 3.6.
- C: over 3.5m and up to 100m, with work limited to a sub-frame no longer than 1.2m — Class III item 3.6.
Window A is Class II and needs notice at least seven days before commencement. B and C are Class III and do not need pre-start notice. All three require completion documents within 14 days. [1]
These examples apply published criteria. A registered contractor must verify the actual classification on site. [2][1]

08
Professional and official guidance
Owners are responsible for maintaining their windows. The Buildings Department notes a falling window caused by disrepair may lead to prosecution under section 4B of the Summary Offences Ordinance, with a fine of HK$10,000 and six months' imprisonment, as well as possible civil claims.[8]
The Buildings Department requires a repair standard at least equal to the original design. For a replacement hinge, use at least three appropriate rivets or screws. Stainless steel hinges require compatible stainless steel fixings.[8] These requirements also apply to hardware fitted during window replacement.
The Buildings Department advises arranging prompt inspection by a qualified person if a window shows defects, with necessary repairs by a registered contractor.[4] Of 445 reported window-fall incidents in 2017–2024, the Audit Commission found that 295, or 66%, occurred in buildings that had not been selected for mandatory inspection at the time.[7] Even a building without an inspection notice can have defective windows.
The Labour Department identifies window replacement at height as work requiring risk assessment, safe access and suitable work platforms.[3] These requirements form the basis for planning and recording window replacement.
- Owner's legal responsibility
- Repairs must meet or exceed the original design standard
- Inspect windows regularly even before receiving a statutory notice
- Provide a suitable work platform for work at height
You can swipe left or right on your phone to view the complete table.
| steps | What is it for? | person in charge | You need to obtain |
|---|---|---|---|
| 1. Inspection | Inspect frames, hinges and signs of leakage around windows | Window specialist or qualified person | Photos and inspection findings |
| 2. Site measurement and quotation | Measure the opening and confirm the specification | Contractor | Written quotation stating specifications and works class |
| 3. Register with building management | Working hours and insurance | Owner and contractor | Approval or registration record |
| 4. Pre-commencement submission | Class I / II — at least seven days before commencement [1] | Registered contractor, plus a prescribed building professional for Class I | Copies of submission documents |
| 5. Remove old windows and install new ones | Work-at-height safety measures [5] | Contractor | Site photographs |
| 6. Seal joints and make good | Exterior weather seal, interior mould-resistant sealant, rendering and paint around the frame | Contractor | Finished photos |
| 7. Handover inspection | Opening, locking, hinge fixings and surrounding finishes | Owner | Handover inspection record |
| 8. Completion submission | Within 14 days [1] | Registered Contractor | Copy of completion submission |
The written quote and agreed schedule confirm timing. [1][5]
09
Common compliance problems when replacing windows
One common problem is omitting the required submission. Missing records may be discovered during a property transaction or a Buildings Department inspection.
Misclassifying Class II work as Class III can result in the required pre-start filing being missed.[1] Ask the contractor to state the minor works item and basis for the classification in the quotation.
Another mistake is changing the design during replacement. Removing a low sill wall, enclosing a balcony or narrowing an opening can involve a different works item or prior approval,[2] Assess this separately from ordinary window replacement.
Another problem is the absence of safety measures. The Labour Department identifies window replacement as high-risk work,[9] Failure to provide safe access and fall protection can have serious consequences for workers and owners. Another common issue is realizing after completion that the contractor never lodged the required documents.
- Ask who will make the submissions
- Record the minor works item number in the quotation
- Check changes to the original design separately
- Insist on safe working arrangements
- Ask for the documents at completion
Example 3: budgeting for work around a newly replaced window
Assumptions
- Aluminium window pricing is confirmed by written quotation.
- Around 30 sq ft of rendering at B01, HK$43 per sq ft, subject to the HK$2,350 minimum. [11]
- Local mould treatment and repainting of one internal wall beside the window, E05 at HK$1,250 per surface. [11]
How to calculate quantities
- Rendering: 30 × HK$43 = HK$1,290. The HK$2,350 minimum applies.
- Painting: one surface × HK$1,250 = HK$1,250.
- Associated works total: HK$2,350 + HK$1,250 = HK$3,600.
Associated making good around HK$3,600, plus the separately quoted aluminium windows.
Where other rendering work is carried out at the same time, the minimum may apply to the combined scope. Confirm the measured area. [11]
10
Handover and completion records
At handover, check from a safe indoor position that each sash operates and locks securely. Have the installer demonstrate that each new hinge has at least three appropriate, compatible rivets or screws.[8] Check the glass, glazing beads and gaskets. Missing aluminium beads that retain a pane are one of the Buildings Department's listed signs of a defect.[4]
Inspect the continuous exterior weather seal and the smooth interior seal. Look for cracks in the surrounding render or paint. After heavy rain, check the sill and indoor wall for staining.
Retain the written quote, invoice, pre-start filing for Class I or II, completion submissions, finished photos and warranty terms.[1] Keep these records with the property documents.
Notify the contractor promptly in writing during the warranty period, with dated photos of any defect. Our work carries a one-year warranty subject to its written terms.
- Check each sash opens, closes and locks
- Hinge fixings
- All glazing beads present
- Seal the interior and exterior joints
- Keep the submission records
- Check again after rain


11
Costs and financial assistance
Separate the window system (profiles, glass and hardware), removal and disposal, safe access, filings and making good. The Buildings Department's indicative repair costs under the mandatory inspection scheme exclude a contractor's minor works submission fee. The Department does not charge a processing fee.[6] A quotation may therefore include a separate submission fee.
Associated rates include B01 cement-sand rendering at HK$43 per sq ft, minimum HK$2,350, and E05 local mould treatment and repainting at HK$1,250 per surface. Small jobs and rubble removal have a HK$2,000 minimum charge.[11] There is no single fixed aluminium window rate. Measurement and a written quote confirm the price. For an itemised explanation see ourAluminium window replacement pricesarticle.
The Buildings Department describes interest-free loans under the Integrated Building Rehabilitation Assistance Scheme of up to HK$50,000 per eligible flat for internal repairs including windows.[10] Check assistance eligibility and any application deadlines before starting work.
Repairs following a Mandatory Window Inspection Scheme notice are supervised by a qualified person and follow the notice's requirements. See our mandatory inspection guide for the separate process.
- Price the windows separately from the associated work
- A contractor may charge for preparing a submission
- Check assistance scheme eligibility first
- Follow the mandatory inspection notice for prescribed repairs
You can swipe left or right on your phone to view the complete table.
| Item | What may be included or charged separately | Remarks |
|---|---|---|
| New frame, sashes, glass and hardware | What should be included | Specify each unit separately. Aluminium windows require on-site measurement and a written quotation |
| Minor works submission documents | should be written clearly | The Buildings Department's indicative repair fees exclude the contractor's submission fee. The Department itself charges no processing fee. [6] |
| Working platform, truss-out scaffold and fall prevention | should be written clearly | Labour Department guidance on suitable work platforms [5] |
| Remove and dispose of existing windows | May be excluded | Small works and rubble removal — minimum HK$2,000 [11] |
| Rendering around the window | May be excluded | B01 HK$43 per sq ft, minimum HK$2,350 [11] |
| Interior painting around the window | May be excluded | E05 local mould treatment and repainting — HK$1,250 per surface [11] |
| Contractor’s site assessment | depending on | L04 HK$500, credited in full against a confirmed order [11] |
The company rates are preliminary references from HK Create Design's 2026 price list. The written quotation after site measurement confirms the cost. [6][5][11]

12
Follow up with the construction team
HK Create Design opened in 2019, and its team has over ten years of project experience. We coordinate the window specialist and registered contractor for installation and submissions, and our team handles associated rendering, waterproofing and painting. Work carries a one-year warranty under the written terms.
Measurement arrangements are as follows. On-site measurement is free through 31 December 2026 for two or more work items, with no deposit. After that, the HK$500 fee is credited against the order.
For a free quotation from the HK Create Design team, WhatsApp 5243 7747 or visit our Wong Tai Sin shop, Monday to Saturday, 10:00–18:00.
When booking, give the floor level, number and approximate sizes of windows, any mandatory inspection notice and special building management requirements.
- Prepare floor level and window details
- Check whether a mandatory window inspection notice applies
- Check building management rules
- WhatsApp Appointment
Advice from our tradespeople
「Window replacements generally need the relevant registered contractor and minor works submissions. Keep completion records for future sale and insurance enquiries.」
「Before work starts, we explain the expected class and time needed for submissions.」
「For high-level replacement, appoint an insured contractor and check the working platform and fall protection arrangements.」
FAQ
12 practical questions answered
01Do replacement aluminium windows always require formal plans?
Many replacements fall within the Minor Works Control System's simplified requirements. Window work outside the applicable minor works or other exemption may need Buildings Department approval and consent before starting.[4][1]
02Which class of minor works covers window replacement?
The height above ground, span and frame elements determine whether Class I item 1.60, Class II item 2.8 or Class III item 3.6 applies.[2]
03When must the documents be submitted?
For Classes I and II, file at least seven days before commencement. For all three classes, file completion documents within 14 days.[1]
04Who is responsible for submission?
Class I requires both a prescribed building professional and a prescribed registered contractor. Classes II and III require a prescribed registered contractor.[1]
05Is HK Create Design a registered minor works contractor?
Our window specialist and relevant registered contractor handle the window scope and filings. HK Create Design coordinates the surrounding repairs. The written quote identifies each party's responsibility.
06Can a low window sill be removed when replacing the windows?
Adjusting a protective barrier may fall under a different minor works item or require prior approval. Openings in external walls above ground-floor level generally require a barrier at least 1.1m high.[2]
07Can I enclose a balcony by adding windows?
Green balconies or utility platforms exempted from gross floor area calculations must not be enclosed.[2]
08Is scaffolding needed for window replacement?
The Labour Department requires suitable work platforms for work at height, such as a truss-out scaffold for external work. Where a suitable platform is not reasonably practicable and work there is unavoidable, a properly secured harness and fall-arrest arrangement are required.[5][9]
09Does the Buildings Department charge a processing fee?
The Buildings Department charges no processing fee, but a contractor may charge for preparing and lodging the submission.[6]
10Are my windows safe if I have not received an inspection notice?
The Audit Commission found that 295 of 445 window-fall incidents occurred in buildings that had not been selected for statutory inspection at the time.[7]
11Is an interest-free loan available for window replacement?
The Integrated Building Rehabilitation Assistance Scheme includes an interest-free loan of up to HK$50,000 per eligible flat for internal repairs, including windows.[10]
12Which documents should I keep after completion?
Quotation, invoice, copies of start and completion submissions, finished photos and warranty terms.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]Buildings Department: Introduction to the Minor Works Control System Accessed: 2026-11-03
- [2]Buildings Department: Minor works related to windows Accessed: 2026-11-03
- [3]Labour Department: Overview of Safety at Work at Height Accessed: 2026-11-03
- [4]Buildings Department: Important Notes about Window Safety Accessed: 2026-11-03
- [5]Labour Department: Work Safety Alert — fall from height while installing a glass window Accessed: 2026-11-03
- [6]Buildings Department: Mandatory Window Inspection Scheme: Cost Reference (July 2025 to June 2026) Accessed: 2026-11-03
- [7]Audit Commission: Management of Mandatory Window Inspection Scheme by the Buildings Department (Report No. 84, Chapter 4, summary) Accessed: 2026-11-03
- [8]Buildings Department: Frequently Asked Questions: Windows Maintenance Accessed: 2026-11-03
- [9]Labour Department: repair, maintenance, alteration and addition works — guidance for owners and tenants Accessed: 2026-11-03
- [10]Buildings Department — Integrated Building Rehabilitation Assistance Scheme Accessed: 2026-11-03
- [11]HK Create Design 2026 detailed project budget and public price list Accessed: 2026-11-03







