01
5 × 6 ft bathroom: how are the walls and floor measured?
Assume a bathroom 6 ft long and 5 ft wide, tiled 8 ft up every wall, with one 3 × 7 ft doorway and no other openings. This example illustrates measurement only. Actual tiling heights depend on the design and site measurements.[2]
You can swipe left or right on your phone to view the complete table.
| Itemised | How it is calculated | Indicative subtotal |
|---|---|---|
| Floor tiling area | 6 × 5 = 30 sq ft. D01: 30 × 78 = 2,340 | Apply the HK$3,250 minimum |
| Wall tiling area | 2 × (6 + 5) × 8 − 3 × 7 = 155 sq ft | D02:155×78=HK$12,090 |
| Combined cost of the two tiling items | 3,250+12,090 | HK$15,340 for these items only. The full bathroom is priced separately |
Assume D01 and D02 apply. This subtotal excludes finish tiles, removal, waterproofing, additional substrate work, sanitaryware, plumbing, electrical work and haulage. Measure recesses, windows, columns and areas with different tiling requirements separately. [2]
02
How does replacing tiles differ from renovating the whole bathroom?
Partial retiling requires treatment of junctions between new and old work. A full renovation also needs clearly defined fixture, waterproofing and plumbing scopes.
Partial replacement must address new-to-old junctions
Removing a few wall tiles differs from stripping a whole wall back to its substrate. Check whether neighbouring tiles can stay, how junctions will be repaired and whether matching stock is available. Different batches may vary in shade and pattern.
Check whether retaining sanitaryware will leave adequate access for the work
A vanity, toilet or shower screen can affect tile access and edge details. Decide for each whether to keep it in place, remove and reinstate it, or replace it. Itemise disconnection, plumbing connections and reinstatement.
03
Where in the bathroom tiling process should work pause for confirmation?
Agree on checkpoints and keep the required inspection records before covering the work.
Record the exposed substrate after removal
Photograph pipes, substrate damage and existing damp. If previously concealed issues emerge, set out the proposed treatment, cost and timing before confirming follow-on work. Get approval before covering the area.
Match testing and curing to the material system
Confirm the sequence for substrate preparation, forming falls, waterproofing and tiling against the existing construction and selected system. Test waterproofing at the appropriate stage and keep records. Product timings vary. Avoid treatingTile adhesive's water resistance as a completeWaterproofing.
Replace only the floor tiles and retain the wall tiles and vanity
Assumptions
- Assume wall-to-floor junctions and the area under the cabinet remain unverified.
Checks to make
- Record areas to be retained and existing damage.
- Ask the installer to assess what is feasible at the junctions.
- Compare what local treatment includes with the work in an expanded scope.
Confirm the junctions first. Floor area alone cannot price the entire job.
This hypothetical example illustrates planning only. It represents neither an actual job nor an agreed price or schedule. The site assessment determines the actual plan. [1]
You can swipe left or right on your phone to view the complete table.
| Confirmation checkpoint | What to retain | What to do while details remain uncertain |
|---|---|---|
| After removal | Photos of pipes, substrate and problem areas | Check the extent of additional treatment |
| Before covering | Waterproofing extent, junctions and test records | Confirm materials and testing arrangements |
| Before tiling | Layout, drain, doorway and fixture junctions | Confirm the finished levels work together |
| Before handover | Drainage, edge finishes, fittings and snagging list | List responsibilities and follow-up dates |
Editorial planning and handover checklist. Confirm the individual site and work sequence separately. [1]

04
Why check drainage falls, floor drains and doorways together?
Confirm drainage, floor drains and finished doorway levels together.
Assess drainage direction against the actual layout
The shower, threshold, cabinet feet and toilet affect the available floor and finishing details around the drain. Confirm the drainage design and acceptance checks before tiling, so the drain connection matches the finished level.
Check the finished height using actual dimensions
The new tile, bedding and substrate treatment all affect the finished level. Check the doorway against adjoining spaces. Confirm the appropriate personnel and procedures for pipe alterations, structural work or other regulated tasks.[1]
05
What should a bathroom tiling quotation break down?
Unsure whether you need retiling or a full renovation? Send an overview, the drain and doorway, and photos of the sanitaryware you want to retain so we can review the scope.
You can swipe left or right on your phone to view the complete table.
| range | What the quotation should answer |
|---|---|
| Strip-out | Which wall tiles, floor tiles or bedding to remove, and which parts stay |
| Substrate and drainage | How repairs, levelling or falls and drain connections will be handled |
| Waterproofing and testing | System used, extent, tests and records |
| Tiling and edge finishing | Finish tiles, bedding materials, cutting, grouting and external corners |
| Sanitaryware and waste haulage | Whether removal and reinstatement of fittings, carrying and waste disposal are included |
Editorial planning and handover checklist. Confirm the individual site and work sequence separately. [1]
06
Inspect more than appearance at handover
Include both concealed-work records and surface-finish checks in the handover.
Keep a record of concealed work
Keep material names, treatment areas and test results. A finished photo cannot replace records made before the work was covered. Agree on progress photos before starting.
Check the finish against the agreement item by item
Inspect damage, joints, edges and fixture connections. Verify drainage and test results as agreed. Record suspected hollow tiles or leaks for the installer to assess and keep the surface intact.
Further budget and acceptance informationBathroom renovation costs, Inspection of plastering and tiling work, Masonry and tiling services.
Tiling is complete, but water use is still on hold
Assumptions
- Assume curing and applicable testing required for the selected materials are incomplete.
Checks to make
- Ask the installer to confirm the materials and remaining steps.
- Record when water use can resume, when fixtures will be reinstated and the handover conditions.
Return the bathroom to use under the conditions confirmed for the project. Finished tiling alone cannot establish that the shower is usable the same day.
This hypothetical example illustrates planning only. It represents neither an actual job nor an agreed price or schedule. The site assessment determines the actual plan. [1]
07
How much detail should we record about waterproofing and tiling materials?
Record each product name, model, location and the guidance version used by the installer. Waterproofing and tile adhesive serve different purposes. One photo of a branded product does not document the complete system.
Confirm the method, time and curing conditions against the selected products and work plan. Ask the contractor to record when water use and equipment installation can resume.
08
How do we manage during renovation if our flat has only one bathroom?
List when the toilet, basin and shower will each be out of use and verify alternatives and access. Phasing alone cannot guarantee that a bathroom is always available.
If applicableOlder residents, children or family members with limited mobility, agree on a workable temporary arrangement before setting a start date. Allow time for materials, testing and snagging.
09
Bathroom tiling enquiry checklist
Mark the items to remove and keep so everyone starts with the same scope.
Compare related workPartial kitchen and bathroom demolition.
- Bathroom overview and photos of the drain, doorway and pipes
- New tile dimensions and intended wall or floor use
- Retain, remove and reinstate, or replace the sanitaryware
- Past leaks, permitted work hours and household constraints
FAQ
6 practical questions answered
01Does grouting new tiles guarantee there will be no leaks?
No. Grouting and a complete waterproofing system are different.
02Can floor tiles be removed without affecting any wall edges?
Assess junctions and site conditions. All wall edges cannot be guaranteed to remain undamaged in advance.
03How soon after tiling can the bathroom be used?
Check actual materials, curing and testing. A single number of days cannot apply to every project.
04Can I replace just the few tiles that look worst?
Check removal and junction conditions, and allow for shade differences between old and new tiles.
05Can I keep the old vanity and replace only the floor tiles?
Check the cabinet base, wall-to-floor junction and work space, and identify inaccessible areas. Exposed floor area alone cannot define the full scope.
06If water pools at handover, should I open the tiles myself immediately?
Keep the finished surface intact. Record the location, time and conditions of use, then ask the contractor to inspect and address the issue against the agreed standards.
CHECK THE BASIS