What determines private flat renovation costs?
A cost per sq ft comes from the work chosen. First, will the kitchen and bathroom be redone? Second, do plumbing and electrical services need replacing? Third, how muchBespoke furnituredo you need? These three answers establish much of the initial budget.
Kitchen and bathroom work involves demolition, waterproofing, tiling, plumbing and sanitaryware. In this example, stripping and refitting one bathroom already costs over HK$50,000. Plumbing and electrical changes involve cutting chases, installing wiring and making good the walls. Custom furniture is priced by the linear foot: a 6 ft wardrobe alone costs close to HK$20,000. Painting and flooring cover larger areas, but their lower unit rates keep their share of the total down.
A light scope covers painting, floors and furniture. Mid-range adds the kitchen and bathroom. Full adds building services, ceilings and doors. Choose the scope based on condition and budget.
HK Create Design’s website includes a quick renovation budget calculator[2]for an initial estimate based on area and selected work. The example below itemises each cost.
- Will the kitchen and bathroom be redone?
- Do services need replacing?
- How much fitted furniture is required?
- Three scopes: light, mid-range and full refurbishment
You can swipe left or right on your phone to view the complete table.
| Grade | include | Example total | Approximate price per sq ft |
|---|---|---|---|
| Light refurbishment | Painting, SPC, wardrobes, TV unit, shoe cabinet and cleaning | HK$107,110 | HK$238 |
| Mid-range refurbishment | Light refurbishment plus kitchen and bathroom | HK$236,890 | HK$526 |
| Full refurbishment | Mid-range work plus distribution board, sockets, ceiling, spotlights, doors and insurance | HK$270,980 | HK$602 |
Based on HK Create Design’s published 2026 rates. Curtains, appliances and a separate 20% planning contingency excluded. [1]
- $107,110Light refurbishmentPaint floor furniture
- $236,890Mid-range refurbishmentAdd kitchen and bathroom refurbishment
- $270,980Full refurbishmentAdd services and ceilings
Examples based on HK Create Design's published 2026 rates.

02
Example: 450 sq ft two-bedroom private flat
The example is a 450 sq ft saleable, two-bedroom private flat around 30 years old, with one living room, kitchen and bathroom. Walls are mostly sound with some cracking, existing tiles are dated but level, wet areas are original, pipework shows some rust and the distribution board is old.
Buildings Department figures list around 8,721 private buildings aged 30–39 years, 6,751 aged 40–49 and 9,402 aged 50 or more[3]. Together, more than two thirds of the private buildings counted were at least 30 years old.
The example allows paintable walls and ceilings at about three times saleable area, or 1,350 sq ft. Floors excluding kitchen and bathroom cover 380 sq ft. Bathroom walls and floor allow 150 and 35 sq ft respectively, and the kitchen 120 and 40 sq ft. Actual quantities require measurement.
All prices use HK Create Design’s published 2026 rates[1], including labour and standard materials, with a HK$2,000 minimum order.
- 450 sq ft saleable area, two bedrooms, around 30 years old
- Paintable area around 1,350 sq ft
- Flooring area around 380 sq ft
- Illustrative quantities, subject to site measurement

03
1. Light refurbishment, around HK$107,110
Light refurbishment suits sound walls and serviceable wet areas where the aim is a refresh and more storage. The example includes local filling and repainting, SPC flooring, two wardrobes, a low TV unit, a tall entrance shoe cabinet,Post-renovation cleaning.
E02 local filling, moisture-resistant primer, sanding and painting costs HK$21 per sq ft on generally sound walls with local cracking[1]. At 1,350 sq ft the cost is about HK$28,350. If paint is peeling or walls have mould, investigate the cause and consider E01 stripping and skimming at HK$39 per sq ft[1], with a price difference of nearly twofold.
J01 SPC costs HK$60 per sq ft when laid over suitable existing tiles[1]. At 380 sq ft this is about HK$22,800. Overlaying avoids tile removal and reduces noise and waste. Two six-foot wardrobes (FUR05, HK$2,900/linear ft) total about HK$34,800, a six-foot low TV unit (FUR10, HK$1,250/linear ft) HK$7,500, and a two-foot tall entrance shoe cabinet (FUR12, HK$2,900/linear ft) HK$5,800[1].
Add L01 post-renovation cleaning and formaldehyde treatment at HK$16 per sq ft, around HK$7,200, plus one delivery at HK$660[1]. The light example totals around HK$107,110, about HK$238 per sq ft, with a typical programme of three to four weeks.
- E02 local preparation and repainting: HK$21 per sq ft
- J01 SPC: HK$60 per sq ft
- Furniture: wardrobes, TV unit and shoe cabinet
- Total around HK$107,110 (about HK$238 per sq ft)
「When customers ask for a price per square foot, we ask whether the kitchen, bathroom, plumbing and electrics need replacement. Changing those items can more than double the budget.」

04
2. Mid-range refurbishment, around HK$236,890
The mid-range scope adds kitchen and bathroom refurbishment to the light package. Consider it where original wet areas are worn, show signs of seepage or need new cabinets and sanitaryware.
Bathroom: A10 strip-out and clearance HK$9,950, followed by C02 Bathroom waterproofing at HK$4,850 including a 24-hour ponding test. D02 wall tiling: 150 sq ft × HK$78 = HK$11,700. D01 floor tiling: 35 sq ft × HK$78 = HK$2,730. G04 bathroom hot and cold pipework: HK$13,300. K06 installation of bathroom fittings: HK$5,650. FUR25 vanity with solid-surface top, 2 ft: HK$6,500. K05 shower screen installation: HK$860[1]. Bathroom total: about HK$55,540.
Kitchen: A09 removal and clearance HK$9,950. C03 waterproofing HK$4,300. D02 wall tiling, 120 sq ft, HK$9,360. D01 floor tiling, 40 sq ft, HK$3,120. G03 hot and cold pipework HK$13,300. FUR14 base cabinets, 8 ft, HK$10,400. FUR15 wall cabinets, 8 ft, HK$10,000. FUR20 quartz worktop, 8 ft, HK$9,600. H06 dedicated induction-hob circuit HK$3,350. K04 cooker-hood installation HK$860[1]. Kitchen total: about HK$74,240.
The HK$107,110 light package plus HK$129,780 for the kitchen and bathroom totals around HK$236,890, or HK$526 per sq ft, taking about six to eight weeks. Wet areas account for over half of this example.
- Bathroom example: around HK$55,540
- Kitchen example: around HK$74,240
- Mid-range example total: about HK$236,890
- About HK$526 per sq ft
Example: light refurbishment of a 450 sq ft flat
Assumptions
- Walls generally sound
- Existing tiles level
- Two 6 ft wardrobes, TV cabinet and shoe cabinet
How to calculate quantities
- E02:1,350 × HK$21 = HK$28,350
- J01:380 × HK$60 = HK$22,800
- FUR05:12 × HK$2,900 = HK$34,800
- FUR10:HK$7,500;FUR12:HK$5,800
- L01:450 × HK$16 = HK$7,200;FUR42:HK$660
- Total: HK$107,110
Example total around HK$107,110, about HK$238 per sq ft.
Failing or mould-affected walls need assessment and may require E01. Curtains and appliances excluded. [1]


05
3. Full refurbishment, around HK$270,980
The full example adds electrical work, ceilings and doors. It can suit an older flat with a fuse box, insufficient sockets or a planned lighting recess and spotlights.
Additional items include H09 replacement of theDistribution board replacementof the old fuse box with an MCB/RCD board at HK$6,800. Six H02 13 A sockets at 6 × HK$640 = HK$3,840. F01 suspended ceiling in living and dining areas, 150 sq ft × HK$51 = HK$7,650. Ten H08 spotlights at 10 × HK$310 = HK$3,100. Two L03 doors at 2 × HK$3,000 = HK$6,000. L02 third-party liability and employees’ compensation insurance: HK$6,700[1]. Total about HK$34,090.
Adding these items to the HK$236,890 mid-range example gives a full refurbishment of around HK$270,980, or HK$602 per sq ft. Allow roughly eight to ten weeks. If you needwhole-home rewiringor whole-flat pipe replacement (G05 from HK$22,300), allow for the additional cost[1].
The Buildings Department advises that structural alterations generally require appointment of an authorised person and prior approval, while certain specified works can follow the Minor Works Control System. Check planned layout and window-ledge changes before starting.[7][8]. Establish which items require applications before accepting the quotation.
- H09 distribution board replacement: HK$6,800
- F01 suspended ceiling — HK$51 per sq ft
- Full example total: about HK$270,980
- About HK$602 per sq ft
You can swipe left or right on your phone to view the complete table.
| Item | No. | Quantity × unit rate | Subtotal |
|---|---|---|---|
| Patch the surface, damp-proof, sand and paint | E02 | 1,350 sq ft × HK$21 | HK$28,350 |
| SPC flooring | J01 | 380 sq ft × HK$60 | HK$22,800 |
| Two wardrobes | FUR05 | 12 linear feet × HK$2,900 | HK$34,800 |
| Low TV cabinet | FUR10 | 6 linear ft × HK$1,250 | HK$7,500 |
| Full-height shoe cabinet in the entrance hall | FUR12 | 2 linear feet × HK$2,900 | HK$5,800 |
| Post-renovation cleaning | L01 | 450 sq ft × HK$16 | HK$7,200 |
| Delivery | FUR42 | 1 visit | HK$660 |
HK Create Design’s published prices for 2026. [1]


06
Why prices per sq ft need a scope comparison
The three budget levels range from HK$238 to HK$602 per sq ft, roughly a 2.5-fold difference. If someone quotes HK$400 per sq ft for renovating a private flat, ask whether it includes the kitchen and bathroom, plumbing and electrical work, and how much furniture. A per-square-foot figure only makes sense when the scope is clear.
Check the measurement basis: gross or saleable area, paintable wall and ceiling area, actual floor area and cabinet width in linear feet. Each line should state its code, quantity, unit and rate. The Consumer Council identifies twelve quotation checks including scope, material brands and models, quantities, payment arrangements and warranty[9].
The Consumer Council has called for tighter oversight of home renovation and highlighted disputes involving unclear quotations, delays and workmanship[10]. HK Create Design quotes each code, unit price and quantity, for example J01 SPC at 380 sq ft × HK$60, so you can compare or remove individual items.
Align two quotations item by item to see what is included or omitted before comparing the totals.
- Check the scope behind every price per sq ft
- Use a consistent measurement basis
- Consumer Council: twelve quotation checks
- Compare line by line
07
Labour costs: indicative day rates
Labour accounts for a substantial share. In July 2026, Census and Statistics Department average public-sector construction wages were about HK$1,538.8 per day for plumbers, HK$1,451.2 for electrical fitters, HK$1,322.7 for painters and HK$1,195.6 for gas installers[6]. Actual private renovation day rates vary by experience and workload. These figures give context for labour costs.
Clarify daywork and unit-price items. Most HK Create Design rates cover labour and standard materials, such as painting by sq ft or cabinets by linear foot. B06 masonry daywork is for small repairs at HK$2,700 per day, with materials charged at cost[1]. An agreed unit price and quantity make the cost less sensitive to the days needed to complete the agreed scope.
The Labour Department reminds owners and contractors to plan safe repair, maintenance, alteration and addition works, including electrical work and work at height[12]. Check employees’ compensation and third-party liability insurance. For a whole-home project, the L02 insurance allowance is HK$6,700[1].
- Plumber’s average public-sector daily wage: about HK$1,538.8 (July 2026)
- Painter’s average public-sector daily wage: about HK$1,322.7
- Supply-and-install unit rates help define the budget
- Allow insurance for whole-home projects

08
Costs that may sit outside the quotation
Allow for rubble. Hong Kong’s Construction Waste Disposal Charging Scheme charges for disposal by weight[11]. A11 rubble removal is listed at HK$4,200 per truckload[1]. The kitchen and bathroom strip-out price includes removal, while whole-home floor tile removal requires a separate truckload allowance.
Check management requirements for deposits, hours, lift protection and worker registration. Deposits are often refundable but still need upfront cash. In walk-up buildings FUR43 stair carry costs HK$300 per floor[1].
Leaks, cracked pipes or hollow surfaces may only become visible after strip-out. Consider a separate 20% contingency for site findings. This is the owner’s reserve.
Curtains, mattresses, sofas and appliances are usually outside the renovation quotation. For a 450 sq ft flat, buying them can add tens of thousands of dollars to the overall budget.
- A11 rubble removal: HK$4,200 per truckload
- Management deposit and working hours
- FUR43 walk-up stair carry: HK$300 per floor
- Set aside a 20% contingency in your own budget
- Curtains, mattresses and appliances priced separately
Example: upgrading from a mid-range to a full renovation
Assumptions
- Includes the HK$236,890 mid-range example
- Old fuse box
- Suspended ceiling and spotlights planned for the living room
How to calculate quantities
- H09:HK$6,800;H02:6 × HK$640 = HK$3,840
- F01:150 × HK$51 = HK$7,650
- H08:10 × HK$310 = HK$3,100
- L03:2 × HK$3,000 = HK$6,000;L02:HK$6,700
- Total additions: HK$34,090
- Full refurbishment: HK$270,980
Full refurbishment example: around HK$270,980, or HK$602 per sq ft.
Whole-flat rewiring, repiping and structural alterations excluded. Subject to site measurement and written quotation. [1]
- SPC over existing tilesSave on strip-out and rubble.
- Retain sound wet-area finishes where appropriateRetain sound tiles and replace cabinets or sanitaryware.
- Combine into one deliveryOne delivery charge.
- Standard heightUp to 2,400 mm.
- Work in stagesComplete wet trades before furniture.
- ENF board as standardNo extra upgrade charge.
09
Five ways to control cost
Lay SPC over sound, level tiles to avoid strip-out and retiling. If wet-area tiles and waterproofing are sound, replacing cabinets and fittings and renewing grout may cost less than a full rebuild.
Plan custom furniture together and consolidate the delivery. FUR42 costs HK$660 per trip[1]. Fourth, use standard sizes. Keeping wardrobes at or below 2,400 mm avoids the FUR04 surcharge of HK$100 per linear foot for every extra 100 mm[1].
Phase the work if needed. Complete services, wet areas and flooring while the home is empty. Furniture and lighting choices can follow, subject to power and fitting positions.
HK Create Design specifies ENF board as standard, with no additional upgrade charge.
- Lay SPC over existing tiles
- Full wet-area strip-out may not be needed
- One combined furniture delivery
- Keep wardrobe height within 2,400 mm
- Wet trades first, furniture later
You can swipe left or right on your phone to view the complete table.
| space | Item | No. | Subtotal |
|---|---|---|---|
| Bathroom | Strip-out and removal | A10 | HK$9,950 |
| Bathroom | Waterproofing and ponding test | C02 | HK$4,850 |
| Bathroom | 185 sq ft of wall and floor tiling | D01/D02 | HK$14,430 |
| Bathroom | Complete hot and cold pipework | G04 | HK$13,300 |
| Bathroom | Sanitary fittings, vanity and shower screen | K06/FUR25/K05 | HK$13,010 |
| kitchen | Strip-out and removal | A09 | HK$9,950 |
| kitchen | Waterproofing | C03 | HK$4,300 |
| kitchen | 160 sq ft of wall and floor tiling | D01/D02 | HK$12,480 |
| kitchen | Complete hot and cold pipework | G03 | HK$13,300 |
| kitchen | Cabinets, worktop, circuit and cooker hood | FUR14/15/20、H06、K04 | HK$34,210 |
Bathroom: HK$55,540. Kitchen: HK$74,240. [1]
10
Priorities for new, second-hand and older flats
The Rating and Valuation Department’s preliminary Hong Kong Property Review 2026 figures record about 24,260 private completions in 2024 and 18,450 in 2025. Its forecasts were about 16,980 for 2026 and 15,360 for 2027[4]. New completions, second-hand flats and older properties have different refurbishment priorities.
A new flat usually has new wet areas, services and flooring. Budgets can focus on fitted furniture, lights and a small number of additional sockets. The starting point is the handoverFlat inspectioninspection. Report defects to the developer before paying for private repairs. Good fitted furniture can be particularly valuable in a compact new flat.
For a second-hand flat around 10–30 years old, a light refresh may suffice if it is well maintained. Seepage, slow drains or cracked tiles may justify a larger scope. At viewings, check wet-area ceilings and window edges for water marks.
In flats over about 30 years old, investigate old fuse boxes, galvanised pipework and bathroom waterproofing before deciding the scope. Buildings Department figures identify around 9,402 private buildings aged 50 years or more[3]. Coordinating necessary services work in an older flat can reduce later disruption. Assess the condition before deciding whether the larger initial outlay is warranted.
For the same 450 sq ft, a new flat might need less than HK$100,000, while an older one could need over HK$200,000. Tell us the building age and current condition so we can give a more accurate estimate. If you are still choosing a property, bring your viewing photos. We can give an initial renovation estimate so you can factor the work into your offer.
- Around 18,450 private flats completed in 2025
- New flats: focus on furniture and lighting
- Second-hand flats: check for wet-area seepage
- Older buildings: assess whether to renew services together
- Strip-outKitchen, bathroom and old cabinets
- Plumbing and electrical workPipes, wiring and sockets
- Waterproofing and tilingTile after the ponding test
- Ceilings and paintingCeiling before walls
- Flooring and furnitureFinal cleaning

11
Private flat renovation programme
The light example takes around three to four weeks: painting in week one, flooring in week two, then furniture and cleaning in weeks three and four. Furniture can be made off site while painting proceeds.
A mid-range refurbishment typically takes six to eight weeks. Use the first two for kitchen and bathroom strip-out, pipework and waterproofing, including the 24-hour ponding test. Tile and fit sanitaryware in weeks three and four, then paint, fit flooring and install furniture.
A full refurbishment usually takes eight to ten weeks. Complete wiring and sockets before skimming and ceilings before painting. Typical order: strip-out, services, waterproofing, tiling, ceilings, painting, flooring, furniture and cleaning.
Observe the building’s permitted work hours and restrictions on Sundays and public holidays. A building might, for example, specify 9 am to 6 pm on weekdays. Tell the contractor the actual rules before confirming the schedule.
- Light refurbishment: 3–4 weeks
- Mid-range: 6–8 weeks
- Full refurbishment: 8–10 weeks
- Sequence: strip-out, services, waterproofing, tiling, ceiling, painting, flooring and furniture
12
Get a private flat renovation estimate from HK Create Design
HK Create Design has served Hong Kong private flats, public housing and village houses since 2019, with designers and tradespeople with over 15 years’ experience. Custom furniture includes floor plans, building-services drawings, furniture designs, VR renderings and production drawings.
WhatsApp 5243 7747 with plans, photos and the scope you have in mind for a free initial estimate, or try the online renovation budget calculator[2]. Free site measurement for two or more items of work runs through 31 December 2026. Otherwise L04 costs HK$500, credited in full against a confirmed order[1].
Visit Shop 16, G/F, Fu Yau Building, 61 Po Kong Village Road, Wong Tai Sin, Kowloon by appointment for board, tile and fitting samples. All work has a one-year warranty.
- WhatsApp 5243 7747
- Try the online budget calculator
- Free measurement for a limited period, then HK$500 credited against a confirmed order
- One-year warranty
Advice from our tradespeople
「When customers ask for a price per square foot, we ask whether the kitchen, bathroom, plumbing and electrics need replacement. Changing those items can more than double the budget.」
「“Start with the wet trades. After waterproofing we test for 24 hours before tiling. Painting and flooring come later to avoid rework.”」
FAQ
9 practical questions answered
01How much should I budget to renovate a 450 sq ft private flat?
Light example around HK$107,110, mid-range around HK$236,890 and full around HK$270,980. Subject to measurement and written quotation[1].
02How much does private flat renovation cost per square foot?
The examples range from about HK$238 per sq ft for light refurbishment to HK$602 for full renovation. Compare area rates only with their scope.
03How much does renovating one bathroom cost?
Bathroom strip-out, waterproofing, tiling, plumbing, sanitaryware installation and vanity: about HK$55,540 in this example[1].
04How much does a kitchen renovation cost?
The 8 ft kitchen example includes strip-out, waterproofing, tiles, plumbing, cabinets, quartz worktop and a dedicated electrical circuit for about HK$74,240[1].
05Does renovation of a private flat require an application?
Routine decoration generally does not need Buildings Department approval. Work affecting structure, partitions, window ledges or external walls may require approval or the Minor Works Control System[7][8].
06How do I compare two renovation quotations?
Align item descriptions, quantities, rates and materials. The Consumer Council recommends checking twelve aspects of renovation quotations[9].
07How do renovation budgets differ between new and older flats?
For the same 450 sq ft, a new flat may only need custom furniture and lighting, bringing the total below HK$100,000. If a flat over 30 years old needs a new distribution board, replacement pipes and a kitchen and bathroom renovation, the full-renovation example comes to about HK$270,980[1].
08How much contingency should I include in a renovation budget?
We suggest that owners hold a planning reserve of about 20%. It is separate from our charges and covers hidden plumbing, seepage or wall problems and items outside the quote such as curtains, mattresses and appliances.
09How long does a private flat renovation take?
Light refurbishment takes about 3–4 weeks, mid-range renovation 6–8 weeks and full renovation 8–10 weeks, subject to management's permitted working hours.
CHECK THE BASIS
Data and technical basis, sources can be verified
- [1]HK Create Design published 2026 rates and work item descriptions Accessed: 2026-11-03
- [2]HK Create Design 2026 quick renovation budget calculator Accessed: 2026-11-03
- [3]Buildings Department: 2026–27 Estimates reply on numbers of private buildings by age Accessed: 2026-11-03
- [4]Rating and Valuation Department, Hong Kong Property Review 2026 — preliminary findings Accessed: 2026-11-03
- [5]Housing Bureau: Housing in Figures 2026 Accessed: 2026-11-03
- [6]Census and Statistics Department: Average daily wages of workers on public construction projects, as reported by main contractors (July 2026) Accessed: 2026-11-03
- [7]Buildings Department — frequently asked questions on alterations and additions in domestic premises Accessed: 2026-11-03
- [8]Buildings Department: Minor Works Control System Accessed: 2026-11-03
- [9]Consumer Council: Renovation quotations should be detailed and teach you one by one in 12 major areas Accessed: 2026-11-03
- [10]Consumer Council: 4 proposed measures to strengthen regulation of the home renovation industry (21 February 2024) Accessed: 2026-11-03
- [11]Environmental Protection Department: Construction Waste Disposal Charging Scheme Accessed: 2026-11-03
- [12]Labour Department: repair, maintenance, alteration and addition works — guidance for owners and tenants Accessed: 2026-11-03